Google Columbus
Google Columbus is an operating + expanding ai campus in Columbus, Ohio. Operated or owned by Google. Current power: 364 MW (estimated). Planned capacity: 464 MW (estimated). Verification: verified operating. 11 cited sources.
Follow
Get changes to Google Columbus
Or subscribe in a feed reader: RSS / Atom
Cite this
Datacenter Source. “Google Columbus.” /facilities/google-columbus-columbus-oh. Data as of 2026-10-12. Accessed 2026-10-12.
@misc{datacentersource_google_columbus_columbus_oh_2026,
title = {{Google Columbus}},
author = {{Datacenter Source}},
year = {2026},
howpublished = {\url{/facilities/google-columbus-columbus-oh}},
note = {Data as of 2026-10-12; accessed 2026-10-12. Compiled from cited sources, including OpenStreetMap contributors (ODbL) and Epoch AI (CC BY 4.0)},
}Please also cite the original source of any specific figure (linked beside it).
POWER & GRID
Time-to-power · verification · interconnectionPower reality
- ⚠ No public interconnection record for this load — PJM does not publish large-load requests.
- ⚠ No permit record linked to this site yet.
How the time-to-power window was estimated
- From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
- The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Project verification
- Announcedimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- EnergizationApr 1, 2024
Satellite imagery
- Apr 1, 2024 · Building 1 operational. No visible construction and roads/parking complete around the building. Building 2 chillers are beginning construction. Foundation work begins for Building [1]
- Mar 1, 2025 · Building 2 operational. Parking complete, no more visible construction.[1]
- Oct 1, 2025 · Building 3 operational. Surrounding roads finished, no more visible construction.[1]
- May 1, 2026 · Building 4 operational. No more visible construction, and since only 3 fans needed to be installed since Feburary, operational date was likely soon after. Building 5 roof almost co[1]
- OperationalApr 1, 2024
Satellite imagery · Government record
- Apr 1, 2024 · Building 1 operational. No visible construction and roads/parking complete around the building. Building 2 chillers are beginning construction. Foundation work begins for Building [1]
- Mar 1, 2025 · Building 2 operational. Parking complete, no more visible construction.[1]
- Oct 1, 2025 · Building 3 operational. Surrounding roads finished, no more visible construction.[1]
- May 1, 2026 · Building 4 operational. No more visible construction, and since only 3 fans needed to be installed since Feburary, operational date was likely soon after. Building 5 roof almost co[1]
- Oct 12, 2026 · County land use: data center[2]
- Oct 12, 2026 · County records a 1,172,656 sq ft building[2]
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Government record, Model estimate, Satellite imagery.
Grid path
- →facilityGoogle Columbus
- →substationSatellite imageryLikely5 substation outlines traced inside the campus on satellite imagery; OSM maps Unnamed substation 0.34 km away
- →transmission345 kV line[6]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (1.62 km away). Not confirmed as the supply path.
- →utilityAmerican Electric Power[3]Service territoryLikelyRetail service territory containing the site
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
LOCAL IMPACT
Water · generation · incentives · regulation · ratesWater & cooling1
- Evaporative (cooling towers)[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Aug 5, 2026.Aug 5, 2026cooling
“Building 5 has progressed since February, with a complete roof, all backup generators in place, and five cooling towers in place.”
Named in Epoch AI's satellite-imagery notes for this date.
On-site generation & air permits
Not yet collected: we haven't found a source for on-site generation or an air permit for this site. Know one? Add a source
Incentives
Not yet collected: we haven't found a source for tax abatements, PILOTs or other incentives for this project. Know one? Add a source
Regulatory events
Not yet collected: we haven't found a source for hearings, rezonings, permits or commission proceedings. Know one? Add a source
Utility & rates1
- AEP Ohio data center tariff[12]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 9, 2025.Jul 9, 2025American Electric Power · Public Utilities Commission of Ohio · Docket 24-508-EL-ATA · Order issued; moratorium on new data center connections to be lifted
“AEP Ohio is ordered to file updated tariffs and lift its moratorium on connecting new data centers as soon as possible.”
Applies in AEP Ohio's territory (AEP operating company in Ohio).
Location & imagery
Mapped outline- Coordinates
- 39.84940, -82.99757
- Address
- 5076 S High St, Columbus, OH 43207[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Aug 5, 2026.Likely
- County
- Franklin County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of record
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workload
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Property owner of record
- End user
- Utility
Location falls inside this utility's retail service territory.
Power (all fields)
- Current facility power
- 364 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Aug 5, 2026.Likelyestimated
Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.
- Current IT capacity
- 303 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Aug 5, 2026.Likelyestimated
Estimated IT load currently online, based on buildings observed operational.
