DC
/

What changed

RSS / Atom feed for this view

Capacity, status, permit, grid-request and construction changes over the last three years, each with its source. A change means the same source reported a new value later; two sources disagreeing is not a change. Follow a facility, company, utility, state or ISO by email, or subscribe to the feed in any RSS reader.

Each change is tagged by evidence: ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. filing, deed, permit or grid recordAnnouncedStated by the company or reported in the press; not yet backed by a filing or grid record. company or press claimEst.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. satellite, model or map inferenceHow levels are assigned

Clear
Changes per month by evidence level. Click a month to filter (showing 2024-04; click it again to clear).
2023-112026-10
This view:Download CSVJSONAPI docs
  1. Apr 30, 2024
    CoreWeave Chester VA · VA
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Current IT capacity: 18 MW → 27 MW
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Current facility power: 25 MW → 38 MW
    Source: Epoch AI
  2. Apr 29, 2024
    Google Bristow · VA
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Buildings operational: 0 → 1
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Status: Under construction → Operating + expanding
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.New capacity online: Building 1 is operational, based off of colored motion artifacts from cooling towers. Building 2 is undergoing construction.
    Source: Epoch AI
  3. Apr 24, 2024
    Colossus 1 · TN
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Construction started: Construction starts with a road added on site, retrofitting a former Electrolux building.
    Source: Epoch AI
  4. Apr 20, 2024
    Google New Albany · OH
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Construction started: Building 1 is operational. Based on ~7 months since roof being completed, and cooling towers being installed sometime within that period. Building 2 roof is complete.
    Source: Epoch AI
  5. Apr 8, 2024
    Google Omaha · NE
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Buildings operational: 0 → 1
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Status: Under construction → Operating + expanding
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.New capacity online: Building 1 operational, based on it being 6 months after roof was complete, infrastructure looked complete for 5 months.
    Source: Epoch AI
  6. Apr 3, 2024
    QTS · AZ
    • ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Land acquired: Deed recorded for parcel 121-01-643 (owner of record: Qts Phoenix II Dc1 LLC).
  7. Apr 1, 2024
    Google Columbus · OH
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Buildings operational: 0 → 1
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Status: Under construction → Operating + expanding
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.New capacity online: Building 1 operational. No visible construction and roads/parking complete around the building. Building 2 chillers are beginning construction. Foundation work begins for Building 3.
    Source: Epoch AI
  8. Apr 1, 2024
    Google Fort Wayne · IN
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Construction started: First signs of development/land clearing
    Source: Epoch AI
  9. Apr 1, 2024
    Meta Cheyenne · WY
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Construction started: Land clearing begins.
    Source: Epoch AI
  10. Apr 1, 2024
    QTS Richmond 3 · VA
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Construction started: Land clearing begins.
    Source: Epoch AI