STACK Infrastructure NVA02
STACK Infrastructure NVA02 is an operating + expanding ai campus in Manassas, Virginia. Current power: 118 MW (estimated). Planned capacity: 487 MW (estimated). Verification: verified operating. 12 cited sources.
Follow
Get changes to STACK Infrastructure NVA02
Or subscribe in a feed reader: RSS / Atom
Cite this
Datacenter Source. “STACK Infrastructure NVA02.” /facilities/stack-infrastructure-nva02-manassas-va. Data as of 2026-10-12. Accessed 2026-10-12.
@misc{datacentersource_stack_infrastructure_nva02_manassas_va_2026,
title = {{STACK Infrastructure NVA02}},
author = {{Datacenter Source}},
year = {2026},
howpublished = {\url{/facilities/stack-infrastructure-nva02-manassas-va}},
note = {Data as of 2026-10-12; accessed 2026-10-12. Compiled from cited sources, including OpenStreetMap contributors (ODbL) and Epoch AI (CC BY 4.0)},
}Please also cite the original source of any specific figure (linked beside it).
POWER & GRID
Time-to-power · verification · interconnectionPower reality
- ⚠ No public interconnection record for this load — PJM does not publish large-load requests.
- ⚠ No permit record linked to this site yet.
How the time-to-power window was estimated
- From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
- The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Project verification
- Announcedimplied by a later stage
- Land acquiredMay 6, 2025
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- Under constructionOct 19, 2019
Model estimate · Satellite imagery
- Oct 19, 2019 · Reported status: under construction[1]
- Oct 19, 2019 · Construction start[1]
- Oct 19, 2019 · Land clearing begins by Peterson Companies for Stack Infrastructure, which is noted in the [news](https://www.bisnow.com/washington-dc/news/data-center/peterson-cos-partnering-to-b[1]
- Oct 1, 2024 · Reported status: expanding[1]
- EnergizationOct 1, 2024
Satellite imagery
- Oct 1, 2024 · Building 1 is operational, which is assumed to be three months after the last backup diesel generators are finished. The generators were first seen to be finished July 1 from satel[1]
- OperationalOct 1, 2024
Satellite imagery
- Oct 1, 2024 · Building 1 is operational, which is assumed to be three months after the last backup diesel generators are finished. The generators were first seen to be finished July 1 from satel[1]
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Government record, Model estimate, Satellite imagery.
Grid path
- →facilitySTACK Infrastructure NVA02
- →substationOn-site substation[1]Satellite imageryLikely1 substation outline traced inside the campus on satellite imagery
- →transmissionNot identifiedUnknownUnverifiedNo transmission line mapped within 2 km.
- →
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
LOCAL IMPACT
Water · generation · incentives · regulation · ratesWater & cooling
Not yet collected: we haven't found a source for water use or the cooling type at this site. Know one? Add a source
On-site generation & air permits
Not yet collected: we haven't found a source for on-site generation or an air permit for this site. Know one? Add a source
Incentives
Not yet collected: we haven't found a source for tax abatements, PILOTs or other incentives for this project. Know one? Add a source
Regulatory events
Not yet collected: we haven't found a source for hearings, rezonings, permits or commission proceedings. Know one? Add a source
Utility & rates1
- GS-5 rate class for customers demanding 25 MW or more[13]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Nov 25, 2025.Nov 25, 2025Dominion Energy · Virginia State Corporation Commission · Docket PUR-2025-00058 · Final order issued · effective Jan 1, 2027
“the new GS-5 rate class will comprise customers demanding 25 megawatts or more. The new rate class will be effective beginning January 1, 2027.”
Applies to Dominion Energy Virginia's service territory; the facility's utility is the most likely retail provider by location unless a source names it.
Location & imagery
Mapped outline- Coordinates
- 38.74436, -77.54020
- Address
- 9590 Hornbaker Rd, Manassas, VA 20109[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Feb 14, 2026.Likely
- County
- Prince William County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developerNot identified
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workloadNot identified
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Utility
Location falls inside this utility's retail service territory.
No tenants or end users identified in our sources yet.
Power (all fields)
- Current facility power
- 118 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Feb 14, 2026.Likelyestimated
Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.
- Current IT capacity
- 85 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Feb 14, 2026.Likelyestimated
Estimated IT load currently online, based on buildings observed operational.
- Planned capacity
- 487 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Feb 14, 2026.Likelyestimated
Projected facility power at the last tracked milestone (2028-01-01); not necessarily full build-out.
- Estimated annual consumption
- 724 GWh/yr[3]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Speculativeestimated
118 MW × 8,760 h × 70% utilization.
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
- PJM[4]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived
Location falls inside this ISO/RTO footprint.
