DC
/

Meta Temple

OperatingEst.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 30, 2026.AI campusCampusTemple, Bell County, Texas

Meta Temple is an operating ai campus in Temple, Texas. Operated or owned by Meta; used by Meta. Current power: 231 MW (estimated). Verification: verified operating. 11 cited sources.

70% profile completeness
44 claims from 11 sources
Last verified against sources: Oct 12, 2026
Newest dated evidence: Sep 30, 2026
Follow

Get changes to Meta Temple

How often

Double opt-in; one-click unsubscribe in every email. We store only your email and what you follow. More

Or subscribe in a feed reader: RSS / Atom

Cite this
Text
Datacenter Source. “Meta Temple.” /facilities/meta-temple-temple-tx. Data as of 2026-10-12. Accessed 2026-10-12.
BibTeX
@misc{datacentersource_meta_temple_temple_tx_2026,
  title = {{Meta Temple}},
  author = {{Datacenter Source}},
  year = {2026},
  howpublished = {\url{/facilities/meta-temple-temple-tx}},
  note = {Data as of 2026-10-12; accessed 2026-10-12. Compiled from cited sources, including OpenStreetMap contributors (ODbL) and Epoch AI (CC BY 4.0)},
}

Please also cite the original source of any specific figure (linked beside it).

Current facility power
231 MW[1]
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 30, 2026.Likelyestimated
Planned capacity
Not yet sourced
Building footprint
666,600 sq ft[5]
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Likelyderived
Buildings (planned)
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 30, 2026.Likelyderived
Capital cost / investment
$6.7B[1]
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 30, 2026.Likelyestimated
First operational
Dec 9, 2025[1]
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 30, 2026.Likelyderived

POWER & GRID

Time-to-power · verification · interconnection
Time to power
Energized — operating
High confidence
Project verification
Verified operating
Operation documented by satellite imagery.
Current stage
Operational
Furthest stage with documented evidence
Utility · ISO
Pedernales Electric Coop, INC · ERCOT
Substation: On-site substation

Power reality

Announced
No record
Interconnection request
No record
Contracted / approved
No record
Under construction
No record
Operational
231 MW[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
Estimated from buildings observed operational
AI evidence brief
Summarizes only the evidence on this page. Answers citing anything else are rejected automatically.

Project verification

Development
  1. Announcedimplied by a later stage
  2. Land acquiredimplied by a later stage
  3. Planning / zoningimplied by a later stage
  4. Permittingimplied by a later stage
Grid interconnection
  1. Interconnection application
  2. Feasibility study
  3. System impact study
  4. Facilities study
  5. Interconnection agreement / service contract
Build & energization
  1. Financing
  2. Under constructionApr 1, 2022
    Model estimate · Satellite imagery
    • Apr 1, 2022 · Reported status: under construction[1]
    • Apr 1, 2022 · Construction start[1]
    • Apr 1, 2022 · Land clearing begins.[1]
    • Dec 9, 2025 · Reported status: expanding[1]
  3. EnergizationDec 9, 2025
    Satellite imagery
    • Dec 9, 2025 · Building 1 and 2 are operational. Activity related to the air quality permit (namely, emergency diesel generators) was reported to have started as of 2025-12-09. This is our best e[1]
    • Sep 30, 2026 · Building 3 is operational. Based on the stated completion date in this [regulatory filing](https://www.tdlr.texas.gov/TABS/Search/Project/TABS2026008019)[1]
  4. OperationalDec 9, 2025
    Satellite imagery
    • Dec 9, 2025 · Building 1 and 2 are operational. Activity related to the air quality permit (namely, emergency diesel generators) was reported to have started as of 2025-12-09. This is our best e[1]
    • Sep 30, 2026 · Building 3 is operational. Based on the stated completion date in this [regulatory filing](https://www.tdlr.texas.gov/TABS/Search/Project/TABS2026008019)[1]

● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.

