Google Omaha
Google Omaha is an operating + expanding ai campus in Omaha, Nebraska. Operated or owned by Google. Current power: 284 MW (estimated). Planned capacity: 474 MW (estimated). Verification: verified operating. 10 cited sources.
Follow
Get changes to Google Omaha
Or subscribe in a feed reader: RSS / Atom
Cite this
Datacenter Source. “Google Omaha.” /facilities/google-omaha-omaha-ne. Data as of 2026-10-12. Accessed 2026-10-12.
@misc{datacentersource_google_omaha_omaha_ne_2026,
title = {{Google Omaha}},
author = {{Datacenter Source}},
year = {2026},
howpublished = {\url{/facilities/google-omaha-omaha-ne}},
note = {Data as of 2026-10-12; accessed 2026-10-12. Compiled from cited sources, including OpenStreetMap contributors (ODbL) and Epoch AI (CC BY 4.0)},
}Please also cite the original source of any specific figure (linked beside it).
POWER & GRID
Time-to-power · verification · interconnectionPower reality
- ⚠ No public interconnection record for this load — SPP does not publish large-load requests.
- ⚠ No permit record linked to this site yet.
How the time-to-power window was estimated
- From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
- The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- EnergizationApr 8, 2024
Satellite imagery
- Apr 8, 2024 · Building 1 operational, based on it being 6 months after roof was complete, infrastructure looked complete for 5 months.[1]
- Nov 19, 2024 · Building 2 is operational, based on it being 8 months since the roof was complete, and surrounding infrastructure looks just completed (finishing the cooling towers).[1]
- Jun 30, 2026 · Building 3 is operational (estimate). Based on there being minimal construction work as of May 15.[1]
- OperationalApr 8, 2024
Satellite imagery
- Apr 8, 2024 · Building 1 operational, based on it being 6 months after roof was complete, infrastructure looked complete for 5 months.[1]
- Nov 19, 2024 · Building 2 is operational, based on it being 8 months since the roof was complete, and surrounding infrastructure looks just completed (finishing the cooling towers).[1]
- Jun 30, 2026 · Building 3 is operational (estimate). Based on there being minimal construction work as of May 15.[1]
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.
Grid path
- →facilityGoogle Omaha
- →substationSatellite imageryLikely4 substation outlines traced inside the campus on satellite imagery; OSM maps Unnamed substation 0.28 km away
- →transmission161 kV line[5]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (0.28 km away). Not confirmed as the supply path.
- →utilityOmaha Public Power District[2]Service territoryLikelyRetail service territory containing the site
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
LOCAL IMPACT
Water · generation · incentives · regulation · ratesWater & cooling2
- 0.088 million gal/day[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 29, 2024.Jul 29, 2024modeled water use
Epoch AI's modeled estimate at the latest observed milestone, in million gallons per day. Not a permit or metered figure.
- Evaporative (cooling towers)[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of May 15, 2026.May 15, 2026cooling
“The cooling towers are spaced apart in an unusual way, but there's no obvious sign that more will be installed before operation.”
Named in Epoch AI's satellite-imagery notes for this date.
On-site generation & air permits
Not yet collected: we haven't found a source for on-site generation or an air permit for this site. Know one? Add a source
Incentives
Not yet collected: we haven't found a source for tax abatements, PILOTs or other incentives for this project. Know one? Add a source
Regulatory events
Not yet collected: we haven't found a source for hearings, rezonings, permits or commission proceedings. Know one? Add a source
Utility & rates
Not yet collected: we haven't found a source for a large-load tariff or commission docket for Omaha Public Power District. Know one? Add a source
Location & imagery
Mapped outline- Coordinates
- 41.34225, -96.08879
- Address
- 11110 State St, Omaha, NE 68142[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jun 30, 2026.Likely
- County
- Douglas County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workload
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- End user
- Utility
Location falls inside this utility's retail service territory.
Power (all fields)
- Current facility power
- 284 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jun 30, 2026.Likelyestimated
Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.
- Current IT capacity
- 237 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jun 30, 2026.Likelyestimated
Estimated IT load currently online, based on buildings observed operational.
- Planned capacity
- 474 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jun 30, 2026.Likelyestimated
Projected facility power at the last tracked milestone (2028-07-23); not necessarily full build-out.
- Estimated annual consumption
- 1,741 GWh/yr[3]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Speculativeestimated
284 MW × 8,760 h × 70% utilization.
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
- SPP[4]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived
Location falls inside this ISO/RTO footprint.
- Balancing authority
- SWPP[2]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived
Control area of the containing utility territory.
- Nearest mapped substation
- Unnamed substation[5]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- 0.3 km[5]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
- Highest-voltage line nearby
- 161 kV[5]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
- 10.00¢/kWh[7]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed
Nebraska statewide average, July 2026.
- State avg. commercial price
- 9.39¢/kWh[7]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed
Nebraska statewide average, July 2026.
