QTS Richmond 3

Operating + expandingEst.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of May 14, 2026.AI campusCampusSandston, Henrico County, Virginia

QTS Richmond 3 is an operating + expanding ai campus in Sandston, Virginia. Current power: 202 MW (estimated). Planned capacity: 336 MW (estimated). Verification: verified operating. 10 cited sources.

60% profile completeness
36 claims from 11 sources
Last verified against sources: Oct 12, 2026
Newest dated evidence: May 14, 2026
Follow

Get changes to QTS Richmond 3

How often

Double opt-in; one-click unsubscribe in every email. We store only your email and what you follow. More

Or subscribe in a feed reader: RSS / Atom

Cite this
Text
Datacenter Source. “QTS Richmond 3.” /facilities/qts-richmond-3-sandston-va. Data as of 2026-10-12. Accessed 2026-10-12.
BibTeX
@misc{datacentersource_qts_richmond_3_sandston_va_2026,
  title = {{QTS Richmond 3}},
  author = {{Datacenter Source}},
  year = {2026},
  howpublished = {\url{/facilities/qts-richmond-3-sandston-va}},
  note = {Data as of 2026-10-12; accessed 2026-10-12. Compiled from cited sources, including OpenStreetMap contributors (ODbL) and Epoch AI (CC BY 4.0)},
}

Please also cite the original source of any specific figure (linked beside it).

Current facility power
202 MW[1]
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of May 14, 2026.Likelyestimated
Planned capacity
336 MW[1]
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of May 14, 2026.Likelyestimated
Floor area
Not yet sourced
Buildings (planned)
Not yet sourced
Capital cost / investment
$5.5B[1]
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of May 14, 2026.Likelyestimated
First operational
Feb 13, 2026[1]
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of May 14, 2026.Likelyderived

POWER & GRID

Time-to-power · verification · interconnection
Time to power
Remaining capacity: H1 2027 – H2 2028
Medium confidencewindow, not a prediction
Project verification
Verified operating
Operation documented by satellite imagery.
Current stage
Operational
Furthest stage with documented evidence
Utility · ISO
Dominion Energy · PJM
Substation: Techpark Place Substation (230 kV) (nearest, unverified)

Power reality

Announced
336 MW[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
Research estimate of planned capacity (no company figure found)
Interconnection request
No record
Contracted / approved
No record
Under construction
134 MW[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
Buildings 4–5 under construction (satellite-tracked phases)
Operational
202 MW[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
Estimated from buildings observed operational
  • ⚠ No public interconnection record for this load — PJM does not publish large-load requests.
  • ⚠ No permit record linked to this site yet.
AI evidence brief
Summarizes only the evidence on this page. Answers citing anything else are rejected automatically.
How the time-to-power window was estimated
Evidence used
  • Current stage: Operational (furthest stage with documented evidence)[1]
  • Stated date: Next projected milestone: 2027-02-13 (modeled/speculative)[1]
  • Required: 336 MW
Assumptions
  • From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
  • The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Window: H1 2027 – H2 2028

Project verification

Development
  1. Announcedimplied by a later stage
  2. Land acquiredimplied by a later stage
  3. Planning / zoningimplied by a later stage
  4. Permittingimplied by a later stage
Grid interconnection
  1. Interconnection application
  2. Feasibility study
  3. System impact study
  4. Facilities study
  5. Interconnection agreement / service contract
Build & energization
  1. Financing
  2. Under constructionApr 1, 2024
    Model estimate · Satellite imagery
    • Apr 1, 2024 · Reported status: under construction[1]
    • Apr 1, 2024 · Construction start[1]
    • Apr 1, 2024 · Land clearing begins.[1]
    • Feb 13, 2026 · Reported status: expanding[1]
  3. EnergizationFeb 13, 2026
    Satellite imagery
    • Feb 13, 2026 · Building 1 is operational, based on the substation being completed earlier and cars in the carpark. Building 2 and 3 are not operational, based on minor construction work at the pe[1]
    • May 14, 2026 · Building 2 and 3 are operational, based on the previous entry.[1]
  4. OperationalFeb 13, 2026
    Satellite imagery
    • Feb 13, 2026 · Building 1 is operational, based on the substation being completed earlier and cars in the carpark. Building 2 and 3 are not operational, based on minor construction work at the pe[1]
    • May 14, 2026 · Building 2 and 3 are operational, based on the previous entry.[1]

● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.

