DC
/

Google Omaha

Operating + expandingEst.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jun 30, 2026.AI campusCampusOmaha, Douglas County, Nebraska

Google Omaha is an operating + expanding ai campus in Omaha, Nebraska. Operated or owned by Google. Current power: 284 MW (estimated). Planned capacity: 474 MW (estimated). Verification: verified operating. 10 cited sources.

80% profile completeness
61 claims from 10 sources
Last verified against sources: Oct 12, 2026
Newest dated evidence: Jun 30, 2026
Follow

Get changes to Google Omaha

How often

Double opt-in; one-click unsubscribe in every email. We store only your email and what you follow. More

Or subscribe in a feed reader: RSS / Atom

Cite this
Text
Datacenter Source. “Google Omaha.” /facilities/google-omaha-omaha-ne. Data as of 2026-10-12. Accessed 2026-10-12.
BibTeX
@misc{datacentersource_google_omaha_omaha_ne_2026,
  title = {{Google Omaha}},
  author = {{Datacenter Source}},
  year = {2026},
  howpublished = {\url{/facilities/google-omaha-omaha-ne}},
  note = {Data as of 2026-10-12; accessed 2026-10-12. Compiled from cited sources, including OpenStreetMap contributors (ODbL) and Epoch AI (CC BY 4.0)},
}

Please also cite the original source of any specific figure (linked beside it).

Current facility power
284 MW[1]
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jun 30, 2026.Likelyestimated
Planned capacity
474 MW[1]
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jun 30, 2026.Likelyestimated
Floor area
Not yet sourced
Buildings (planned)
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jun 30, 2026.Likelyderived
Capital cost / investment
$9B[1]
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jun 30, 2026.Likelyestimated
First operational
Apr 8, 2024[1]
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jun 30, 2026.Likelyderived

POWER & GRID

Time-to-power · verification · interconnection
Time to power
Remaining capacity: H2 2027 – H2 2028
Medium confidencewindow, not a prediction
Project verification
Verified operating
Operation documented by satellite imagery.
Current stage
Operational
Furthest stage with documented evidence
Utility · ISO
Omaha Public Power District · SPP
Substation: On-site substation

Power reality

Announced
474 MW[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
Research estimate of planned capacity (no company figure found)
Interconnection request
No record
Contracted / approved
No record
Under construction
190 MW[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
Building 4, Building 5 under construction (satellite-tracked phases)
Operational
284 MW[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
Estimated from buildings observed operational
  • ⚠ No public interconnection record for this load — SPP does not publish large-load requests.
  • ⚠ No permit record linked to this site yet.
AI evidence brief
Summarizes only the evidence on this page. Answers citing anything else are rejected automatically.
How the time-to-power window was estimated
Evidence used
  • Current stage: Operational (furthest stage with documented evidence)[1]
  • Stated date: Next projected milestone: 2028-01-23 (modeled/speculative)[1]
  • Required: 474 MW
Assumptions
  • From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
  • The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Window: H2 2027 – H2 2028

Project verification

Development
  1. Announcedimplied by a later stage
  2. Land acquiredimplied by a later stage
  3. Planning / zoningimplied by a later stage
  4. Permittingimplied by a later stage
Grid interconnection
  1. Interconnection application
  2. Feasibility study
  3. System impact study
  4. Facilities study
  5. Interconnection agreement / service contract
Build & energization
  1. Financing
  2. Under constructionNov 25, 2021
    Model estimate · Satellite imagery
    • Nov 25, 2021 · Reported status: under construction[1]
    • Nov 25, 2021 · Construction start[1]
    • Nov 25, 2021 · Land clearing begins.[1]
    • Apr 8, 2024 · Reported status: expanding[1]
  3. EnergizationApr 8, 2024
    Satellite imagery
    • Apr 8, 2024 · Building 1 operational, based on it being 6 months after roof was complete, infrastructure looked complete for 5 months.[1]
    • Nov 19, 2024 · Building 2 is operational, based on it being 8 months since the roof was complete, and surrounding infrastructure looks just completed (finishing the cooling towers).[1]
    • Jun 30, 2026 · Building 3 is operational (estimate). Based on there being minimal construction work as of May 15.[1]
  4. OperationalApr 8, 2024
    Satellite imagery
    • Apr 8, 2024 · Building 1 operational, based on it being 6 months after roof was complete, infrastructure looked complete for 5 months.[1]
    • Nov 19, 2024 · Building 2 is operational, based on it being 8 months since the roof was complete, and surrounding infrastructure looks just completed (finishing the cooling towers).[1]
    • Jun 30, 2026 · Building 3 is operational (estimate). Based on there being minimal construction work as of May 15.[1]

● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.