- Generation within 50 km
- 3.11 GW[8]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jan 1, 202502.Confirmedderived
12 EIA-reported plants within 50 km.
- Generation queued in county
- 450 MW[6]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Confirmedderived
3 active generation interconnection requests in Douglas County: Storage 450 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 161 kV line | Transmission line | 0.28 km | 161 kV | [5] |
| North Omaha · Omaha Public Power District | Power plant (Coal) | 12.1 km | 564 MW | [8] |
| Jones Street · Omaha Public Power District | Power plant (Petroleum) | 17.2 km | 124 MW | [8] |
| Sarpy County · Omaha Public Power District | Power plant (Natural Gas) | 21.5 km | 316 MW | [8] |
| Walter Scott Jr Energy Center · MidAmerican Energy Co | Power plant (Coal) | 27.5 km | 1.51 GW | [8] |
| Platteview Solar LLC · AES Distributed Energy | Power plant (Solar) | 29.5 km | 81 MW | [8] |
| Lon Wright · City of Fremont - (NE) | Power plant (Coal) | 32.6 km | 159 MW | [8] |
| Cass County · Omaha Public Power District | Power plant (Natural Gas) | 45.1 km | 324 MW | [8] |
| Wahoo · City of Wahoo - (NE) | Power plant (Natural Gas) | 46 km | 14 MW | [8] |
| Unnamed substation | Substation | 0.28 km | — | [5] |
| Google substation · Google | Substation | 0.62 km | — | [5] |
| Google Switchyard (OPPD) · Omaha Public Power District | Substation | 0.63 km | — | [5] |
| Unnamed substation | Substation | 2.99 km | — | [5] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| GEN-2024-372 at S1247 161 kV SubstationSPP GEN-2024-372 | Storage | In study · proposed 2028-03 | 250 MW | [6] |
| GEN-2021-039 at New 161kV substation looping in OPPD 161kV lines S1211 to S1220 and S1211 to S1299SPP GEN-2021-039 | Storage | IA signed · proposed 2030-05 | 100 MW | [6] |
| GEN-2018-037 at Looping in OPPD (S1211) (S1220) (S1211) (S1299) 161kVSPP GEN-2018-037 | Storage | IA signed · proposed 2032-05 | 100 MW | [6] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction startNov 25, 2021[1]
- First operationalApr 8, 2024[1]
- Expected completionJul 23, 2028[1]Projected
- Planned capacity
- 474 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jun 30, 2026.Likelyestimated
Projected facility power at the last tracked milestone (2028-07-23); not necessarily full build-out.
- Buildings (planned)
- 3[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jun 30, 2026.Likelyderived
Count of building outlines traced on satellite imagery.
- Buildings operational
- 3[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jun 30, 2026.Likelyestimated
Real estate
None sourced yet
None sourced yet
None sourced yet
- Capital cost / investment
- $9B[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jun 30, 2026.Likelyestimated
Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Floor area
- Not yet sourced
Compute
- Chip types
- TPU v5e, TPU v5p, TPU v6e, TPU v7[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jun 30, 2026.Confirmed
- Compute (H100-equivalents)
- 198,600[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jun 30, 2026.Likelyestimated
What changed (last 3 years)
Follow this facility (RSS)- Current IT capacity79 MWApr 8, 2024[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→158 MWNov 19, 2024[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→237 MWJun 30, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
- Current facility power95 MWApr 8, 2024[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→189 MWNov 19, 2024[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→284 MWJun 30, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
- Buildings operational0Nov 25, 2021[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→1Apr 8, 2024[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→2Nov 19, 2024[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→3Jun 30, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
- StatusUnder constructionNov 25, 2021[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→Operating + expandingApr 8, 2024[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
Timeline
- Nov 25, 2021[1]
Land clearing begins.
Building 1 operational, based on it being 6 months after roof was complete, infrastructure looked complete for 5 months.
Building 2 has 3 cooling towers installed.
Building 2 is operational, based on it being 8 months since the roof was complete, and surrounding infrastructure looks just completed (finishing the cooling towers).
Confirmation that there's no obvious construction happening for Building 2. Building 3 roof started.
Confident that Building 2 is operational
Building 3 has all backup generators in place but they are still being installed. Two cooling towers have fans on them, with more underway. To the south of Building 3, more land has been cleared and there's a new carpark. This suggests another building will soon start construction.
Building 3 appears almost complete, with only minimal construction work and equipment remaining. The cooling towers are spaced apart in an unusual way, but there's no obvious sign that more will be installed before operation. Buildings 4 and 5 haven't started construction yet, the cleared land is still empty.
Building 3 is operational (estimate). Based on there being minimal construction work as of May 15.
Building 4 is operational. Expect a 4th building because there's enough land cleared for it. Assuming the foundation starts at the end of May 2026 and it takes a similar time to Building 3 from foundation to operational (1 year 8 months).
Building 5 is operational. We expect a 5th building because there's enough land cleared for one. We assume a roughly 6-month delay after Building 4.
