QTS Richmond 2
QTS Richmond 2 is an operating ai campus in Sandston, Virginia. Current power: 252 MW (estimated). Verification: verified operating. 10 cited sources.
Follow
Get changes to QTS Richmond 2
Or subscribe in a feed reader: RSS / Atom
Cite this
Datacenter Source. “QTS Richmond 2.” /facilities/qts-richmond-2-sandston-va. Data as of 2026-10-12. Accessed 2026-10-12.
@misc{datacentersource_qts_richmond_2_sandston_va_2026,
title = {{QTS Richmond 2}},
author = {{Datacenter Source}},
year = {2026},
howpublished = {\url{/facilities/qts-richmond-2-sandston-va}},
note = {Data as of 2026-10-12; accessed 2026-10-12. Compiled from cited sources, including OpenStreetMap contributors (ODbL) and Epoch AI (CC BY 4.0)},
}Please also cite the original source of any specific figure (linked beside it).
POWER & GRID
Time-to-power · verification · interconnectionPower reality
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- EnergizationFeb 4, 2025
Satellite imagery
- Feb 4, 2025 · Building 1 and 2 are operational, based on the east substation looking complete and the carparks being more full. Building 3 has cooling and generators mostly installed. Building 4[1]
- Dec 31, 2025 · Building 3 and 4 are operational, based on the substation being completed earlier, the buildings looking complete, and carparks being moderately full. Building 5 still has construc[1]
- May 14, 2026 · Building 5 is estimated to be operational, based on the previous entry.[1]
- OperationalFeb 4, 2025
Satellite imagery
- Feb 4, 2025 · Building 1 and 2 are operational, based on the east substation looking complete and the carparks being more full. Building 3 has cooling and generators mostly installed. Building 4[1]
- Dec 31, 2025 · Building 3 and 4 are operational, based on the substation being completed earlier, the buildings looking complete, and carparks being moderately full. Building 5 still has construc[1]
- May 14, 2026 · Building 5 is estimated to be operational, based on the previous entry.[1]
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.
Grid path
- →facilityQTS Richmond 2
- →substationTechpark Place Substation (230 kV)[5]Proximity onlyUnverifiedNearest mapped substation, 0.36 km away. Proximity does not establish that it serves the site.
- →transmission230 kV line[5]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (0.27 km away). Not confirmed as the supply path.
- →
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
| Queue | Relationship | Stage | MW req. | MW appr. | Queued | Expected in service | POI / TO | Source · as of |
|---|---|---|---|---|---|---|---|---|
PJM U2-013 Richmond Energy Facility · Gas | Possibly related generation Speculative Generation request name/developer shares “richmond” with this facility, in the same county. Not confirmed as serving it. | In service In Service; feasibility: Document Posted; system impact: Document Posted; facilities: Not Required; ISA/GIA: Document Posted | 8 ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Oct 12, 2026. | 8 | May 16, 2008 | In service Dec 29, 2011 | Northeast 34.5kV TO: Dominion | [6] Oct 12, 2026 |
On-site & dedicated generation
- PJM U2-013 Richmond Energy Facility (Gas, 8 MW requested)[6]Generation request name/developer shares “richmond” with this facility, in the same county. Not confirmed as serving it.Natural gasArrangement unknown8 MWConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Speculative
LOCAL IMPACT
Water · generation · incentives · regulation · ratesWater & cooling1
- 0 million gal/day[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Apr 1, 2022.Apr 1, 2022modeled water use
Epoch AI's modeled estimate at the latest observed milestone, in million gallons per day. Not a permit or metered figure.
On-site generation & air permits
Not yet collected: we haven't found a source for on-site generation or an air permit for this site. Know one? Add a source
Incentives
Not yet collected: we haven't found a source for tax abatements, PILOTs or other incentives for this project. Know one? Add a source
Regulatory events
Not yet collected: we haven't found a source for hearings, rezonings, permits or commission proceedings. Know one? Add a source
Utility & rates1
- GS-5 rate class for customers demanding 25 MW or more[11]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Nov 25, 2025.Nov 25, 2025Dominion Energy · Virginia State Corporation Commission · Docket PUR-2025-00058 · Final order issued · effective Jan 1, 2027
“the new GS-5 rate class will comprise customers demanding 25 megawatts or more. The new rate class will be effective beginning January 1, 2027.”
Applies to Dominion Energy Virginia's service territory; the facility's utility is the most likely retail provider by location unless a source names it.
Location & imagery
ApproximateLocation is approximate (approximate); the marker does not identify the exact site.
