Microsoft Goodyear

OperatingEst.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Apr 27, 2026.AI campusCampusGoodyear, Maricopa County, Arizona

Microsoft Goodyear is an operating ai campus in Goodyear, Arizona. Operated or owned by Microsoft; used by Microsoft and OpenAI. Current power: 263 MW (estimated). Verification: verified operating. 12 cited sources.

70% profile completeness
52 claims from 12 sources
Last verified against sources: Oct 12, 2026
Newest dated evidence: Oct 12, 2026
Follow

Get changes to Microsoft Goodyear

How often

Double opt-in; one-click unsubscribe in every email. We store only your email and what you follow. More

Or subscribe in a feed reader: RSS / Atom

Cite this
Text
Datacenter Source. “Microsoft Goodyear.” /facilities/microsoft-goodyear-goodyear-az. Data as of 2026-10-12. Accessed 2026-10-12.
BibTeX
@misc{datacentersource_microsoft_goodyear_goodyear_az_2026,
  title = {{Microsoft Goodyear}},
  author = {{Datacenter Source}},
  year = {2026},
  howpublished = {\url{/facilities/microsoft-goodyear-goodyear-az}},
  note = {Data as of 2026-10-12; accessed 2026-10-12. Compiled from cited sources, including OpenStreetMap contributors (ODbL) and Epoch AI (CC BY 4.0)},
}

Please also cite the original source of any specific figure (linked beside it).

Current facility power
263 MW[1]
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Apr 27, 2026.Likelyestimated
Planned capacity
Not yet sourced
Floor area
Not yet sourced
Buildings (planned)
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Apr 27, 2026.Likelyderived
Capital cost / investment
$7.7B[1]
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Apr 27, 2026.Likelyestimated
First operational
Apr 24, 2023[1]
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Apr 27, 2026.Likelyderived

POWER & GRID

Time-to-power · verification · interconnection
Time to power
Energized — operating
High confidence
Project verification
Verified operating
Operation documented by satellite imagery and government record.
Current stage
Operational
Furthest stage with documented evidence
Utility · ISO
Salt River Project · None (non-RTO region)
Substation: On-site substation

Power reality

Announced
No record
Interconnection request
No record
Contracted / approved
No record
Under construction
No record
Operational
263 MW[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
Estimated from buildings observed operational
AI evidence brief
Summarizes only the evidence on this page. Answers citing anything else are rejected automatically.

Project verification

Development
  1. Announcedimplied by a later stage
  2. Land acquiredOct 30, 2024
    Government record
    • Oct 30, 2024 · Land acquisition / deed recorded[2]
    • Oct 30, 2024 · Deed recorded for parcel 500-07-984A (owner of record: Microsoft Corporation).[2]
    • Oct 12, 2026 · Owner of record in county parcel data[2]
  3. Planning / zoningimplied by a later stage
  4. Permittingimplied by a later stage
Grid interconnection
  1. Interconnection application
  2. Feasibility study
  3. System impact study
  4. Facilities study
  5. Interconnection agreement / service contract
Build & energization
  1. Financing
  2. Under constructionJun 21, 2021
    Model estimate · Satellite imagery
    • Jun 21, 2021 · Reported status: under construction[1]
    • Jun 21, 2021 · Construction start[1]
    • Jun 21, 2021 · Land clearing begins for Building 1.[1]
    • Apr 24, 2023 · Reported status: expanding[1]
  3. EnergizationApr 24, 2023
    Satellite imagery
    • Apr 24, 2023 · Building 1 operational. Based on interpolating satellite images from Sentinel-2 and Google Earth.[1]
    • Jan 16, 2025 · Building 2 operational. Based on interpolating satellite images from Sentinel-2 and Google Earth.[1]
    • Sep 1, 2025 · Building 3 and 4 operational. Based on interpolating satellite images from Sentinel-2 and Google Earth.[1]
  4. OperationalApr 24, 2023
    Satellite imagery · Government record
    • Apr 24, 2023 · Building 1 operational. Based on interpolating satellite images from Sentinel-2 and Google Earth.[1]
    • Jan 16, 2025 · Building 2 operational. Based on interpolating satellite images from Sentinel-2 and Google Earth.[1]
    • Sep 1, 2025 · Building 3 and 4 operational. Based on interpolating satellite images from Sentinel-2 and Google Earth.[1]
    • Oct 12, 2026 · County land use: Property use code 1507[2]

● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Government record, Model estimate, Satellite imagery.