Grid path

  1. facility
    Meta Temple
  2. substation
    On-site substation[1][5]
    Satellite imageryLikely
    4 substation outlines traced inside the campus on satellite imagery; OSM maps Unnamed substation 0.35 km away
  3. transmission
    138 kV line[5]
    Proximity onlyUnverified
    Highest-voltage line mapped within 2 km (0.33 km away). Not confirmed as the supply path.
  4. utility
    Pedernales Electric Coop, INC[2]
    Service territoryLikely
    Retail service territory containing the site
  5. ISO / RTO
    ERCOT[4]
    Service territoryLikely
    Balancing authority: ERCO
Substation capacity:
not published
Required upgrades:
not yet sourced
Congestion:
not yet sourced (no nodal price data)

Dashed boxes are based on proximity only and do not establish which asset serves the site.

Interconnection records

No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.

On-site & dedicated generation

No on-site, behind-the-meter or dedicated generation found in sources.

LOCAL IMPACT

Water · generation · incentives · regulation · rates

Water & cooling

Not yet collected: we haven't found a source for water use or the cooling type at this site. Know one? Add a source

On-site generation & air permits

Not yet collected: we haven't found a source for on-site generation or an air permit for this site. Know one? Add a source

Incentives

Not yet collected: we haven't found a source for tax abatements, PILOTs or other incentives for this project. Know one? Add a source

Regulatory events

Not yet collected: we haven't found a source for hearings, rezonings, permits or commission proceedings. Know one? Add a source

Utility & rates

Not yet collected: we haven't found a source for a large-load tariff or commission docket for Pedernales Electric Coop, INC. Know one? Add a source

Location & imagery

Mapped outline
Coordinates
31.13066, -97.37037
Address
2310 Eberhardt Rd, Temple, TX 76504[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 30, 2026.Likely
County
Bell County
Photographs

No openly licensed ground-level photos matched to this site yet.

Ownership, operation & customers

  1. 1. Property owner of record
    Not identified
  2. 2. Owner / developer
  3. 3. Operator
    Not identified
  4. 4. Tenant / cloud
    Not identified
  5. 5. End customer / workload
Power supply
Capital & construction
Contractor:

Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.

All parties with evidence
Owner
Meta[1]Confirmed
End user
Meta[1]Confirmed
Utility

Most likely retail provider among 5 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: Heart of Texas Electric Coop, Bartlett Electric Coop, INC, Oncor Electric Delivery Company LLC, City of Bartlett - (Tx).

Contractor
JE Dunn[1]Confirmed

Power (all fields)

Current facility power
231 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 30, 2026.Likelyestimated

Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.

Current IT capacity
178 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 30, 2026.Likelyestimated

Estimated IT load currently online, based on buildings observed operational.

Estimated annual consumption
1,416 GWh/yr[3]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Speculativeestimated

231 MW × 8,760 h × 70% utilization.

Planned capacity
Not yet sourced

Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.

Grid & electricity

ISO / RTO
ERCOT[4]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived

Location falls inside this ISO/RTO footprint.

Balancing authority
ERCO[2]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived

Control area of the containing utility territory.

Nearest mapped substation
Unnamed substation (138 kV)[5]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived

Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.

Distance to substation
0.4 km[5]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
Highest-voltage line nearby
138 kV[5]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived

Highest-voltage transmission line mapped within 2 km.

State avg. industrial price
7.07¢/kWh[7]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed

Texas statewide average, July 2026.

State avg. commercial price
8.47¢/kWh[7]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed

Texas statewide average, July 2026.

Generation within 50 km
3.35 GW[8]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jan 1, 202502.Confirmedderived

20 EIA-reported plants within 50 km.

Generation queued in county
2.34 GW[6]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 1, 2026.Confirmedderived

9 active generation interconnection requests in Bell County: Storage 1,439 MW, Gas 637 MW, Solar 264 MW. Queued projects often don't get built.