Grid path

  1. facility
    Google Omaha
  2. substation
    On-site substation[1][5]
    Satellite imageryLikely
    4 substation outlines traced inside the campus on satellite imagery; OSM maps Unnamed substation 0.28 km away
  3. transmission
    161 kV line[5]
    Proximity onlyUnverified
    Highest-voltage line mapped within 2 km (0.28 km away). Not confirmed as the supply path.
  4. utility
    Omaha Public Power District[2]
    Service territoryLikely
    Retail service territory containing the site
  5. ISO / RTO
    SPP[4]
    Service territoryLikely
    Balancing authority: SWPP
Substation capacity:
not published
Required upgrades:
not yet sourced
Congestion:
not yet sourced (no nodal price data)

Dashed boxes are based on proximity only and do not establish which asset serves the site.

Interconnection records

No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.

On-site & dedicated generation

No on-site, behind-the-meter or dedicated generation found in sources.

LOCAL IMPACT

Water · generation · incentives · regulation · rates

Water & cooling2

  • 0.088 million gal/day[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 29, 2024.Jul 29, 2024modeled water use

    Epoch AI's modeled estimate at the latest observed milestone, in million gallons per day. Not a permit or metered figure.

  • Evaporative (cooling towers)[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of May 15, 2026.May 15, 2026cooling

    “The cooling towers are spaced apart in an unusual way, but there's no obvious sign that more will be installed before operation.”

    Named in Epoch AI's satellite-imagery notes for this date.

On-site generation & air permits

Not yet collected: we haven't found a source for on-site generation or an air permit for this site. Know one? Add a source

Incentives

Not yet collected: we haven't found a source for tax abatements, PILOTs or other incentives for this project. Know one? Add a source

Regulatory events

Not yet collected: we haven't found a source for hearings, rezonings, permits or commission proceedings. Know one? Add a source

Utility & rates

Not yet collected: we haven't found a source for a large-load tariff or commission docket for Omaha Public Power District. Know one? Add a source

Location & imagery

Mapped outline
Coordinates
41.34225, -96.08879
Address
11110 State St, Omaha, NE 68142[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jun 30, 2026.Likely
County
Douglas County
Photographs

No openly licensed ground-level photos matched to this site yet.

Ownership, operation & customers

  1. 1. Property owner of record
    Not identified
  2. 2. Owner / developer
  3. 3. Operator
    Not identified
  4. 4. Tenant / cloud
    Not identified
  5. 5. End customer / workload
Power supply

Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.

All parties with evidence
Owner
Google[1]Confirmed
End user
Utility

Location falls inside this utility's retail service territory.

Power (all fields)

Current facility power
284 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jun 30, 2026.Likelyestimated

Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.

Current IT capacity
237 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jun 30, 2026.Likelyestimated

Estimated IT load currently online, based on buildings observed operational.

Planned capacity
474 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jun 30, 2026.Likelyestimated

Projected facility power at the last tracked milestone (2028-07-23); not necessarily full build-out.

Estimated annual consumption
1,741 GWh/yr[3]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Speculativeestimated

284 MW × 8,760 h × 70% utilization.

Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.

Grid & electricity

ISO / RTO
SPP[4]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived

Location falls inside this ISO/RTO footprint.

Balancing authority
SWPP[2]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived

Control area of the containing utility territory.

Nearest mapped substation
Unnamed substation[5]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived

Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.

Distance to substation
0.3 km[5]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
Highest-voltage line nearby
161 kV[5]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived

Highest-voltage transmission line mapped within 2 km.