- Planned capacity
- 464 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Aug 5, 2026.Likelyestimated
Projected facility power at the last tracked milestone (2027-07-01); not necessarily full build-out.
- Estimated annual consumption
- 2,232 GWh/yr[4]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Speculativeestimated
364 MW × 8,760 h × 70% utilization.
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
- PJM[5]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived
Location falls inside this ISO/RTO footprint.
- Balancing authority
- PJM[3]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived
Control area of the containing utility territory.
- Nearest mapped substation
- Unnamed substation (138 kV)[6]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- 0.3 km[6]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
- Highest-voltage line nearby
- 345 kV[6]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
- 10.95¢/kWh[8]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed
Ohio statewide average, July 2026.
- State avg. commercial price
- 14.06¢/kWh[8]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed
Ohio statewide average, July 2026.
- Generation within 50 km
- 1.98 GW[9]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jan 1, 202502.Confirmedderived
15 EIA-reported plants within 50 km.
- Generation queued in county
- 1.66 GW[7]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Confirmedderived
8 active generation interconnection requests in Franklin County: Solar 845 MW, Storage 810 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 138 kV line | Transmission line | 0.52 km | 138 kV | [6] |
| Cyprus 138kV Extension · American Electric Power | Transmission line | 0.9 km | 138 kV | [6] |
| 345 kV line · American Electric Power | Transmission line | 1.62 km | 345 kV | [6] |
| Darby Power, LLC · Darby Power, LLC | Power plant (Natural Gas) | 21.5 km | 480 MW | [9] |
| Big Plain Solar, LLC · Leeward Asset Management, LLC | Power plant (Solar) | 28.3 km | 196 MW | [9] |
| Fox Squirrel Solar · EDF Renewable Asset Holdings, Inc. | Power plant (Solar) | 32.6 km | 577 MW | [9] |
| O'Shaughnessy Hydro · City of Columbus - (OH) | Power plant (Hydroelectric) | 35.5 km | 5 MW | [9] |
| Atlanta Farms Solar · Dominion Renewable Energy | Power plant (Solar) | 35.6 km | 200 MW | [9] |
| Yellowbud Solar, LLC · Yellowbud Solar LLC | Power plant (Solar) | 39 km | 274 MW | [9] |
| Salt City Solar Project - Hybrid · Salt City Solar LLC | Power plant (Solar) | 48.4 km | 50 MW | [9] |
| Madison Fields Solar Project, LLC · Madison Fields Solar Project, LLC | Power plant (Solar) | 48.7 km | 180 MW | [9] |
| Unnamed substation | Substation | 0.34 km | 138 kV | [6] |
| Unnamed substation | Substation | 0.52 km | 138 kV | [6] |
| Unnamed substation | Substation | 0.55 km | 138 kV | [6] |
| Cyprus Switching Station · AEP Ohio | Substation | 0.91 km | 138 kV | [6] |
| Parsons Substation · AEP Ohio | Substation | 1.24 km | 138 kV | [6] |
| Unnamed substation | Substation | 2.64 km | 69 kV | [6] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| Beatty 345 kVPJM AG2-376 | Storage | In study · proposed 2024-11 | 400 MW | [7] |
| Cole 345 kVPJM AH1-318 | Storage | In study · proposed 2025-12 | 310 MW | [7] |
| Cole Road 345 kVPJM AI2-171 | Solar | In study · proposed 2023-12 | 310 MW | [7] |
| Cole 345 kVPJM AF1-275 | Solar | In study · proposed 2022-12 | 250 MW | [7] |
| Pleasant Prairie SolarPJM AE2-214 | Solar | IA signed · proposed 2026-12 | 200 MW | [7] |
| Hayden 345 kVPJM AH1-270 | Solar | In study · proposed 2023-12 | 85 MW | [7] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquiredJun 8, 2022[2]
- Permitting—
- Construction startOct 1, 2021[1]
- First operationalApr 1, 2024[1]
- Expected completionJul 1, 2027[1]Projected
- Planned capacity
- 464 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Aug 5, 2026.Likelyestimated
Projected facility power at the last tracked milestone (2027-07-01); not necessarily full build-out.
- Buildings (planned)
- 5[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Aug 5, 2026.Likelyderived
Count of building outlines traced on satellite imagery.
- Buildings operational
- 4[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Aug 5, 2026.Likelyestimated
Real estate
None sourced yet
None sourced yet
| Parcel | Record owner | Acres | Zoning / use | Building sq ft | Source |
|---|---|---|---|---|---|
| 510-180711 Franklin County, OH | MAGELLAN ENTERPRISES LLC Tax bills to: GOOGLE LLC PO BOX 28190 SCOTTSDALE AZ 85255-0153 | 480.39 | data center | 1,172,656 | [2] |
- Site area
- 480.4 acres[2]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Oct 12, 2026.Confirmed
Sum of county land area across parcels.