- Coordinates
- 37.48504, -77.24281
- Address
- 6030–6070 Technology Blvd, Sandston, VA 23150[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of May 14, 2026.Likely
- County
- Henrico County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developerNot identified
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workloadNot identified
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Utility
No tenants or end users identified in our sources yet.
Power (all fields)
- Current facility power
- 252 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of May 14, 2026.Likelyestimated
Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.
- Current IT capacity
- 180 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of May 14, 2026.Likelyestimated
Estimated IT load currently online, based on buildings observed operational.
- Estimated annual consumption
- 1,545 GWh/yr[2]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Speculativeestimated
252 MW × 8,760 h × 70% utilization.
- Planned capacity
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
- PJM[3]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived
Location falls inside this ISO/RTO footprint.
- Balancing authority
- PJM[4]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived
Control area of the containing utility territory.
- Nearest mapped substation
- Techpark Place Substation (230 kV)[5]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- 0.4 km[5]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
- Highest-voltage line nearby
- 230 kV[5]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
- 10.07¢/kWh[7]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed
Virginia statewide average, July 2026.
- State avg. commercial price
- 11.68¢/kWh[7]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed
Virginia statewide average, July 2026.
- Generation within 50 km
- 3.35 GW[8]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jan 1, 202502.Confirmedderived
30 EIA-reported plants within 50 km.
- Generation queued in county
- 31 MW[6]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Confirmedderived
4 active generation interconnection requests in Henrico County: Solar 20 MW, Storage 11 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 230 kV line · Virginia Electric and Power Company | Transmission line | 0.27 km | 230 kV | [5] |
| Skipjack Solar Center · AES Distributed Energy | Power plant (Solar) | 9.1 km | 175 MW | [8] |
| Darbytown · Virginia Electric & Power Co | Power plant (Natural Gas) | 11.2 km | 340 MW | [8] |
| Chesterfield · Virginia Electric & Power Co | Power plant (Natural Gas) | 16.9 km | 386 MW | [8] |
| Hopewell Cogeneration · Luminant Generation Company LLC | Power plant (Natural Gas) | 21.8 km | 378 MW | [8] |
| Fort Powhatan Solar · Dominion Renewable Energy | Power plant (Solar) | 28.9 km | 150 MW | [8] |
| Westrock-West Point Mill · WestRock-West Point Mill | Power plant (Biomass) | 39.1 km | 101 MW | [8] |
| Doswell Energy Center · Doswell Ltd Partnership | Power plant (Natural Gas) | 41.4 km | 1.19 GW | [8] |
| Colonial Trail West · Dominion Energy Inc. | Power plant (Solar) | 48.9 km | 142 MW | [8] |
| Techpark Place Substation · Dominion Energy | Substation | 0.36 km | 230 kV | [5] |
| White Oak Substation · Dominion Energy | Substation | 0.4 km | 230 kV | [5] |
| Virginia Electric and Power Company substation · Virginia Electric and Power Company | Substation | 0.44 km | 230 kV | [5] |
| Unnamed substation | Substation | 0.46 km | 230 kV | [5] |
| Elko Substation · Virginia Electric and Power Company | Substation | 0.99 km | 230 kV | [5] |
| Unnamed substation | Substation | 1.47 km | 34.5 kV | [5] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| Turner 34.5 kVPJM AG2-193 | Solar | In study · proposed 2023-12 | 20 MW | [6] |
| Darbytown 230 kVPJM AH1-141 | Storage | In study · proposed 2024-12 | 5 MW | [6] |
| Darbytown 230 kV IIPJM AH1-142 | Storage | In study · proposed 2024-12 | 4 MW | [6] |
| Darbytown 230 kV IIIPJM AH1-143 | Storage | In study · proposed 2024-12 | 2 MW | [6] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction startApr 1, 2022[1]
- First operationalFeb 4, 2025[1]
- Expected completion—
- Buildings operational
- 5[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of May 14, 2026.Likelyestimated
Real estate
None sourced yet
None sourced yet
None sourced yet
- Capital cost / investment
- $6.8B[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of May 14, 2026.Likelyestimated
Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Floor area
- Not yet sourced
Compute
- Compute (H100-equivalents)
- 182,900[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of May 14, 2026.Likelyestimated
What changed (last 3 years)
Follow this facility (RSS)- Current IT capacity72 MWFeb 4, 2025[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→144 MWDec 31, 2025[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→180 MWMay 14, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
- Current facility power101 MWFeb 4, 2025[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→202 MWDec 31, 2025[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→252 MWMay 14, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
- Buildings operational0Apr 1, 2022[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→2Feb 4, 2025[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→4Dec 31, 2025[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→5May 14, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
- StatusUnder constructionApr 1, 2022[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→Operating + expandingFeb 4, 2025[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→OperatingMay 14, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
Timeline
- Apr 1, 2022[1]
Land clearing begins.
