Virginia
Datacenter Source tracks 482 data centers in Virginia, including 7 AI campuses. Facilities that disclose power add up to 5.43 GW online and 628 MW in the pipeline. These are floors, not market size: 21% of facilities have a power figure. Largest operators by tracked MW: Amazon Web Services, Digital Realty and CloudHQ. 1.42 GW has been announced; 7.06 GW is documented as operational.
Follow
Get changes to Virginia
Or subscribe in a feed reader: RSS / Atom
Cite this
Datacenter Source. “Virginia data centers.” /states/VA. Data as of 2026-10-12. Accessed 2026-10-12.
@misc{datacentersource_state_VA_2026,
title = {{Virginia data centers}},
author = {{Datacenter Source}},
year = {2026},
howpublished = {\url{/states/VA}},
note = {Data as of 2026-10-12; accessed 2026-10-12. Compiled from cited sources, including OpenStreetMap contributors (ODbL) and Epoch AI (CC BY 4.0)},
}Please also cite the original source of any specific figure (linked beside it).
Online = operating sites; pipeline = remaining planned MW at sites under construction or planned. Percentages under each total show how much of it is backed by each evidence level. Average industrial electricity price: 10.07¢/kWh (EIA).
ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. filing, deed, permit or grid recordAnnouncedStated by the company or reported in the press; not yet backed by a filing or grid record. company or press claimEst.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. satellite, model or map inferenceHow levels are assignedAI data center capacity over time
Facility power at satellite-tracked AI campuses (Epoch AI timelines), quarterly
Construction pipeline by expected completion
MW from phases with a projected completion date
Power reality
Announced capacity vs. what grid records, construction and operation document. Facility-level sums; sources differ in coverage.
How to read this
Each bar sums one kind of evidence across facilities. Announced is the largest MW a company, utility, government or press source reported. Interconnection requests are MW in active large-load queue requests. Of the grid operators we ingest, only NYISO publishes these project by project. Contracted / approved means an executed interconnection agreement or a reported utility or power contract. Under construction and Operational come from construction records, imagery or operator reports.
The gap between announced and documented MW is capacity that has been claimed but not yet backed by a grid, construction or operating record. It is not proof a project won't happen. On-site generation is listed separately and never added to grid capacity. Method
Time to power puts each site's pending MW (announced minus operational) into a bucket by the midpoint of its evidence-based window. The window starts at the furthest documented stage and adds editorial ranges for what remains (e.g. announced: 2–5 yrs; land acquired: 2–4.5 yrs; planning / zoning: 1.75–4 yrs). Insufficient evidence means no dated stage evidence, not a delay. Windows are ranges, not forecasts. All ranges and rules
- Announced1.42 GW
- Interconnection requests—
- Contracted / approved—
- Under construction586 MW
- Operational7.06 GW
- < 1 year— · 0
- 1–2 years628 MW · 18
- 2–4 years— · 71
- 4+ years— · 0
- Insufficient evidence— · 10
Bucketed by the midpoint of each site's evidence-based window. Windows are ranges, not forecasts.
No large gaps in this scope.
Interconnection queues
Active requests to connect to the grid (PJM). Requests are applications, not commitments.
How to read this
A queue request asks a grid operator (ISO/RTO) to connect a new generator or large load to the transmission system. It then moves through studies (feasibility, system impact, facilities) before an interconnection agreement, construction and service. Filing is an application, not a commitment to build. Generation totals here are active requests only.
Why most aren't built: in the queue files we ingest, PJM: 42% of 1,441 requests withdrawn, 13% in service. These are shares of each published file, not completion rates. Queue sources
Data-center load requests are shown only where an ISO publishes them project by project (NYISO). Elsewhere, large loads go through utilities, and the ISO figures above (e.g. ERCOT's large-load tracking) are quoted from the operator's own documents.
Coverage
How much of this scope our sources describe. Low coverage means data isn't disclosed or not yet collected, not that there's nothing there.