Buildings on this campus
3All claims (provenance audit)
61| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Google Omaha | [1] | Likely | 2026-06-30 | Shown |
| Status | Under construction | [1] derived | Likely | 2021-11-25 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2024-04-08 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2024-07-29 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2024-11-19 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-03-16 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-04-21 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-10-21 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-05-15 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-06-30 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-06-30 | Shown |
| Address | 11110 State St, Omaha, NE 68142 | [1] | Likely | 2026-06-30 | Shown |
| Owner | GoogleOwner: Google | [1] | Confirmed | 2026-06-30 | Shown |
| End users | Google DeepMindUsers: Google DeepMind | [1] | Speculative | 2026-06-30 | Shown |
| Utility | Omaha Public Power Districtterritory 14127: OMAHA PUBLIC POWER DISTRICT (POLITICAL SUBDIVISION, OMAHA PUBLI | [2] derived | Likely | 2022 | Shown |
| Current facility power | 284 MW | [1] estimated | Likely | 2026-06-30 | Shown |
| Current facility power | 95 MW | [1] estimated | Likely | 2024-04-08 | Superseded / alternative |
| Current facility power | 95 MW | [1] estimated | Likely | 2024-07-29 | Superseded / alternative |
| Current facility power | 189 MW | [1] estimated | Likely | 2024-11-19 | Superseded / alternative |
| Current facility power | 189 MW | [1] estimated | Likely | 2025-03-16 | Superseded / alternative |
| Current facility power | 189 MW | [1] estimated | Likely | 2025-04-21 | Superseded / alternative |
| Current facility power | 189 MW | [1] estimated | Likely | 2025-10-21 | Superseded / alternative |
| Current facility power | 189 MW | [1] estimated | Likely | 2026-05-15 | Superseded / alternative |
| Current IT capacity | 237 MW | [1] estimated | Likely | 2026-06-30 | Shown |
| Current IT capacity | 79 MW | [1] estimated | Likely | 2024-04-08 | Superseded / alternative |
| Current IT capacity | 79 MW | [1] estimated | Likely | 2024-07-29 | Superseded / alternative |
| Current IT capacity | 158 MW | [1] estimated | Likely | 2024-11-19 | Superseded / alternative |
| Current IT capacity | 158 MW | [1] estimated | Likely | 2025-03-16 | Superseded / alternative |
| Current IT capacity | 158 MW | [1] estimated | Likely | 2025-04-21 | Superseded / alternative |
| Current IT capacity | 158 MW | [1] estimated | Likely | 2025-10-21 | Superseded / alternative |
| Current IT capacity | 158 MW | [1] estimated | Likely | 2026-05-15 | Superseded / alternative |
| Planned capacity | 474 MW | [1] estimated | Likely | 2026-06-30 | Shown |
| Estimated annual consumption | 1,741 GWh/yr | [3] estimated | Speculative | 2026-10-12 | Shown |
| ISO / RTO | SPPSOUTHWEST POWER POOL | [4] derived | Likely | — | Shown |
| Balancing authority | SWPP | [2] derived | Likely | — | Shown |
| Nearest mapped substation | Unnamed substationway/1478655491 | [5] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.3 km | [5] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 161 kV | [5] derived | Likely | 2026-09-28 | Shown |
| Generation queued in county | 450 MW | [6] derived | Confirmed | 2026-10-12 | Shown |
| State avg. industrial price | 10.00¢/kWh | [7] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 9.39¢/kWh | [7] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 3.11 GW | [8] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 3 | [1] derived | Likely | 2026-06-30 | Shown |
| Buildings operational | 3 | [1] estimated | Likely | 2026-06-30 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2021-11-25 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2024-04-08 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2024-07-29 | Superseded / alternative |
| Buildings operational | 2 | [1] estimated | Likely | 2024-11-19 | Superseded / alternative |
| Buildings operational | 2 | [1] estimated | Likely | 2025-03-16 | Superseded / alternative |
| Buildings operational | 2 | [1] estimated | Likely | 2025-04-21 | Superseded / alternative |
| Buildings operational | 2 | [1] estimated | Likely | 2025-10-21 | Superseded / alternative |
| Buildings operational | 2 | [1] estimated | Likely | 2026-05-15 | Superseded / alternative |
| Capital cost / investment | $9B | [1] estimated | Likely | 2026-06-30 | Shown |
| Compute (H100-equivalents) | 198,600 | [1] estimated | Likely | 2026-06-30 | Shown |
| Chip types | TPU v5e | [1] | Confirmed | 2026-06-30 | Shown |
| Chip types | TPU v5p | [1] | Confirmed | 2026-06-30 | Shown |
| Chip types | TPU v6e | [1] | Confirmed | 2026-06-30 | Shown |
| Chip types | TPU v7 | [1] | Confirmed | 2026-06-30 | Shown |
| Construction start | Nov 25, 2021 | [1] derived | Likely | 2026-06-30 | Shown |
| First operational | Apr 8, 2024 | [1] derived | Likely | 2026-06-30 | Shown |
| Expected completion | Jul 23, 2028 | [1] estimated | Speculative | 2026-06-30 | Shown |