Grid path

  1. facility
    QTS Richmond 3
  2. substation
    Techpark Place Substation (230 kV)[5]
    Proximity onlyUnverified
    Nearest mapped substation, 0.72 km away. Proximity does not establish that it serves the site.
  3. transmission
    230 kV line[5]
    Proximity onlyUnverified
    Highest-voltage line mapped within 2 km (0.58 km away). Not confirmed as the supply path.
  4. utility
    Dominion Energy[1]
    DocumentedConfirmed
    Named in a source
  5. ISO / RTO
    PJM[3]
    Service territoryLikely
    Balancing authority: PJM
Substation capacity:
not published
Required upgrades:
not yet sourced
Congestion:
not yet sourced (no nodal price data)

Dashed boxes are based on proximity only and do not establish which asset serves the site.

Interconnection records

QueueRelationshipStageMW req.MW appr.QueuedExpected in servicePOI / TOSource · as of
PJM U2-013
Richmond Energy Facility · Gas
Possibly related generation
Speculative
Generation request name/developer shares “richmond” with this facility, in the same county. Not confirmed as serving it.
In service
In Service; feasibility: Document Posted; system impact: Document Posted; facilities: Not Required; ISA/GIA: Document Posted
8 ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Oct 12, 2026.8May 16, 2008In service Dec 29, 2011Northeast 34.5kV
TO: Dominion
[6] Oct 12, 2026

On-site & dedicated generation

  • PJM U2-013 Richmond Energy Facility (Gas, 8 MW requested)[6]
    Generation request name/developer shares “richmond” with this facility, in the same county. Not confirmed as serving it.
    Natural gasArrangement unknown8 MWConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Speculative

LOCAL IMPACT

Water · generation · incentives · regulation · rates

Water & cooling

Not yet collected: we haven't found a source for water use or the cooling type at this site. Know one? Add a source

On-site generation & air permits

Not yet collected: we haven't found a source for on-site generation or an air permit for this site. Know one? Add a source

Incentives

Not yet collected: we haven't found a source for tax abatements, PILOTs or other incentives for this project. Know one? Add a source

Regulatory events

Not yet collected: we haven't found a source for hearings, rezonings, permits or commission proceedings. Know one? Add a source

Utility & rates1

  • GS-5 rate class for customers demanding 25 MW or more[11]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Nov 25, 2025.Nov 25, 2025
    Dominion Energy · Virginia State Corporation Commission · Docket PUR-2025-00058 · Final order issued · effective Jan 1, 2027

    “the new GS-5 rate class will comprise customers demanding 25 megawatts or more. The new rate class will be effective beginning January 1, 2027.”

    Applies to Dominion Energy Virginia's service territory; the facility's utility is the most likely retail provider by location unless a source names it.

Location & imagery

Approximate

Location is approximate (approximate); the marker does not identify the exact site.

Coordinates
37.47916, -77.25095
Address
3525–3543 Portugee Rd, Sandston, VA 23150[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of May 14, 2026.Likely
County
Henrico County
Photographs

No openly licensed ground-level photos matched to this site yet.

Ownership, operation & customers

  1. 1. Property owner of record
    Not identified
  2. 2. Owner / developer
    Not identified
  3. 3. Operator
    Not identified
  4. 4. Tenant / cloud
    Not identified
  5. 5. End customer / workload
    Not identified
Power supply

Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.

All parties with evidence
Utility

No tenants or end users identified in our sources yet.

Power (all fields)

Current facility power
202 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of May 14, 2026.Likelyestimated

Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.

Current IT capacity
144 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of May 14, 2026.Likelyestimated

Estimated IT load currently online, based on buildings observed operational.

Planned capacity
336 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of May 14, 2026.Likelyestimated

Projected facility power at the last tracked milestone (2027-02-13); not necessarily full build-out.

Estimated annual consumption
1,239 GWh/yr[2]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Speculativeestimated

202 MW × 8,760 h × 70% utilization.

Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.

Grid & electricity

ISO / RTO
PJM[3]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived

Location falls inside this ISO/RTO footprint.

Balancing authority
PJM[4]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived

Control area of the containing utility territory.

Nearest mapped substation
Techpark Place Substation (230 kV)[5]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived

Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.

Distance to substation
0.7 km[5]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
Highest-voltage line nearby
230 kV[5]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived

Highest-voltage transmission line mapped within 2 km.

