Dallas–Fort Worth
Market boundary: facilities within 70 km of the metro center (editorial definition).
Online = operating sites; pipeline = remaining planned MW at sites under construction or planned. Percentages under each total show how much of it is backed by each evidence level.
ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. filing, deed, permit or grid recordAnnouncedStated by the company or reported in the press; not yet backed by a filing or grid record. company or press claimEst.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. satellite, model or map inferenceHow levels are assignedConstruction pipeline by expected completion
MW from phases with a projected completion date
Power reality
Announced capacity vs. what grid records, construction and operation document. Facility-level sums; sources differ in coverage.
How to read this
Each bar sums one kind of evidence across facilities. Announced is the largest MW a company, utility, government or press source reported. Interconnection requests are MW in active large-load queue requests. Of the grid operators we ingest, only NYISO publishes these project by project. Contracted / approved means an executed interconnection agreement or a reported utility or power contract. Under construction and Operational come from construction records, imagery or operator reports.
The gap between announced and documented MW is capacity that has been claimed but not yet backed by a grid, construction or operating record. It is not proof a project won't happen. On-site generation is listed separately and never added to grid capacity. Method
Time to power puts each site's pending MW (announced minus operational) into a bucket by the midpoint of its evidence-based window. The window starts at the furthest documented stage and adds editorial ranges for what remains (e.g. announced: 2–5 yrs; land acquired: 2–4.5 yrs; planning / zoning: 1.75–4 yrs). Insufficient evidence means no dated stage evidence, not a delay. Windows are ranges, not forecasts. All ranges and rules
- Announced1.45 GW
- Interconnection requests—
- Contracted / approved—
- Under construction120 MW
- Operational583 MW
856 MW announced at 4 sites has no grid, construction or operating record yet.
Bucketed by the midpoint of each site's evidence-based window. Windows are ranges, not forecasts.
- SkyBox Lancaster300 MW / 0
- Stream Wilmer240 MW / 0
- STACK Lancaster216 MW / 0
- SkyBox Plano100 MW / 0
Interconnection queues
Active requests to connect to the grid (ERCOT). Requests are applications, not commitments.
How to read this
A queue request asks a grid operator (ISO/RTO) to connect a new generator or large load to the transmission system. It then moves through studies (feasibility, system impact, facilities) before an interconnection agreement, construction and service. Filing is an application, not a commitment to build. Generation totals here are active requests only.
Why most aren't built: in the queue files we ingest, no grid operator in this scope publishes its withdrawn requests. These are shares of each published file, not completion rates. ERCOT is left out because their files don't include withdrawn requests. Queue sources
Data-center load requests are shown only where an ISO publishes them project by project (NYISO). Elsewhere, large loads go through utilities, and the ISO figures above (e.g. ERCOT's large-load tracking) are quoted from the operator's own documents.
Coverage
How much of this scope our sources describe. Low coverage means data isn't disclosed or not yet collected, not that there's nothing there.
Confirmed evidence = at least one fact about the facility itself from a filing, deed, permit, interconnection record, or government or utility record. Regional context (state prices, nearby plants, utility territory maps) doesn't count. Most facilities come from OpenStreetMap, which records that a building exists but rarely its power, owner or status.
Largest operators & owners
Online + pipeline MW at linked facilities
- CoreWeave367 MW + 28 MW · 1 sites
- Google216 MW + 92 MW · 6 sites
- Digital Realty— · 8 sites
- Aligned Data Centers— · 4 sites
- NTT Global Data Centers— · 4 sites
- Flexential— · 3 sites
- Meta— · 3 sites
- CyrusOne— · 3 sites
- Stream Data Centers— · 3 sites
- Centersquare— · 2 sites
- Lumen Technologies— · 2 sites
- Prime— · 2 sites
Largest customers & end users
Tenants and workload owners, where sourced
- OpenAI367 MW + 28 MW · 1 sites
Utility exposure
Most likely retail utility by location (approximate)
- Denton County Elec Coop, INC367 MW + 28 MW · 28 sites
- United Electric Coop Service INC - (Tx)216 MW + 92 MW · 17 sites
- Farmers Electric Coop, INC - (Tx)— · 23 sites
- City of Garland - (Tx)— · 7 sites
- Oncor Electric Delivery— · 4 sites
Grid operators (ISO / RTO)
By facility location
- ERCOT583 MW + 120 MW · 79 sites
Largest facilities
By online + pipeline MW; badge = evidence behind each figure
| Facility | Status | Online | Pipeline |
|---|---|---|---|
| CoreWeave Denton TX | Operating + expandingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. | 367 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. | 28 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. |
| Google Red Oak | Operating + expandingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. | 93 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. | 92 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. |
| Google Midlothian | OperatingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. | 123 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. | — |
Facilities by status
- Operating73
- Operating + expanding2
- Unknown4
Campuses & sites (53)
Campus pages list their buildings
- CoreWeave Denton TX367 MW online EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. · 28 MW pipeline EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
- Google Red Oak93 MW online EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. · 92 MW pipeline EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
- Google Midlothian123 MW online EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
- Aligned Data Centers DFW-04building
- Alinged Data Center DFW-03building
- Amazon Web Servicesbuilding
- Charles Schwab Data Centerbuilding
- Cisco Allenbuilding
- CITIGROUP TECHNOLOGY INCbuilding
- Compass Data Centerbuilding
- Compass Data Centerbuilding
- Compass Data Centerbuilding
- Compass Data Centerbuilding
- Compass Data Centerbuilding
- Compass Data Centerbuilding
- Compass Data Centerbuilding
- Compass Data Centerbuilding
- Compass Data Centerbuilding
- Compass Data Centerbuilding
- CoreSpace Dallasbuilding
- CyrusOne DFW7building
- Cyxtera Dallas-Fort Worth Data Centerbuilding
- DataBankbuilding
- DataBank Dallas Empire Central Data Centerbuilding
- DataBank Plano Data Centerbuilding
- Equinix Infomartbuilding
- Evoque Allen DA1building
- Experian McKinney Data Centerbuilding
- Flexential Dallas - Downtown Dallassite
- Flexential Dallas - Planobuilding
- Flexential Dallas - Richardsonbuilding
- Live Oak Data Centerbuilding
- Lumen Dallas - 3180 Irving Blvd.building
- Lumen Dallas 6building
- Novartisbuilding
- QTS Data Centerbuilding
- QTS Irving - Dallas Data Center Campusbuilding
- Rackspace Richardson DFW3building
- Rad Web Hostingsite
- ScaleMatrix US-South 01building
- SkyBox Lancastercampus
- SkyBox Planocampus
- STACK Lancastercampus
- Stream Data Centers DFWAbuilding
- Stream DFW IVbuilding
- Stream Wilmercampus
- TierPoint DA2building
- TierPoint Dallas Data Centerbuilding
- Unnamed data centerbuilding
- Unnamed data center — 800 Guardians Waybuilding
- Unnamed data center — 904 Quality Waybuilding
- Verizon Wireless Mew Buildingbuilding
- VIRTBIZsite