Google DeepMind
What changedAI lab · deepmind.google · also matched as DeepMind
Google DeepMind is linked to 11 tracked US data centers in 8 states as owner, operator, developer, tenant, utility or other party. Facilities with a disclosed figure add up to 2.56 GW online and 3.11 GW in the pipeline (floors: 11 of 11 report power). Every relationship cites its source.
Follow
Get changes to Google DeepMind
Or subscribe in a feed reader: RSS / Atom
Cite this
Datacenter Source. “Google DeepMind: US data center footprint.” /companies/google-deepmind. Data as of 2026-10-12. Accessed 2026-10-12.
@misc{datacentersource_google_deepmind_2026,
title = {{Google DeepMind: US data center footprint}},
author = {{Datacenter Source}},
year = {2026},
howpublished = {\url{/companies/google-deepmind}},
note = {Data as of 2026-10-12; accessed 2026-10-12. Compiled from cited sources, including OpenStreetMap contributors (ODbL) and Epoch AI (CC BY 4.0)},
}Please also cite the original source of any specific figure (linked beside it).
Floors, not totals: power sums only facilities with a reported or estimated figure (11 of 11), across all roles (a company can be tenant at one site and owner at another). “—” means not disclosed or not yet collected.
Relationship graph
Derived from the ownership → operation → tenancy → workload chain at each shared facility, plus company-to-company relationships extracted from cited documents. Speculative links are excluded.
Workloads served by
- Google1 site · ConfirmedGoogle Bristow
| Facility | Role | Location | Status | Power |
|---|---|---|---|---|
| Goodnight | End user Speculative | Claude, TX | Under construction | 1.29 GW planned EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. |
| Google Fort Wayne | End user Speculative | Fort Wayne, IN | Under construction | 1.04 GW planned EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. |
| Google Pryor (North) | End user Speculative | Pryor, OK | Operating | 442 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. |
| Google New Albany | End user Speculative | New Albany, OH | Operating | 400 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. |
| Google Columbus | End user Speculative | Columbus, OH | Operating + expanding | 364 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. |
| Google Cedar Rapids | End user Speculative | IA | Under construction | 314 MW planned EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. |
| Google Bristow | End user | Bristow, VA | Operating | 286 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. |
| Google Council Bluffs (East) | End user Speculative | Council Bluffs, IA | Operating | 284 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. |
| Google Omaha | End user Speculative | Omaha, NE | Operating + expanding | 284 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. |
| Google Papillion | End user Speculative | NE | Operating | 284 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. |
| Google Storey County | End user Speculative | NV | Operating + expanding | 214 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. |