State avg. industrial price
10.07¢/kWh[7]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed

Virginia statewide average, July 2026.

State avg. commercial price
11.68¢/kWh[7]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed

Virginia statewide average, July 2026.

Generation within 50 km
3.35 GW[8]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jan 1, 202502.Confirmedderived

30 EIA-reported plants within 50 km.

Generation queued in county
31 MW[6]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Confirmedderived

4 active generation interconnection requests in Henrico County: Solar 20 MW, Storage 11 MW. Queued projects often don't get built.

Interconnection status
Not yet sourced
Contracted / committed power
Not yet sourced
Nearby infrastructureTypeDistanceVoltage / capacitySource
230 kV line · Virginia Electric and Power CompanyTransmission line0.58 km230 kV[5]
Skipjack Solar Center · AES Distributed EnergyPower plant (Solar)9.4 km175 MW[8]
Darbytown · Virginia Electric & Power CoPower plant (Natural Gas)10.6 km340 MW[8]
Chesterfield · Virginia Electric & Power CoPower plant (Natural Gas)15.9 km386 MW[8]
Hopewell Cogeneration · Luminant Generation Company LLCPower plant (Natural Gas)21 km378 MW[8]
Fort Powhatan Solar · Dominion Renewable EnergyPower plant (Solar)28.7 km150 MW[8]
Westrock-West Point Mill · WestRock-West Point MillPower plant (Biomass)39.9 km101 MW[8]
Doswell Energy Center · Doswell Ltd PartnershipPower plant (Natural Gas)41.7 km1.19 GW[8]
Colonial Trail West · Dominion Energy Inc.Power plant (Solar)48.8 km142 MW[8]
Techpark Place Substation · Dominion EnergySubstation0.72 km230 kV[5]
White Oak Substation · Dominion EnergySubstation0.84 km230 kV[5]
Virginia Electric and Power Company substation · Virginia Electric and Power CompanySubstation0.96 km230 kV[5]
Unnamed substationSubstation1.04 km230 kV[5]
Elko Substation · Virginia Electric and Power CompanySubstation1.21 km230 kV[5]
Unnamed substationSubstation2.33 km34.5 kV[5]
Largest queued generation in this countyFuelQueue statusMWSource
Turner 34.5 kVPJM AG2-193SolarIn study · proposed 2023-1220 MW[6]
Darbytown 230 kVPJM AH1-141StorageIn study · proposed 2024-125 MW[6]
Darbytown 230 kV IIPJM AH1-142StorageIn study · proposed 2024-124 MW[6]
Darbytown 230 kV IIIPJM AH1-143StorageIn study · proposed 2024-122 MW[6]

Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.

Construction & permitting

  1. Announced
    —
  2. Land acquired
    —
  3. Permitting
    —
  4. Construction start
    Apr 1, 2024[1]
  5. First operational
    Feb 13, 2026[1]
  6. Expected completion
    Feb 13, 2027[1]
    Projected
Planned capacity
336 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of May 14, 2026.Likelyestimated

Projected facility power at the last tracked milestone (2027-02-13); not necessarily full build-out.

Buildings operational
3[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of May 14, 2026.Likelyestimated
PhaseStatusAdded MWCompleted / expectedSource
Building 1operational67 MWFeb 13, 2026[1]
Buildings 2–3operational135 MWMay 14, 2026[1]
Buildings 4–5under construction134 MWFeb 13, 2027 (projected)[1]

Real estate

Official assessments
Assessor's value for a tax year

None sourced yet

Recorded transactions
Sale prices from recorded deeds

None sourced yet

Model estimates
Our model — not an appraisal

None sourced yet

Capital cost / investment
$5.5B[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of May 14, 2026.Likelyestimated

Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.

Annual property tax
Not yet sourced

No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.

Size

Floor area
Not yet sourced

Compute

Compute (H100-equivalents)
174,800[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of May 14, 2026.Likelyestimated

What changed (last 3 years)

Follow this facility (RSS)
  • Current IT capacity
    48 MWFeb 13, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→144 MWMay 14, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
  • Current facility power
    67 MWFeb 13, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→202 MWMay 14, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
  • Buildings operational
    0Apr 1, 2024[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→1Feb 13, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→3May 14, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
  • Status
    Under constructionApr 1, 2024[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→Operating + expandingFeb 13, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.