Grid path

  1. facility
    Microsoft Goodyear
  2. substation
    On-site substation[1][6]
    Satellite imageryLikely
    1 substation outline traced inside the campus on satellite imagery; OSM maps Unnamed substation 0.4 km away
  3. transmission
    Palo Verde - Rudd 500KV[6]
    Proximity onlyUnverified
    Highest-voltage line mapped within 2 km (0.98 km away). Not confirmed as the supply path.
  4. utility
    Salt River Project[3]
    Service territoryLikely
    Retail service territory containing the site
  5. ISO / RTO
    None (non-RTO region)[5]
    Service territoryLikely
    Balancing authority: SRP
Substation capacity:
not published
Required upgrades:
not yet sourced
Congestion:
not yet sourced (no nodal price data)

Dashed boxes are based on proximity only and do not establish which asset serves the site.

Interconnection records

No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.

On-site & dedicated generation

No on-site, behind-the-meter or dedicated generation found in sources.

LOCAL IMPACT

Water · generation · incentives · regulation · rates

Water & cooling

Not yet collected: we haven't found a source for water use or the cooling type at this site. Know one? Add a source

On-site generation & air permits

Not yet collected: we haven't found a source for on-site generation or an air permit for this site. Know one? Add a source

Incentives

Not yet collected: we haven't found a source for tax abatements, PILOTs or other incentives for this project. Know one? Add a source

Regulatory events

Not yet collected: we haven't found a source for hearings, rezonings, permits or commission proceedings. Know one? Add a source

Utility & rates

Not yet collected: we haven't found a source for a large-load tariff or commission docket for Salt River Project. Know one? Add a source

Location & imagery

Mapped outline
Coordinates
33.41089, -112.36483
Address
14250 W Broadway Rd, Goodyear, AZ 85338[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Apr 27, 2026.Likely
County
Maricopa County
Photographs

No openly licensed ground-level photos matched to this site yet.

Ownership, operation & customers

  1. 1. Property owner of record
  2. 2. Owner / developer
  3. 3. Operator
    Not identified
  4. 4. Tenant / cloud
    Not identified
  5. 5. End customer / workload
Power supply
Utility:

Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.

All parties with evidence
Property owner of record
Microsoft[2]Confirmed
Owner
Microsoft[1]Confirmed
End user
Microsoft[1]Confirmed
OpenAI[1]Likely
Utility

Most likely retail provider among 11 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: Wapa-- Western Area Power Administration, Electrical Dist No8 Maricopa, Usbia-San Carlos Project, Gila River Indian Utility Authority (Gricua), Maricopa County M W C Dist #1, Buckeye Water C&D District, ….

Power (all fields)

Current facility power
263 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Apr 27, 2026.Likelyestimated

Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.

Current IT capacity
202 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Apr 27, 2026.Likelyestimated

Estimated IT load currently online, based on buildings observed operational.

Estimated annual consumption
1,613 GWh/yr[4]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Speculativeestimated

263 MW × 8,760 h × 70% utilization.

Planned capacity
Not yet sourced

Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.

Grid & electricity

ISO / RTO
None (non-RTO region)[5]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived

Outside all ISO/RTO footprints; balancing authority shown separately.

Balancing authority
SRP[3]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived

Control area of the containing utility territory.

Nearest mapped substation
Unnamed substation (230 kV)[6]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived

Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.

Distance to substation
0.4 km[6]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
Highest-voltage line nearby
500 kV[6]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived

Highest-voltage transmission line mapped within 2 km.

State avg. industrial price
9.35¢/kWh[8]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed

Arizona statewide average, July 2026.

State avg. commercial price
13.12¢/kWh[8]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed

Arizona statewide average, July 2026.

Generation within 50 km
11.7 GW[9]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jan 1, 202502.Confirmedderived

40 EIA-reported plants within 50 km.

Generation queued in county
1.12 GW[7]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Confirmedderived

5 active generation interconnection requests in Maricopa County: Solar + storage 1,100 MW, Solar 20 MW. Queued projects often don't get built.

Interconnection status
Not yet sourced
Contracted / committed power
Not yet sourced
Nearby infrastructureTypeDistanceVoltage / capacitySource
230 kV lineTransmission line0.37 km230 kV[6]
69 kV lineTransmission line0.37 km69 kV[6]
Palo Verde - Rudd 500KV · Arizona Public ServiceTransmission line0.98 km500 kV[6]
345 kV lineTransmission line1.11 km345 kV[6]
Jojoba - Kyrene 500KV · Arizona Public ServiceTransmission line1.16 km500 kV[6]
West Phoenix · Arizona Public Service CoPower plant (Natural Gas)19.5 km909 MW[9]
Agua Fria · Salt River ProjectPower plant (Natural Gas)21.3 km741 MW[9]
Ocotillo · Arizona Public Service CoPower plant (Natural Gas)42 km605 MW[9]
Red Hawk · Arizona Public Service CoPower plant (Natural Gas)45 km1 GW[9]
Palo Verde · Arizona Public Service CoPower plant (Nuclear)46.2 km3.94 GW[9]
Mesquite Generating Station Block 2 · Mesquite Power LLCPower plant (Natural Gas)46.9 km624 MW[9]
Mesquite Generating Station Block 1 · Salt River ProjectPower plant (Natural Gas)46.9 km620 MW[9]
Arlington Valley Energy Facility · Arlington Valley LLCPower plant (Natural Gas)49.3 km580 MW[9]
Unnamed substationSubstation0.4 km230 kV[6]
Unnamed substationSubstation0.52 km69 kV[6]
Largest queued generation in this countyFuelQueue statusMWSource
HARQUAHALA FLATS 2CAISO 2027Solar + storageIn study · proposed 2028-04400 MW[7]
HARQUAHALA SUNRISECAISO 1678Solar + storageIn study · proposed 2030-04300 MW[7]
VULCANCAISO 1534Solar + storageIn study · proposed 2027-12250 MW[7]
HARQUAHALA SUNRISE 2CAISO 2029Solar + storageIn study · proposed 2026-09150 MW[7]
AGUA CALIENTE SOLAR 2CAISO 1222SolarIn study · proposed 2016-1220 MW[7]

Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.

Construction & permitting

  1. Announced
    —
  2. Land acquired
    Oct 30, 2024[2]
  3. Permitting
    —
  4. Construction start
    Jun 21, 2021[1]
  5. First operational
    Apr 24, 2023[1]
  6. Expected completion
    —
Buildings (planned)
4[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Apr 27, 2026.Likelyderived

Count of building outlines traced on satellite imagery.

Buildings operational
4[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Apr 27, 2026.Likelyestimated
PhaseStatusAdded MWCompleted / expectedSource
Building 1operational53 MWApr 24, 2023[1]
Building 2operational52 MWJan 16, 2025[1]
Buildings 3–4operational158 MWSep 1, 2025[1]

Real estate

Official assessments
Assessor's value for a tax year
  • $357M[2]
    Full cash value · tax year 2027 · parcel 500-07-984A
  • $193.6M[2]
    Limited property value (taxable basis) · tax year 2027 · parcel 500-07-984A
  • $341.5M[2]
    Full cash value · tax year 2026 · parcel 500-07-984A
Recorded transactions
Sale prices from recorded deeds

None sourced yet

Model estimates
Our model — not an appraisal

None sourced yet

ParcelRecord ownerAcresZoning / useBuilding sq ftSource
500-07-984A
Maricopa County, AZ
MICROSOFT CORPORATION
1 MICROSOFT WAY REDMOND WA USA 98052
189.11CONTACT LOCAL JURISDICTION · Property use code 1507—[2]
Site area
189.1 acres[2]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Oct 12, 2026.Confirmed

Sum of county land area across parcels.

Land use
Property use code 1507[2]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Oct 12, 2026.Confirmed
Capital cost / investment
$7.7B[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Apr 27, 2026.Likelyestimated

Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.

Annual property tax
Not yet sourced
Nearby comparable transactions

Size

Parcel / land records
500-07-984A (Maricopa County)[2]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Oct 12, 2026.Confirmed
Floor area
Not yet sourced

Compute

Chip types
H100, B200[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Apr 27, 2026.Confirmed
Compute (H100-equivalents)
205,200[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Apr 27, 2026.Likelyestimated

What changed (last 3 years)

Follow this facility (RSS)
  • Current IT capacity
    40 MWApr 24, 2023[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→81 MWJan 16, 2025[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→202 MWSep 1, 2025[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
  • Current facility power
    53 MWApr 24, 2023[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→105 MWJan 16, 2025[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→263 MWSep 1, 2025[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
  • Buildings operational
    1Apr 24, 2023[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→2Jan 16, 2025[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→4Sep 1, 2025[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
  • Status
    Operating + expandingApr 24, 2023[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→OperatingApr 27, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.

Timeline

Construction start: Jun 21, 2021[1]
First operational: Apr 24, 2023[1]
  1. Jun 21, 2021[1]

    Land clearing begins for Building 1.

  2. Apr 24, 202353 MW facility power· 1 buildings operational[1]

    Building 1 operational. Based on interpolating satellite images from Sentinel-2 and Google Earth.

  3. Jan 16, 2025105 MW facility power· 2 buildings operational[1]

    Building 2 operational. Based on interpolating satellite images from Sentinel-2 and Google Earth.

  4. Sep 1, 2025263 MW facility power· 4 buildings operational[1]

    Building 3 and 4 operational. Based on interpolating satellite images from Sentinel-2 and Google Earth.

  5. Nov 12, 2025263 MW facility power· 4 buildings operational[1]

    Confirmation that Building 3 and 4 look complete.

  6. Apr 27, 2026263 MW facility power· 4 buildings operational[1]

    Foundations appear to be underway for Building 5 and 6, just north of Building 4.

  7. Oct 30, 2024[2]

    Deed recorded for parcel 500-07-984A (owner of record: Microsoft Corporation).