Confirmed evidence = at least one fact about the facility itself from a filing, deed, permit, interconnection record, or government or utility record. Regional context (state prices, nearby plants, utility territory maps) doesn't count. Most facilities come from OpenStreetMap, which records that a building exists but rarely its power, owner or status.
| Markets | Facilities | With power | Confirmed |
|---|---|---|---|
| Northern Virginia | 432 | 23% | 97% |
| Richmond | 28 | 14% | 0% |
Markets
Click through to drill down
| Name | Facilities | Online | Pipeline | |
|---|---|---|---|---|
| Northern Virginia | 432 | 4.53 GW | 411 MW | |
| Richmond | 28 | 901 MW | 217 MW |
Largest operators & owners
Online + pipeline MW at linked facilities
- Amazon Web Services1.3 GW + 0 MW · 142 sites
- Digital Realty1.22 GW + 0 MW · 39 sites
- CloudHQ558 MW + 0 MW · 12 sites
- CyrusOne387 MW + 0 MW · 7 sites
- Vantage Data Centers287 MW + 0 MW · 8 sites
- Google286 MW + 0 MW · 10 sites
- QTS Data Centers249 MW + 0 MW · 23 sites
- CoreWeave114 MW + 83 MW · 1 sites
- COPT74 MW + 0 MW · 3 sites
- GI Partners66 MW + 0 MW · 1 sites
- Cologix51 MW + 0 MW · 2 sites
- H5 Data Centers0 MW + 42 MW · 1 sites
Largest customers & end users
Tenants and workload owners, where sourced
- Google DeepMind286 MW + 0 MW · 1 sites
Utility exposure
Most likely retail utility by location (approximate)
- Dominion Energy5.42 GW + 628 MW · 472 sites
- American Electric Power— · 1 sites
- Rappahannock Electric Coop— · 1 sites
- City of Harrisonburg - (Va)— · 1 sites
Grid operators (ISO / RTO)
By facility location
- PJM5.43 GW + 628 MW · 477 sites
Largest facilities
By online + pipeline MW; badge = evidence behind each figure
| Facility | Status | Online | Pipeline |
|---|---|---|---|
| STACK Infrastructure NVA02 | Operating + expandingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. | 118 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. | 369 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. |
| QTS Richmond 3 | Operating + expandingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. | 202 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. | 134 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. |
| QTS Richmond 1 | OperatingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. | 333 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. | — |
| Google Bristow | OperatingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. | 286 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. | — |
| CloudHQ LC1 | OperatingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. | 264 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. | — |
| QTS Richmond 2 | OperatingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. | 252 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. | — |
| CoreWeave Chester VA | Operating + expandingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. | 114 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. | 83 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. |
| CyrusOne NVA5 | OperatingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. | 194 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. | — |
| Digital Realty IAD39 | OperatingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. | 192 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. | — |
| CloudHQ LC2 | OperatingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. | 162 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. | — |
| Digital Realty IAD41 | OperatingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. | 135 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. | — |
| CloudHQ LC3 | OperatingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. | 132 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. | — |
| Vantage VA13 | OperatingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. | 91 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. | — |
| Vantage VA14 | OperatingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. | 91 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. | — |
| Digital Realty IAD42 | OperatingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. | 90 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. | — |
Facilities by status
- Operating331
- Operating + expanding3
- Under construction74
- Planned74
Counties
- Loudoun County 317 · 4.13 GW
- Prince William County 69 · 404 MW
- Fairfax County 34
- Henrico County 24 · 787 MW
- Mecklenburg County 18
- Manassas 9
- Chesterfield County 4 · 114 MW
- Fauquier County 3
- Lynchburg 1
- Culpeper County 1
- Frederick County 1
- Harrisonburg 1
Local impact
Water, on-site generation and air permits, incentives, regulatory events and large-load tariffs, where a source documents them. Counts are of sourced records, not of the state's totals.
0 M gal/day modeled at 1 site EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
Evaporative (cooling towers): 4 sites EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
14 sites with documented on-site generation (MW not reported)
47 air permits matched to tracked sites ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Synthetic Minor Emissions: 14 · Minor Emissions: 6 · 80% Synthetic Minor Emissions: 26 · Major Emissions: 1
Not yet collected
- Dominion Energy: GS-5 rate class for customers demanding 25 MW or more ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Virginia State Corporation Commission · Docket PUR-2025-00058 · Nov 25, 2025 · source
86 dated permit, rezoning or commission records