Capacity, status, permit, grid-request and construction changes over the last three years, each with its source. A change means the same source reported a new value later; two sources disagreeing is not a change. Follow a facility, company, utility, state or ISO by email, or subscribe to the feed in any RSS reader.

Each change is tagged by evidence: ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. filing, deed, permit or grid recordAnnouncedStated by the company or reported in the press; not yet backed by a filing or grid record. company or press claimEst.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. satellite, model or map inferenceHow levels are assigned

Clear
Changes per month by evidence level. Click a month to filter (showing 2025-04; click it again to clear).
2023-112026-10
This view:Download CSVJSONAPI docs
  1. Apr 29, 2025
    Google Bristow · VA
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Current IT capacity: 87 MW → 174 MW
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Current facility power: 104 MW → 208 MW
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Buildings operational: 1 → 2
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.New capacity online: Building 2 is operational, based off it being at least 12 months since the roof was complete. Building 3 is finishing construction of cooling towers.
    Source: Epoch AI
  2. Apr 23, 2025
    Menlo Digital MD-DC1 · VA
    • ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Land acquired: Deed/transfer recorded for parcel 0244 03 0002B (no sale price disclosed).
  3. Apr 10, 2025
    Unnamed data center · VA
    • ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Land acquired: Deed recorded for parcel 7596-61-8378.00.
  4. Apr 10, 2025
    Unnamed data center · VA
    • ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Land acquired: Deed recorded for parcel 7596-62-9148.00.
  5. Apr 9, 2025
    AWS New Albany · OH
    • ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Land acquired: Deed/transfer recorded for parcel 095-111756-00.024 (no sale price disclosed).
  6. Apr 1, 2025
    CoreSite VA2 · VA