State avg. industrial price
10.00¢/kWh[7]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed

Nebraska statewide average, July 2026.

State avg. commercial price
9.39¢/kWh[7]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed

Nebraska statewide average, July 2026.

Generation within 50 km
3.11 GW[8]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jan 1, 202502.Confirmedderived

12 EIA-reported plants within 50 km.

Generation queued in county
450 MW[6]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Confirmedderived

3 active generation interconnection requests in Douglas County: Storage 450 MW. Queued projects often don't get built.

Interconnection status
Not yet sourced
Contracted / committed power
Not yet sourced
Nearby infrastructureTypeDistanceVoltage / capacitySource
161 kV lineTransmission line0.28 km161 kV[5]
North Omaha · Omaha Public Power DistrictPower plant (Coal)12.1 km564 MW[8]
Jones Street · Omaha Public Power DistrictPower plant (Petroleum)17.2 km124 MW[8]
Sarpy County · Omaha Public Power DistrictPower plant (Natural Gas)21.5 km316 MW[8]
Walter Scott Jr Energy Center · MidAmerican Energy CoPower plant (Coal)27.5 km1.51 GW[8]
Platteview Solar LLC · AES Distributed EnergyPower plant (Solar)29.5 km81 MW[8]
Lon Wright · City of Fremont - (NE)Power plant (Coal)32.6 km159 MW[8]
Cass County · Omaha Public Power DistrictPower plant (Natural Gas)45.1 km324 MW[8]
Wahoo · City of Wahoo - (NE)Power plant (Natural Gas)46 km14 MW[8]
Unnamed substationSubstation0.28 km—[5]
Google substation · GoogleSubstation0.62 km—[5]
Google Switchyard (OPPD) · Omaha Public Power DistrictSubstation0.63 km—[5]
Unnamed substationSubstation2.99 km—[5]
Largest queued generation in this countyFuelQueue statusMWSource
GEN-2024-372 at S1247 161 kV SubstationSPP GEN-2024-372StorageIn study · proposed 2028-03250 MW[6]
GEN-2021-039 at New 161kV substation looping in OPPD 161kV lines S1211 to S1220 and S1211 to S1299SPP GEN-2021-039StorageIA signed · proposed 2030-05100 MW[6]
GEN-2018-037 at Looping in OPPD (S1211) (S1220) (S1211) (S1299) 161kVSPP GEN-2018-037StorageIA signed · proposed 2032-05100 MW[6]

Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.

Construction & permitting

  1. Announced
    —
  2. Land acquired
    —
  3. Permitting
    —
  4. Construction start
    Nov 25, 2021[1]
  5. First operational
    Apr 8, 2024[1]
  6. Expected completion
    Jul 23, 2028[1]
    Projected
Planned capacity
474 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jun 30, 2026.Likelyestimated

Projected facility power at the last tracked milestone (2028-07-23); not necessarily full build-out.

Buildings (planned)
3[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jun 30, 2026.Likelyderived

Count of building outlines traced on satellite imagery.

Buildings operational
3[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jun 30, 2026.Likelyestimated
PhaseStatusAdded MWCompleted / expectedSource
Building 1operational95 MWApr 8, 2024[1]
Building 2operational94 MWNov 19, 2024[1]
Building 3operational95 MWJun 30, 2026[1]
Building 4under construction95 MWJan 23, 2028 (projected)[1]
Building 5under construction95 MWJul 23, 2028 (projected)[1]

Real estate

Official assessments
Assessor's value for a tax year

None sourced yet

Recorded transactions
Sale prices from recorded deeds

None sourced yet

Model estimates
Our model — not an appraisal

None sourced yet

Capital cost / investment
$9B[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jun 30, 2026.Likelyestimated

Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.

Annual property tax
Not yet sourced

No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.