Buildings on this campus

5
  • PHX-10Operating · 246,800 sq ft footprint
  • PHX-11Operating · 249,500 sq ft footprint
  • PHX-12Operating · 247,800 sq ft footprint
  • PHX-13Operating · 247,800 sq ft footprint
  • PHX-14Operating · 247,800 sq ft footprint

All claims (provenance audit)

52
FieldValueSourceConfidenceAs ofStatus
NameMicrosoft Goodyear[1] Likely2026-04-27Shown
StatusUnder construction[1] derivedLikely2021-06-21Superseded / alternative
StatusOperating + expanding[1] derivedLikely2023-04-24Superseded / alternative
StatusOperating + expanding[1] derivedLikely2025-01-16Superseded / alternative
StatusOperating + expanding[1] derivedLikely2025-09-01Superseded / alternative
StatusOperating + expanding[1] derivedLikely2025-11-12Superseded / alternative
StatusOperating[1] derivedLikely2026-04-27Shown
Facility typeAI campus[1] derivedLikely2026-04-27Shown
Address14250 W Broadway Rd, Goodyear, AZ 85338[1] Likely2026-04-27Shown
Property owner of recordMicrosoftParcel 500-07-984A: MICROSOFT CORPORATION[2] Confirmed2026-10-12Shown
OwnerMicrosoftOwner: Microsoft[1] Confirmed2026-04-27Shown
End usersOpenAIUsers: OpenAI[1] Likely2026-04-27Shown
End usersMicrosoftUsers: Microsoft[1] Confirmed2026-04-27Shown
UtilitySalt River Projectterritory 16572: SALT RIVER PROJECT (POLITICAL SUBDIVISION, SALT RIVER PROJECT)[3] derivedUnverified2022Shown
Current facility power263 MW[1] estimatedLikely2026-04-27Shown
Current facility power53 MW[1] estimatedLikely2023-04-24Superseded / alternative
Current facility power105 MW[1] estimatedLikely2025-01-16Superseded / alternative
Current facility power263 MW[1] estimatedLikely2025-09-01Superseded / alternative
Current facility power263 MW[1] estimatedLikely2025-11-12Superseded / alternative
Current IT capacity202 MW[1] estimatedLikely2026-04-27Shown
Current IT capacity40 MW[1] estimatedLikely2023-04-24Superseded / alternative
Current IT capacity81 MW[1] estimatedLikely2025-01-16Superseded / alternative
Current IT capacity202 MW[1] estimatedLikely2025-09-01Superseded / alternative
Current IT capacity202 MW[1] estimatedLikely2025-11-12Superseded / alternative
Estimated annual consumption1,613 GWh/yr[4] estimatedSpeculative2026-10-12Shown
ISO / RTONone (non-RTO region)[5] derivedLikely—Shown
Balancing authoritySRP[3] derivedLikely—Shown
Nearest mapped substationUnnamed substation (230 kV)way/1091128477[6] derivedLikely2026-09-28Shown
Distance to substation0.4 km[6] derivedLikely2026-09-28Shown
Highest-voltage line nearby500 kV[6] derivedLikely2026-09-28Shown
Generation queued in county1.12 GW[7] derivedConfirmed2026-10-12Shown
State avg. industrial price9.35¢/kWh[8] Confirmed2026-07Shown
State avg. commercial price13.12¢/kWh[8] Confirmed2026-07Shown
Generation within 50 km11.7 GW[9] derivedConfirmed202502Shown
Buildings (planned)4[1] derivedLikely2026-04-27Shown
Buildings operational4[1] estimatedLikely2026-04-27Shown
Buildings operational0[1] estimatedLikely2021-06-21Superseded / alternative
Buildings operational1[1] estimatedLikely2023-04-24Superseded / alternative
Buildings operational2[1] estimatedLikely2025-01-16Superseded / alternative
Buildings operational4[1] estimatedLikely2025-09-01Superseded / alternative
Buildings operational4[1] estimatedLikely2025-11-12Superseded / alternative
Site area189.1 acres[2] Confirmed2026-10-12Shown
Capital cost / investment$7.7B[1] estimatedLikely2026-04-27Shown
Parcel / land records500-07-984A (Maricopa County)[2] Confirmed2026-10-12Shown
Assessed value (official)$357M[2] Confirmed2027Shown
Land useProperty use code 1507[2] Confirmed2026-10-12Shown
Compute (H100-equivalents)205,200[1] estimatedLikely2026-04-27Shown
Chip typesH100[1] Confirmed2026-04-27Shown
Chip typesB200[1] Confirmed2026-04-27Shown
Land acquiredOct 30, 2024[2] derivedConfirmed2026-10-12Shown
Construction startJun 21, 2021[1] derivedLikely2026-04-27Shown
First operationalApr 24, 2023[1] derivedLikely2026-04-27Shown