Timeline

Construction start: Apr 1, 2024[1]
First operational: Feb 13, 2026[1]
  1. Apr 1, 2024[1]

    Land clearing begins.

  2. Feb 4, 2025[1]

    Building 1 shell is mostly complete, with some chillers installed on the roof. Building 2 shell is under construction.

  3. Nov 19, 2025[1]

    The substation is still under construction, based on a Google Earth image, so we don't think any buildings are operational yet.

  4. Dec 31, 2025[1]

    The substation looks complete, but we expect Building 1 still needs commissioning before it is fully operational.

  5. Feb 13, 202667 MW facility power· 1 buildings operational[1]

    Building 1 is operational, based on the substation being completed earlier and cars in the carpark. Building 2 and 3 are not operational, based on minor construction work at the perimeter and no cars in the carpark, but we expect they will be operational within 3 months. Building 4 has complete chillers and backup generators, while Building 5 has chillers but only a few backup generators - roughly the state of Building 1 on 2025-02-04.

  6. May 14, 2026202 MW facility power· 3 buildings operational[1]

    Building 2 and 3 are operational, based on the previous entry.

  7. Feb 13, 2027Projected336 MW facility power· 5 buildings operational[1]

    Building 4 and 5 are operational, based on Building 5 being roughly 1 year behind Building 1 in satellite imagery.

All claims (provenance audit)

36
FieldValueSourceConfidenceAs ofStatus
NameQTS Richmond 3[1] Likely2026-05-14Shown
StatusUnder construction[1] derivedLikely2024-04-01Superseded / alternative
StatusUnder construction[1] derivedLikely2025-02-04Superseded / alternative
StatusUnder construction[1] derivedLikely2025-11-19Superseded / alternative
StatusUnder construction[1] derivedLikely2025-12-31Superseded / alternative
StatusOperating + expanding[1] derivedLikely2026-02-13Superseded / alternative
StatusOperating + expanding[1] derivedLikely2026-05-14Shown
Facility typeAI campus[1] derivedLikely2026-05-14Shown
Address3525–3543 Portugee Rd, Sandston, VA 23150[1] Likely2026-05-14Shown
UtilityDominion EnergyEnergy companies: Dominion Energy[1] Confirmed2026-05-14Shown
Current facility power202 MW[1] estimatedLikely2026-05-14Shown
Current facility power67 MW[1] estimatedLikely2026-02-13Superseded / alternative
Current IT capacity144 MW[1] estimatedLikely2026-05-14Shown
Current IT capacity48 MW[1] estimatedLikely2026-02-13Superseded / alternative
Planned capacity336 MW[1] estimatedLikely2026-05-14Shown
Estimated annual consumption1,239 GWh/yr[2] estimatedSpeculative2026-10-12Shown
ISO / RTOPJMPJM INTERCONNECTION, LLC[3] derivedLikely—Shown
Balancing authorityPJM[4] derivedLikely—Shown
Nearest mapped substationTechpark Place Substation (230 kV)way/1265396511[5] derivedLikely2026-09-28Shown
Distance to substation0.7 km[5] derivedLikely2026-09-28Shown
Highest-voltage line nearby230 kV[5] derivedLikely2026-09-28Shown
Generation queued in county31 MW[6] derivedConfirmed2026-10-12Shown
State avg. industrial price10.07¢/kWh[7] Confirmed2026-07Shown
State avg. commercial price11.68¢/kWh[7] Confirmed2026-07Shown
Generation within 50 km3.35 GW[8] derivedConfirmed202502Shown
Buildings operational3[1] estimatedLikely2026-05-14Shown
Buildings operational0[1] estimatedLikely2024-04-01Superseded / alternative
Buildings operational0[1] estimatedLikely2025-02-04Superseded / alternative
Buildings operational0[1] estimatedLikely2025-11-19Superseded / alternative
Buildings operational0[1] estimatedLikely2025-12-31Superseded / alternative
Buildings operational1[1] estimatedLikely2026-02-13Superseded / alternative
Capital cost / investment$5.5B[1] estimatedLikely2026-05-14Shown
Compute (H100-equivalents)174,800[1] estimatedLikely2026-05-14Shown
Construction startApr 1, 2024[1] derivedLikely2026-05-14Shown
First operationalFeb 13, 2026[1] derivedLikely2026-05-14Shown
Expected completionFeb 13, 2027[1] estimatedSpeculative2026-05-14Shown