Size

Floor area
Not yet sourced

Compute

Chip types
TPU v5e, TPU v5p, TPU v6e, TPU v7[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jun 30, 2026.Confirmed
Compute (H100-equivalents)
198,600[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jun 30, 2026.Likelyestimated

What changed (last 3 years)

Follow this facility (RSS)
  • Current IT capacity
    79 MWApr 8, 2024[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→158 MWNov 19, 2024[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→237 MWJun 30, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
  • Current facility power
    95 MWApr 8, 2024[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→189 MWNov 19, 2024[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→284 MWJun 30, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
  • Buildings operational
    0Nov 25, 2021[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→1Apr 8, 2024[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→2Nov 19, 2024[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→3Jun 30, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
  • Status
    Under constructionNov 25, 2021[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→Operating + expandingApr 8, 2024[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.

Timeline

Construction start: Nov 25, 2021[1]
First operational: Apr 8, 2024[1]
  1. Nov 25, 2021[1]

    Land clearing begins.

  2. Apr 8, 202495 MW facility power· 1 buildings operational[1]

    Building 1 operational, based on it being 6 months after roof was complete, infrastructure looked complete for 5 months.

  3. Jul 29, 202495 MW facility power· 1 buildings operational[1]

    Building 2 has 3 cooling towers installed.

  4. Nov 19, 2024189 MW facility power· 2 buildings operational[1]

    Building 2 is operational, based on it being 8 months since the roof was complete, and surrounding infrastructure looks just completed (finishing the cooling towers).

  5. Mar 16, 2025189 MW facility power· 2 buildings operational[1]

    Confirmation that there's no obvious construction happening for Building 2. Building 3 roof started.

  6. Apr 21, 2025189 MW facility power· 2 buildings operational[1]

    Confident that Building 2 is operational

  7. Oct 21, 2025189 MW facility power· 2 buildings operational[1]

    Building 3 has all backup generators in place but they are still being installed. Two cooling towers have fans on them, with more underway. To the south of Building 3, more land has been cleared and there's a new carpark. This suggests another building will soon start construction.

  8. May 15, 2026189 MW facility power· 2 buildings operational[1]

    Building 3 appears almost complete, with only minimal construction work and equipment remaining. The cooling towers are spaced apart in an unusual way, but there's no obvious sign that more will be installed before operation. Buildings 4 and 5 haven't started construction yet, the cleared land is still empty.

  9. Jun 30, 2026284 MW facility power· 3 buildings operational[1]

    Building 3 is operational (estimate). Based on there being minimal construction work as of May 15.

  10. Jan 23, 2028Projected379 MW facility power· 4 buildings operational[1]

    Building 4 is operational. Expect a 4th building because there's enough land cleared for it. Assuming the foundation starts at the end of May 2026 and it takes a similar time to Building 3 from foundation to operational (1 year 8 months).

  11. Jul 23, 2028Projected474 MW facility power· 5 buildings operational[1]

    Building 5 is operational. We expect a 5th building because there's enough land cleared for one. We assume a roughly 6-month delay after Building 4.

Buildings on this campus

3
  • GoogleOperating · 290,400 sq ft footprint
  • GoogleOperating · 290,400 sq ft footprint
  • GoogleOperating · 290,400 sq ft footprint

All claims (provenance audit)

