DC
/

OpenAI

What changed

AI lab · openai.com

OpenAI is linked to 19 tracked US data centers in 13 states as owner, operator, developer, tenant, utility or other party. Facilities with a disclosed figure add up to 3.28 GW online and 12.93 GW in the pipeline (floors: 19 of 19 report power). Every relationship cites its source.

View on map →
Follow

Get changes to OpenAI

How often

Double opt-in; one-click unsubscribe in every email. We store only your email and what you follow. More

Or subscribe in a feed reader: RSS / Atom

Cite this
Text
Datacenter Source. “OpenAI: US data center footprint.” /companies/openai. Data as of 2026-10-12. Accessed 2026-10-12.
BibTeX
@misc{datacentersource_openai_2026,
  title = {{OpenAI: US data center footprint}},
  author = {{Datacenter Source}},
  year = {2026},
  howpublished = {\url{/companies/openai}},
  note = {Data as of 2026-10-12; accessed 2026-10-12. Compiled from cited sources, including OpenStreetMap contributors (ODbL) and Epoch AI (CC BY 4.0)},
}

Please also cite the original source of any specific figure (linked beside it).

Linked facilities
19
States
13
Reported power online (floor)
3.28 GW
AnnouncedStated by the company or reported in the press; not yet backed by a filing or grid record.6%EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.94%
Reported planned capacity (floor)
14.73 GW
ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.22%EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.78%
This company's facilities:Download CSVJSONAPI docs

Floors, not totals: power sums only facilities with a reported or estimated figure (19 of 19), across all roles (a company can be tenant at one site and owner at another). “—” means not disclosed or not yet collected.

Loading map…

US footprint by state

Relationship graph

Derived from the ownership → operation → tenancy → workload chain at each shared facility, plus company-to-company relationships extracted from cited documents. Speculative links are excluded.

Workloads served by

  • Oracle5 sites · Confirmed
    OpenAI Stargate Abilene, OpenAI Stargate Michigan, OpenAI Stargate New Mexico
  • Microsoft3 sites · Likely
    Microsoft Fairwater Atlanta, Microsoft Fairwater Wisconsin, Microsoft Goodyear
  • SoftBank2 sites · Confirmed
    OpenAI Stargate Lordstown, OpenAI Stargate Milam
  • CoreWeave1 site · Likely
    CoreWeave Denton TX

Invests in

  • Oracle3 sites · Confirmed
    OpenAI Stargate Abilene, OpenAI Stargate Shackelford, OpenAI Stargate Wisconsin
  • Vantage Data Centers2 sites · Likely
    OpenAI Stargate Shackelford, OpenAI Stargate Wisconsin
  • Crusoe1 site · Confirmed
    OpenAI Stargate Abilene
FacilityRoleLocationStatusPower
OpenAI Stargate New MexicoEnd user NMUnder construction2.45 GW planned EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
OpenAI Stargate ShackelfordEnd user, Investor Abilene, TXUnder construction1.96 GW planned EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
OpenAI Stargate MichiganEnd user MIUnder construction1.4 GW planned ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.
OpenAI Stargate WisconsinEnd user, Investor WIUnder construction1.3 GW planned ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.
OpenAI Stargate MilamEnd user TXUnder construction1.2 GW planned EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
Microsoft Fairwater AtlantaEnd user LikelyFayetteville, GAOperating859 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
OpenAI Stargate AbileneEnd user, Investor Abilene, TXOperating + expanding590 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
Microsoft Fairwater WisconsinEnd user LikelyMount Pleasant, WIOperating + expanding442 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
CoreWeave Denton TXEnd user LikelyDenton, TXOperating + expanding367 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
OpenAI Stargate LordstownEnd user Warren, OHUnder construction300 MW planned EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
Microsoft GoodyearEnd user LikelyGoodyear, AZOperating263 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
Microsoft Project OsmiumEnd user SpeculativeCumming, IAOperating228 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
Coreweave HeliosEnd user SpeculativeAfton, TXOperating + expanding200 MW AnnouncedStated by the company or reported in the press; not yet backed by a filing or grid record.
CoreWeave Muskogee OKEnd user SpeculativeMuskogee, OKUnder construction181 MW planned EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
CoreWeave Lancaster Greenfield siteEnd user SpeculativePAUnder construction124 MW planned EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
CoreWeave Chester VAEnd user SpeculativeVAOperating + expanding114 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
CoreWeave Marble NCEnd user SpeculativeMarble, NCOperating91 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
CoreWeave Ellendale NDEnd user SpeculativeEllendale, NDOperating + expanding88 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
CoreWeave Dalton 1 & 2End user SpeculativeGAOperating40 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.