RSS / Atom feed for this viewCapacity, status, permit, grid-request and construction changes over the last three years, each with its source. A change means the same source reported a new value later; two sources disagreeing is not a change. Follow a facility, company, utility, state or ISO by email, or subscribe to the feed in any RSS reader.
Each change is tagged by evidence: ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. filing, deed, permit or grid recordAnnouncedStated by the company or reported in the press; not yet backed by a filing or grid record. company or press claimEst.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. satellite, model or map inferenceHow levels are assigned
- May 31, 2024Microsoft-Nebius New Jersey · NJ
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Construction started: Land clearing begins for northern two buildings (Building 1-2).
Source: Epoch AI - May 31, 2024OpenAI Stargate Abilene · TX
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Construction started: Land clearing begins for northern two buildings (Building 1-2)
Source: Epoch AI - May 30, 2024Meta Aiken · SC
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Construction started: Land clearing begins
Source: Epoch AI - May 24, 2024Microsoft SAT40 · TX
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Buildings operational: 0 → 1
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Status: Under construction → Operating + expanding
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.New capacity online: Building 1 operational. Estimated 3 months out from February, when there was still construction equipment.
Source: Epoch AI - May 6, 2024Amazon IAD-500 · VA
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Land acquired: Deed/transfer recorded for parcel 0242 14 0001 (no sale price disclosed).
- May 6, 2024Unnamed data center — Redskin Drive · VA
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Land acquired: Deed/transfer recorded for parcel 0242 14 0002 (no sale price disclosed).
- May 6, 2024Unnamed data center — Redskin Drive · VA
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Land acquired: Deed/transfer recorded for parcel 0242 14 0003 (no sale price disclosed).
- May 1, 2024Meta Rosemount · MN
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Construction started: Land clearing begins.
Source: Epoch AI