- Jan 29, 2024[1]
Building 1 and 2 look complete but we don't think they are operational, as the substation is still under construction.
- Jun 23, 2024[1]
Still not many cars parked at Building 1 and 2, and the east substation looks very close to completion, based on a Google Earth image.
Building 1 and 2 are operational, based on the east substation looking complete and the carparks being more full. Building 3 has cooling and generators mostly installed. Building 4 roof is partly completed.
The west substation looks complete, based on a Google Earth image. This image also shows one corner of Building 5 that still has construction work, so it's probably not operational.
Building 3 and 4 are operational, based on the substation being completed earlier, the buildings looking complete, and carparks being moderately full. Building 5 still has construction work.
Building 5 still has construction work at the perimeter, but given how close it looks to completion, we estimate it's only about 3 months away from operational.
Building 5 is estimated to be operational, based on the previous entry.
All claims (provenance audit)
44| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | QTS Richmond 2 | [1] | Likely | 2026-05-14 | Shown |
| Status | Under construction | [1] derived | Likely | 2022-04-01 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2024-01-29 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2024-06-23 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-02-04 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-11-19 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-12-31 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-02-13 | Superseded / alternative |
| Status | Operating | [1] derived | Likely | 2026-05-14 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-05-14 | Shown |
| Address | 6030–6070 Technology Blvd, Sandston, VA 23150 | [1] | Likely | 2026-05-14 | Shown |
| Utility | Dominion EnergyEnergy companies: Dominion Energy | [1] | Confirmed | 2026-05-14 | Shown |
| Current facility power | 252 MW | [1] estimated | Likely | 2026-05-14 | Shown |
| Current facility power | 101 MW | [1] estimated | Likely | 2025-02-04 | Superseded / alternative |
| Current facility power | 101 MW | [1] estimated | Likely | 2025-11-19 | Superseded / alternative |
| Current facility power | 202 MW | [1] estimated | Likely | 2025-12-31 | Superseded / alternative |
| Current facility power | 202 MW | [1] estimated | Likely | 2026-02-13 | Superseded / alternative |
| Current IT capacity | 180 MW | [1] estimated | Likely | 2026-05-14 | Shown |
| Current IT capacity | 72 MW | [1] estimated | Likely | 2025-02-04 | Superseded / alternative |
| Current IT capacity | 72 MW | [1] estimated | Likely | 2025-11-19 | Superseded / alternative |
| Current IT capacity | 144 MW | [1] estimated | Likely | 2025-12-31 | Superseded / alternative |
| Current IT capacity | 144 MW | [1] estimated | Likely | 2026-02-13 | Superseded / alternative |
| Estimated annual consumption | 1,545 GWh/yr | [2] estimated | Speculative | 2026-10-12 | Shown |
| ISO / RTO | PJMPJM INTERCONNECTION, LLC | [3] derived | Likely | — | Shown |
| Balancing authority | PJM | [4] derived | Likely | — | Shown |
| Nearest mapped substation | Techpark Place Substation (230 kV)way/1265396511 | [5] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.4 km | [5] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 230 kV | [5] derived | Likely | 2026-09-28 | Shown |
| Generation queued in county | 31 MW | [6] derived | Confirmed | 2026-10-12 | Shown |
| State avg. industrial price | 10.07¢/kWh | [7] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 11.68¢/kWh | [7] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 3.35 GW | [8] derived | Confirmed | 202502 | Shown |
| Buildings operational | 5 | [1] estimated | Likely | 2026-05-14 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2022-04-01 | Superseded / alternative |
| Buildings operational | 0 | [1] estimated | Likely | 2024-01-29 | Superseded / alternative |
| Buildings operational | 0 | [1] estimated | Likely | 2024-06-23 | Superseded / alternative |
| Buildings operational | 2 | [1] estimated | Likely | 2025-02-04 | Superseded / alternative |
| Buildings operational | 2 | [1] estimated | Likely | 2025-11-19 | Superseded / alternative |
| Buildings operational | 4 | [1] estimated | Likely | 2025-12-31 | Superseded / alternative |
| Buildings operational | 4 | [1] estimated | Likely | 2026-02-13 | Superseded / alternative |
| Capital cost / investment | $6.8B | [1] estimated | Likely | 2026-05-14 | Shown |
| Compute (H100-equivalents) | 182,900 | [1] estimated | Likely | 2026-05-14 | Shown |
| Construction start | Apr 1, 2022 | [1] derived | Likely | 2026-05-14 | Shown |
| First operational | Feb 4, 2025 | [1] derived | Likely | 2026-05-14 | Shown |