Interconnection status
Not yet sourced
Contracted / committed power
Not yet sourced
Nearby infrastructureTypeDistanceVoltage / capacitySource
138 kV lineTransmission line0.33 km138 kV[5]
Temple Power Station · Temple Generation Holdings LLCPower plant (Natural Gas)9.7 km1.58 GW[8]
Big Elm Solar · Big Elm Solar, LLCPower plant (Solar)14.6 km200 MW[8]
Five Wells Solar Center - Hybrid · Five Wells Solar Center, LLCPower plant (Solar)18.1 km579 MW[8]
Orion III Solar Project · Ben Milam Solar 3 LLCPower plant (Solar)30.1 km250 MW[8]
Bpl Crown Solar LLC · BPL Crown Solar LLCPower plant (Solar)36.4 km100 MW[8]
Bpl Sol Solar LLC · BPL Sol Solar LLCPower plant (Solar)36.4 km100 MW[8]
Orion I Solar Project · Ben Milam Solar 1 LLCPower plant (Solar)38.2 km200 MW[8]
Orion II Solar Project · Ben Milam Solar 2 LLCPower plant (Solar)43 km250 MW[8]
Unnamed substationSubstation0.35 km138 kV[5]
Unnamed substationSubstation0.41 km138 kV[5]
Unnamed substationSubstation0.77 km138 kV[5]
Unnamed substationSubstation0.93 km138 kV[5]
Largest queued generation in this countyFuelQueue statusMWSource
Riviera GasERCOT 29INR0206 · BKV-BPP Power GasIn study · proposed 2030-06637 MW[6]
Lavita BESSERCOT 26INR0465 · Lavita BESS, LLCStorageIn study · proposed 2028-07606 MW[6]
Bell County Morgan StorageERCOT 26INR0615 · DM-BCTRM, LLCStorageIn study · proposed 2029-12256 MW[6]
Bell County Leifester StorageERCOT 26INR0614 · DM-BCRCML, LLCStorageIn study · proposed 2029-09205 MW[6]
Goldeneye BESSERCOT 25INR0100 · Black Mountain Energy Storage IIStorageIA signed · proposed 2028-05202 MW[6]
Cosper SolarERCOT 25INR0281 · Gransolar Texas Twenty LLCSolarIA signed · proposed 2027-11148 MW[6]

Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.

Construction & permitting

  1. Announced
    —
  2. Land acquired
    —
  3. Permitting
    —
  4. Construction start
    Apr 1, 2022[1]
  5. First operational
    Dec 9, 2025[1]
  6. Expected completion
    —
Buildings (planned)
3[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 30, 2026.Likelyderived

Count of building outlines traced on satellite imagery.

Buildings operational
3[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 30, 2026.Likelyestimated
PhaseStatusAdded MWCompleted / expectedSource
Buildings 1–2operational198 MWDec 9, 2025[1]
Building 3operational33 MWSep 30, 2026[1]

Real estate

Official assessments
Assessor's value for a tax year

None sourced yet

Recorded transactions
Sale prices from recorded deeds

None sourced yet

Model estimates
Our model — not an appraisal

None sourced yet

Capital cost / investment
$6.7B[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 30, 2026.Likelyestimated

Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.

Annual property tax
Not yet sourced

No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.

Size

Building footprint
666,600 sq ft[5]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Likelyderived

Sum of 2 building outlines mapped in OpenStreetMap within this campus.

Floor area
Not yet sourced

Compute

Chip types
B300[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 30, 2026.Confirmed
Compute (H100-equivalents)
202,500[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 30, 2026.Likelyestimated

What changed (last 3 years)

Follow this facility (RSS)
  • Current IT capacity
    152 MWDec 9, 2025[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→178 MWSep 30, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
  • Current facility power
    198 MWDec 9, 2025[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→231 MWSep 30, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
  • Compute (H100-equivalents)
    173,200Feb 24, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→202,500Sep 30, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
  • Capital cost / investment
    $5.8BFeb 24, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→$6.7BSep 30, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
  • Buildings operational
    0Apr 1, 2022[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→2Dec 9, 2025[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→3Sep 30, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
  • Status
    Under constructionApr 1, 2022[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→Operating + expandingDec 9, 2025[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→OperatingSep 30, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.

Timeline

Construction start: Apr 1, 2022[1]
First operational: Dec 9, 2025[1]
  1. Apr 1, 2022[1]

    Land clearing begins.

  2. Feb 5, 2023[1]

    A traditional H-shaped Meta data center is partially built.

  3. Apr 1, 2023[1]

    The traditional Meta data center has been demolished mid-construction, in favor of Meta's new AI-optimized design.

  4. Nov 15, 2025[1]

    Building 1 and 2 look complete from outside, with all electrical and cooling equipment installed. Space is cleared for Building 3.

  5. Dec 9, 2025198 MW facility power· 2 buildings operational[1]

    Building 1 and 2 are operational. Activity related to the air quality permit (namely, emergency diesel generators) was reported to have started as of 2025-12-09. This is our best estimate, but note that the planned completion date in this regulatory filing is 2026-03-01.