- Land use
- data center[2]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Oct 12, 2026.Confirmed
- Capital cost / investment
- $11.5B[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Aug 5, 2026.Likelyestimated
Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.
- Annual property tax
- Not yet sourced
- Amazon Web Services · 26.9 km · parcel 050-011455$226,596 · Oct 18, 2022 [2]
- DartPoints Dublin · 29.5 km · parcel 273-001702$15.3M · Oct 29, 2020 [2]
- Google NBY-4 · 30.3 km · parcel 222-004984$27.4M · Dec 13, 2018 [2]
- TJX Corporate Techno · 32.5 km · parcel 222-004441$2.1M · Jul 23, 2010 [2]
- Compugen New Albany · 32.5 km · parcel 222-004644$2.2M · Oct 1, 2014 [2]
- Compugen New Albany · 32.8 km · parcel 222-001940$6.8M · Feb 6, 2023 [2]
Size
- Floor area
- 1.17M sq ft[2]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Oct 12, 2026.Confirmed
Building area in county assessment records.
- Parcel / land records
- 510-180711 (Franklin County)[2]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Oct 12, 2026.Confirmed
Compute
- Chip types
- TPU v5e, TPU v5p, TPU v6e, TPU v7[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Aug 5, 2026.Confirmed
- Compute (H100-equivalents)
- 332,000[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Aug 5, 2026.Likelyestimated
What changed (last 3 years)
Follow this facility (RSS)- Current IT capacity65 MWApr 1, 2024[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→130 MWMar 1, 2025[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→216 MWOct 1, 2025[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→303 MWMay 1, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
- Current facility power78 MWApr 1, 2024[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→156 MWMar 1, 2025[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→260 MWOct 1, 2025[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→364 MWMay 1, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
- Buildings operational0Oct 1, 2021[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→1Apr 1, 2024[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→2Mar 1, 2025[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→3Oct 1, 2025[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→4May 1, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
- StatusUnder constructionOct 1, 2021[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→Operating + expandingApr 1, 2024[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
Timeline
- Oct 1, 2021[1]
Land clearing begins on the eastern half of the site, for Buildings 1-2
- Jul 1, 2023[1]
Building 2 foundation work begins. Building 1 generators seem complete, cooling towers still under construction.
Building 1 operational. No visible construction and roads/parking complete around the building. Building 2 chillers are beginning construction. Foundation work begins for Building 3.
Building 2 operational. Parking complete, no more visible construction.
Building 3 operational. Surrounding roads finished, no more visible construction.
Buildings 1-3 are visibly operational, with steam coming out of the cooling towers. Meanwhile Building 4 is extremely close to completion, with all backup generators complete with only 3 cooling towers missing their fans. ~1/2 the generators are installed for Building 5, and the roof is mostly complete (starting to install the final white layer, with the actual roof structure already complete).
Building 4 operational. No more visible construction, and since only 3 fans needed to be installed since Feburary, operational date was likely soon after. Building 5 roof almost complete.
Confirmation that Building 4 is complete. Building 5 has progressed since February, with a complete roof, all backup generators in place, and five cooling towers in place.
Building 5 operational. The transmission line construction notice that expands site by 100 MW is assumed to be entirely for Building 5, and has an in-service date of July 1, 2027 (page 3). Estimate taken on the safe side based on completion times for Building 3-4 from when roof was complete.
- Jun 8, 2022[2]
Deed/transfer recorded for parcel 510-180711 (no sale price disclosed).