- Balancing authority
- PJM[2]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived
Control area of the containing utility territory.
- Nearest mapped substation
- Hourglass Substation (230 kV)[5]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- 2.1 km[5]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
- State avg. industrial price
- 10.07¢/kWh[7]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed
Virginia statewide average, July 2026.
- State avg. commercial price
- 11.68¢/kWh[7]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed
Virginia statewide average, July 2026.
- Generation within 50 km
- 2.83 GW[8]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jan 1, 202502.Confirmedderived
35 EIA-reported plants within 50 km.
- Generation queued in county
- 1.35 GW[6]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Confirmedderived
16 active generation interconnection requests in Prince William County: Storage 1,350 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| Covanta Fairfax Energy · Covanta Fairfax Inc | Power plant (Biomass) | 26.5 km | 98 MW | [8] |
| Remington · Virginia Electric & Power Co | Power plant (Natural Gas) | 30 km | 604 MW | [8] |
| Marsh Run Generation Facility · Old Dominion Electric Coop | Power plant (Natural Gas) | 31.1 km | 481 MW | [8] |
| Possum Point · Virginia Electric & Power Co | Power plant (Natural Gas) | 32.3 km | 645 MW | [8] |
| Potomac Energy Center, LLC · Potomac Energy Center LLC | Power plant (Natural Gas) | 34.9 km | 766 MW | [8] |
| Covanta Alexandria/Arlington Energy · Covanta Alexandria/Arlington | Power plant (Biomass) | 36.2 km | 29 MW | [8] |
| Ripley · MN8 Energy LLC | Power plant (Solar) | 45 km | 28 MW | [8] |
| Nih Cogeneration Facility · National Institutes of Health | Power plant (Natural Gas) | 48 km | 28 MW | [8] |
| Hourglass Substation | Substation | 2.12 km | 230 kV | [5] |
| Sandlot Substation · Dominion Energy | Substation | 2.62 km | 230 kV | [5] |
| Innovation Substation | Substation | 2.65 km | 230 kV | [5] |
| Wellington Delivery Point | Substation | 2.68 km | 115 kV | [5] |
| Dominion Delivery Point · Dominion Energy | Substation | 2.68 km | 115 kV | [5] |
| City of Manassas - (VA) substation · City of Manassas - (VA) | Substation | 2.71 km | 13.2 kV | [5] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| Gainesville-Loudoun 230 kVPJM AI2-231 | Storage | In study · proposed 2023-10 | 200 MW | [6] |
| Nokesville-Vint Hill 230 kVPJM AG2-113 | Storage | In study · proposed 2022-08 | 150 MW | [6] |
| Catharpin 230 kVPJM AG2-284 | Storage | In study · proposed 2023-12 | 150 MW | [6] |
| Liberty 230 kVPJM AG2-304 | Storage | In study · proposed 2023-12 | 150 MW | [6] |
| Possum Point 230 kVPJM AG2-306 | Storage | In study · proposed 2023-12 | 150 MW | [6] |
| Possum Point 230kVPJM AH2-034 | Storage | In study · proposed 2028-12 | 100 MW | [6] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquiredMay 6, 2025[9]
- Permitting—
- Construction startOct 19, 2019[1]
- First operationalOct 1, 2024[1]
- Expected completionJan 1, 2028[1]Projected
- Planned capacity
- 487 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Feb 14, 2026.Likelyestimated
Projected facility power at the last tracked milestone (2028-01-01); not necessarily full build-out.
- Buildings (planned)
- 6[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Feb 14, 2026.Likelyderived
Count of building outlines traced on satellite imagery.
- Buildings operational
- 1[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Feb 14, 2026.Likelyestimated
Real estate
None sourced yet
None sourced yet
None sourced yet
| Parcel | Record owner | Acres | Zoning / use | Building sq ft | Source |
|---|---|---|---|---|---|
| 7595-65-9789.00 Prince William County, VA | — | 14.22 | — | — | [9] |
| 7595-75-3611 Prince William County, VA | — | 16.44 | — | — | [9] |
| 7595-76-2590 Prince William County, VA | — | 20.77 | — | — | [9] |
| 7595-54-7478 Prince William County, VA | — | 49.76 | — | — | [9] |
- Site area
- 101.2 acres[9]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Oct 12, 2026.Confirmed
Sum of county land area across parcels.
- Capital cost / investment
- $3.2B[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Feb 14, 2026.Likelyestimated
Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.