  6. Feb 24, 2026198 MW facility power· 2 buildings operational[1]

    Building 3 is under construction. An outline is visible for the building which has similar dimensions to those deployed at the Meta Prometheus site.

  7. Sep 30, 2026231 MW facility power· 3 buildings operational[1]

    Building 3 is operational. Based on the stated completion date in this regulatory filing

All claims (provenance audit)

44
FieldValueSourceConfidenceAs ofStatus
NameMeta Temple[1] Likely2026-09-30Shown
StatusUnder construction[1] derivedLikely2022-04-01Superseded / alternative
StatusUnder construction[1] derivedLikely2023-02-05Superseded / alternative
StatusUnder construction[1] derivedLikely2023-04-01Superseded / alternative
StatusUnder construction[1] derivedLikely2025-11-15Superseded / alternative
StatusOperating + expanding[1] derivedLikely2025-12-09Superseded / alternative
StatusOperating + expanding[1] derivedLikely2026-02-24Superseded / alternative
StatusOperating[1] derivedLikely2026-09-30Shown
Facility typeAI campus[1] derivedLikely2026-09-30Shown
Address2310 Eberhardt Rd, Temple, TX 76504[1] Likely2026-09-30Shown
OwnerMetaOwner: Meta[1] Confirmed2026-09-30Shown
End usersMetaUsers: Meta[1] Confirmed2026-09-30Shown
UtilityPedernales Electric Coop, INCterritory 14626: PEDERNALES ELECTRIC COOP, INC (COOPERATIVE, PEDERNALES ELECTRIC[2] derivedUnverified2022Shown
ConstructionJE DunnConstruction companies: JE Dunn[1] Confirmed2026-09-30Shown
Current facility power231 MW[1] estimatedLikely2026-09-30Shown
Current facility power198 MW[1] estimatedLikely2025-12-09Superseded / alternative
Current facility power198 MW[1] estimatedLikely2026-02-24Superseded / alternative
Current IT capacity178 MW[1] estimatedLikely2026-09-30Shown
Current IT capacity152 MW[1] estimatedLikely2025-12-09Superseded / alternative
Current IT capacity152 MW[1] estimatedLikely2026-02-24Superseded / alternative
Estimated annual consumption1,416 GWh/yr[3] estimatedSpeculative2026-10-12Shown
ISO / RTOERCOTELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.[4] derivedLikely—Shown
Balancing authorityERCO[2] derivedLikely—Shown
Nearest mapped substationUnnamed substation (138 kV)way/1469988913[5] derivedLikely2026-09-28Shown
Distance to substation0.4 km[5] derivedLikely2026-09-28Shown
Highest-voltage line nearby138 kV[5] derivedLikely2026-09-28Shown
Generation queued in county2.34 GW[6] derivedConfirmed2026-10-01Shown
State avg. industrial price7.07¢/kWh[7] Confirmed2026-07Shown
State avg. commercial price8.47¢/kWh[7] Confirmed2026-07Shown
Generation within 50 km3.35 GW[8] derivedConfirmed202502Shown
Buildings (planned)3[1] derivedLikely2026-09-30Shown
Buildings operational3[1] estimatedLikely2026-09-30Shown
Buildings operational0[1] estimatedLikely2022-04-01Superseded / alternative
Buildings operational0[1] estimatedLikely2023-02-05Superseded / alternative
Buildings operational0[1] estimatedLikely2023-04-01Superseded / alternative
Buildings operational0[1] estimatedLikely2025-11-15Superseded / alternative
Buildings operational2[1] estimatedLikely2025-12-09Superseded / alternative
Buildings operational2[1] estimatedLikely2026-02-24Superseded / alternative
Building footprint666,600 sq ftway/1469988846 way/1469988847[5] derivedLikely2026-10-12Shown
Capital cost / investment$6.7B[1] estimatedLikely2026-09-30Shown
Compute (H100-equivalents)202,500[1] estimatedLikely2026-09-30Shown
Chip typesB300[1] Confirmed2026-09-30Shown
Construction startApr 1, 2022[1] derivedLikely2026-09-30Shown
First operationalDec 9, 2025[1] derivedLikely2026-09-30Shown