Buildings on this campus
2- GoogleOperating · 290,200 sq ft footprint
- Google Lockbourne, OHOperating
All claims (provenance audit)
62| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Google Columbus | [1] | Likely | 2026-08-05 | Shown |
| Status | Under construction | [1] derived | Likely | 2021-10-01 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2023-07-01 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2024-04-01 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-03-01 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-10-01 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-02-21 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-05-01 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-08-05 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-08-05 | Shown |
| Address | 5076 S High St, Columbus, OH 43207 | [1] | Likely | 2026-08-05 | Shown |
| Property owner of record | Magellan Enterprises LLCParcel 510-180711: MAGELLAN ENTERPRISES LLC (tax mailing name: GOOGLE LLC) | [2] | Confirmed | 2026-10-12 | Shown |
| Owner | GoogleOwner: Google | [1] | Confirmed | 2026-08-05 | Shown |
| End users | Google DeepMindUsers: Google DeepMind | [1] | Speculative | 2026-08-05 | Shown |
| Utility | American Electric Powerterritory 14006: OHIO POWER CO (INVESTOR OWNED, AMERICAN ELECTRIC POWER CO) | [3] derived | Likely | 2022 | Shown |
| Current facility power | 364 MW | [1] estimated | Likely | 2026-08-05 | Shown |
| Current facility power | 78 MW | [1] estimated | Likely | 2024-04-01 | Superseded / alternative |
| Current facility power | 156 MW | [1] estimated | Likely | 2025-03-01 | Superseded / alternative |
| Current facility power | 260 MW | [1] estimated | Likely | 2025-10-01 | Superseded / alternative |
| Current facility power | 260 MW | [1] estimated | Likely | 2026-02-21 | Superseded / alternative |
| Current facility power | 364 MW | [1] estimated | Likely | 2026-05-01 | Superseded / alternative |
| Current IT capacity | 303 MW | [1] estimated | Likely | 2026-08-05 | Shown |
| Current IT capacity | 65 MW | [1] estimated | Likely | 2024-04-01 | Superseded / alternative |
| Current IT capacity | 130 MW | [1] estimated | Likely | 2025-03-01 | Superseded / alternative |
| Current IT capacity | 216 MW | [1] estimated | Likely | 2025-10-01 | Superseded / alternative |
| Current IT capacity | 216 MW | [1] estimated | Likely | 2026-02-21 | Superseded / alternative |
| Current IT capacity | 303 MW | [1] estimated | Likely | 2026-05-01 | Superseded / alternative |
| Planned capacity | 464 MW | [1] estimated | Likely | 2026-08-05 | Shown |
| Estimated annual consumption | 2,232 GWh/yr | [4] estimated | Speculative | 2026-10-12 | Shown |
| ISO / RTO | PJMPJM INTERCONNECTION, LLC | [5] derived | Likely | — | Shown |
| Balancing authority | PJM | [3] derived | Likely | — | Shown |
| Nearest mapped substation | Unnamed substation (138 kV)way/1525005865 | [6] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.3 km | [6] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 345 kV | [6] derived | Likely | 2026-09-28 | Shown |
| Generation queued in county | 1.66 GW | [7] derived | Confirmed | 2026-10-12 | Shown |
| State avg. industrial price | 10.95¢/kWh | [8] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 14.06¢/kWh | [8] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 1.98 GW | [9] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 5 | [1] derived | Likely | 2026-08-05 | Shown |
| Buildings operational | 4 | [1] estimated | Likely | 2026-08-05 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2021-10-01 | Superseded / alternative |
| Buildings operational | 0 | [1] estimated | Likely | 2023-07-01 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2024-04-01 | Superseded / alternative |
| Buildings operational | 2 | [1] estimated | Likely | 2025-03-01 | Superseded / alternative |
| Buildings operational | 3 | [1] estimated | Likely | 2025-10-01 | Superseded / alternative |
| Buildings operational | 3 | [1] estimated | Likely | 2026-02-21 | Superseded / alternative |
| Buildings operational | 4 | [1] estimated | Likely | 2026-05-01 | Superseded / alternative |
| Floor area | 1.17M sq ft | [2] | Confirmed | 2026-10-12 | Shown |
| Site area | 480.4 acres | [2] | Confirmed | 2026-10-12 | Shown |
| Capital cost / investment | $11.5B | [1] estimated | Likely | 2026-08-05 | Shown |
| Parcel / land records | 510-180711 (Franklin County) | [2] | Confirmed | 2026-10-12 | Shown |
| Assessed value (official) | $242.1M | [2] | Confirmed | 2026 | Shown |
| Land use | data center | [2] | Confirmed | 2026-10-12 | Shown |
| Compute (H100-equivalents) | 332,000 | [1] estimated | Likely | 2026-08-05 | Shown |
| Chip types | TPU v5e | [1] | Confirmed | 2026-08-05 | Shown |
| Chip types | TPU v5p | [1] | Confirmed | 2026-08-05 | Shown |
| Chip types | TPU v6e | [1] | Confirmed | 2026-08-05 | Shown |
| Chip types | TPU v7 | [1] | Confirmed | 2026-08-05 | Shown |
| Land acquired | Jun 8, 2022 | [2] derived | Confirmed | 2026-10-12 | Shown |
| Construction start | Oct 1, 2021 | [1] derived | Likely | 2026-08-05 | Shown |
| First operational | Apr 1, 2024 | [1] derived | Likely | 2026-08-05 | Shown |
| Expected completion | Jul 1, 2027 | [1] estimated | Speculative | 2026-08-05 | Shown |