- Annual property tax
- Not yet sourced
Size
- Parcel / land records
- 7595-65-9789.00 (Prince William County),7595-75-3611 (Prince William County),7595-76-2590 (Prince William County),7595-54-7478 (Prince William County)[9]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Oct 12, 2026.Confirmed
- Floor area
- Not yet sourced
Compute
- Chip types
- H100[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Feb 14, 2026.Confirmed
- Compute (H100-equivalents)
- 61,100[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Feb 14, 2026.Likelyestimated
What changed (last 3 years)
Follow this facility (RSS)- Buildings operational
- StatusUnder constructionOct 19, 2019[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→Operating + expandingOct 1, 2024[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
Timeline
- Oct 19, 2019[1]
Land clearing begins by Peterson Companies for Stack Infrastructure, which is noted in the news and visible on satellite imagery.
Building 1 is operational, which is assumed to be three months after the last backup diesel generators are finished. The generators were first seen to be finished July 1 from satellite imagery (a clear image of this can be seen on July 29 via Google Earth).
All buildings have begun construction (with groundwork starting for AI building 6), as depicted by satellite imagery.
Estimate: All 6 AI data center buildings will be finished in 2028, assuming a groundbreak-to-operational timeline of 18-24 months. One is complete, three are clearly under construction, and the last two data centers are still breaking ground and laying foundations.
- May 6, 2025[9]
Deed recorded for parcel 7595-65-9789.00.
- May 6, 2025[9]
Deed recorded for parcel 7595-75-3611.
- May 6, 2025[9]
Deed recorded for parcel 7595-76-2590.
- May 6, 2025[9]
Deed recorded for parcel 7595-54-7478.
Buildings on this campus
2All claims (provenance audit)
37| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | STACK Infrastructure NVA02 | [1] | Likely | 2026-02-14 | Shown |
| Status | Under construction | [1] derived | Likely | 2019-10-19 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2024-10-01 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-02-14 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-02-14 | Shown |
| Address | 9590 Hornbaker Rd, Manassas, VA 20109 | [1] | Likely | 2026-02-14 | Shown |
| Utility | Dominion Energyterritory 19876: VIRGINIA ELECTRIC & POWER CO (INVESTOR OWNED, DOMINION RESOURCE | [2] derived | Likely | 2022 | Shown |
| Current facility power | 118 MW | [1] estimated | Likely | 2026-02-14 | Shown |
| Current facility power | 118 MW | [1] estimated | Likely | 2024-10-01 | Superseded / alternative |
| Current IT capacity | 85 MW | [1] estimated | Likely | 2026-02-14 | Shown |
| Current IT capacity | 85 MW | [1] estimated | Likely | 2024-10-01 | Superseded / alternative |
| Planned capacity | 487 MW | [1] estimated | Likely | 2026-02-14 | Shown |
| Estimated annual consumption | 724 GWh/yr | [3] estimated | Speculative | 2026-10-12 | Shown |
| ISO / RTO | PJMPJM INTERCONNECTION, LLC | [4] derived | Likely | — | Shown |
| Balancing authority | PJM | [2] derived | Likely | — | Shown |
| Nearest mapped substation | Hourglass Substation (230 kV)way/1189694187 | [5] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 2.1 km | [5] derived | Likely | 2026-09-28 | Shown |
| Generation queued in county | 1.35 GW | [6] derived | Confirmed | 2026-10-12 | Shown |
| State avg. industrial price | 10.07¢/kWh | [7] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 11.68¢/kWh | [7] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 2.83 GW | [8] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 6 | [1] derived | Likely | 2026-02-14 | Shown |
| Buildings operational | 1 | [1] estimated | Likely | 2026-02-14 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2019-10-19 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2024-10-01 | Superseded / alternative |
| Site area | 101.2 acres | [9] | Confirmed | 2026-10-12 | Shown |
| Capital cost / investment | $3.2B | [1] estimated | Likely | 2026-02-14 | Shown |
| Parcel / land records | 7595-65-9789.00 (Prince William County) | [9] | Confirmed | 2026-10-12 | Shown |
| Parcel / land records | 7595-75-3611 (Prince William County) | [9] | Confirmed | 2026-10-12 | Shown |
| Parcel / land records | 7595-76-2590 (Prince William County) | [9] | Confirmed | 2026-10-12 | Shown |
| Parcel / land records | 7595-54-7478 (Prince William County) | [9] | Confirmed | 2026-10-12 | Shown |
| Compute (H100-equivalents) | 61,100 | [1] estimated | Likely | 2026-02-14 | Shown |
| Chip types | H100 | [1] | Confirmed | 2026-02-14 | Shown |
| Land acquired | May 6, 2025 | [9] derived | Confirmed | 2026-10-12 | Shown |
| Construction start | Oct 19, 2019 | [1] derived | Likely | 2026-02-14 | Shown |
| First operational | Oct 1, 2024 | [1] derived | Likely | 2026-02-14 | Shown |
| Expected completion | Jan 1, 2028 | [1] estimated | Speculative | 2026-02-14 | Shown |