61
FieldValueSourceConfidenceAs ofStatus
NameGoogle Omaha[1] Likely2026-06-30Shown
StatusUnder construction[1] derivedLikely2021-11-25Superseded / alternative
StatusOperating + expanding[1] derivedLikely2024-04-08Superseded / alternative
StatusOperating + expanding[1] derivedLikely2024-07-29Superseded / alternative
StatusOperating + expanding[1] derivedLikely2024-11-19Superseded / alternative
StatusOperating + expanding[1] derivedLikely2025-03-16Superseded / alternative
StatusOperating + expanding[1] derivedLikely2025-04-21Superseded / alternative
StatusOperating + expanding[1] derivedLikely2025-10-21Superseded / alternative
StatusOperating + expanding[1] derivedLikely2026-05-15Superseded / alternative
StatusOperating + expanding[1] derivedLikely2026-06-30Shown
Facility typeAI campus[1] derivedLikely2026-06-30Shown
Address11110 State St, Omaha, NE 68142[1] Likely2026-06-30Shown
OwnerGoogleOwner: Google[1] Confirmed2026-06-30Shown
End usersGoogle DeepMindUsers: Google DeepMind[1] Speculative2026-06-30Shown
UtilityOmaha Public Power Districtterritory 14127: OMAHA PUBLIC POWER DISTRICT (POLITICAL SUBDIVISION, OMAHA PUBLI[2] derivedLikely2022Shown
Current facility power284 MW[1] estimatedLikely2026-06-30Shown
Current facility power95 MW[1] estimatedLikely2024-04-08Superseded / alternative
Current facility power95 MW[1] estimatedLikely2024-07-29Superseded / alternative
Current facility power189 MW[1] estimatedLikely2024-11-19Superseded / alternative
Current facility power189 MW[1] estimatedLikely2025-03-16Superseded / alternative
Current facility power189 MW[1] estimatedLikely2025-04-21Superseded / alternative
Current facility power189 MW[1] estimatedLikely2025-10-21Superseded / alternative
Current facility power189 MW[1] estimatedLikely2026-05-15Superseded / alternative
Current IT capacity237 MW[1] estimatedLikely2026-06-30Shown
Current IT capacity79 MW[1] estimatedLikely2024-04-08Superseded / alternative
Current IT capacity79 MW[1] estimatedLikely2024-07-29Superseded / alternative
Current IT capacity158 MW[1] estimatedLikely2024-11-19Superseded / alternative
Current IT capacity158 MW[1] estimatedLikely2025-03-16Superseded / alternative
Current IT capacity158 MW[1] estimatedLikely2025-04-21Superseded / alternative
Current IT capacity158 MW[1] estimatedLikely2025-10-21Superseded / alternative
Current IT capacity158 MW[1] estimatedLikely2026-05-15Superseded / alternative
Planned capacity474 MW[1] estimatedLikely2026-06-30Shown
Estimated annual consumption1,741 GWh/yr[3] estimatedSpeculative2026-10-12Shown
ISO / RTOSPPSOUTHWEST POWER POOL[4] derivedLikely—Shown
Balancing authoritySWPP[2] derivedLikely—Shown
Nearest mapped substationUnnamed substationway/1478655491[5] derivedLikely2026-09-28Shown
Distance to substation0.3 km[5] derivedLikely2026-09-28Shown
Highest-voltage line nearby161 kV[5] derivedLikely2026-09-28Shown
Generation queued in county450 MW[6] derivedConfirmed2026-10-12Shown
State avg. industrial price10.00¢/kWh[7] Confirmed2026-07Shown
State avg. commercial price9.39¢/kWh[7] Confirmed2026-07Shown
Generation within 50 km3.11 GW[8] derivedConfirmed202502Shown
Buildings (planned)3[1] derivedLikely2026-06-30Shown
Buildings operational3[1] estimatedLikely2026-06-30Shown
Buildings operational0[1] estimatedLikely2021-11-25Superseded / alternative
Buildings operational1[1] estimatedLikely2024-04-08Superseded / alternative
Buildings operational1[1] estimatedLikely2024-07-29Superseded / alternative
Buildings operational2[1] estimatedLikely2024-11-19Superseded / alternative
Buildings operational2[1] estimatedLikely2025-03-16Superseded / alternative
Buildings operational2[1] estimatedLikely2025-04-21Superseded / alternative
Buildings operational2[1] estimatedLikely2025-10-21Superseded / alternative
Buildings operational2[1] estimatedLikely2026-05-15Superseded / alternative
Capital cost / investment$9B[1] estimatedLikely2026-06-30Shown
Compute (H100-equivalents)198,600[1] estimatedLikely2026-06-30Shown
Chip typesTPU v5e[1] Confirmed2026-06-30Shown
Chip typesTPU v5p[1] Confirmed2026-06-30Shown
Chip typesTPU v6e[1] Confirmed2026-06-30Shown
Chip typesTPU v7[1] Confirmed2026-06-30Shown
Construction startNov 25, 2021[1] derivedLikely2026-06-30Shown
First operationalApr 8, 2024[1] derivedLikely2026-06-30Shown
Expected completionJul 23, 2028[1] estimatedSpeculative2026-06-30Shown