Meta Temple
Meta Temple is an operating ai campus in Temple, Texas. Operated or owned by Meta; used by Meta. Current power: 231 MW (estimated). Verification: verified operating. 11 cited sources.
Follow
Get changes to Meta Temple
Or subscribe in a feed reader: RSS / Atom
Cite this
Datacenter Source. “Meta Temple.” /facilities/meta-temple-temple-tx. Data as of 2026-10-12. Accessed 2026-10-12.
@misc{datacentersource_meta_temple_temple_tx_2026,
title = {{Meta Temple}},
author = {{Datacenter Source}},
year = {2026},
howpublished = {\url{/facilities/meta-temple-temple-tx}},
note = {Data as of 2026-10-12; accessed 2026-10-12. Compiled from cited sources, including OpenStreetMap contributors (ODbL) and Epoch AI (CC BY 4.0)},
}Please also cite the original source of any specific figure (linked beside it).
POWER & GRID
Time-to-power · verification · interconnectionPower reality
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- EnergizationDec 9, 2025
Satellite imagery
- Dec 9, 2025 · Building 1 and 2 are operational. Activity related to the air quality permit (namely, emergency diesel generators) was reported to have started as of 2025-12-09. This is our best e[1]
- Sep 30, 2026 · Building 3 is operational. Based on the stated completion date in this [regulatory filing](https://www.tdlr.texas.gov/TABS/Search/Project/TABS2026008019)[1]
- OperationalDec 9, 2025
Satellite imagery
- Dec 9, 2025 · Building 1 and 2 are operational. Activity related to the air quality permit (namely, emergency diesel generators) was reported to have started as of 2025-12-09. This is our best e[1]
- Sep 30, 2026 · Building 3 is operational. Based on the stated completion date in this [regulatory filing](https://www.tdlr.texas.gov/TABS/Search/Project/TABS2026008019)[1]
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.
Grid path
- →facilityMeta Temple
- →substationSatellite imageryLikely4 substation outlines traced inside the campus on satellite imagery; OSM maps Unnamed substation 0.35 km away
- →transmission138 kV line[5]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (0.33 km away). Not confirmed as the supply path.
- →utilityPedernales Electric Coop, INC[2]Service territoryLikelyRetail service territory containing the site
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
LOCAL IMPACT
Water · generation · incentives · regulation · ratesWater & cooling
Not yet collected: we haven't found a source for water use or the cooling type at this site. Know one? Add a source
On-site generation & air permits
Not yet collected: we haven't found a source for on-site generation or an air permit for this site. Know one? Add a source
Incentives
Not yet collected: we haven't found a source for tax abatements, PILOTs or other incentives for this project. Know one? Add a source
Regulatory events
Not yet collected: we haven't found a source for hearings, rezonings, permits or commission proceedings. Know one? Add a source
Utility & rates
Not yet collected: we haven't found a source for a large-load tariff or commission docket for Pedernales Electric Coop, INC. Know one? Add a source
Location & imagery
Mapped outline- Coordinates
- 31.13066, -97.37037
- Address
- 2310 Eberhardt Rd, Temple, TX 76504[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 30, 2026.Likely
- County
- Bell County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workload
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Utility
Most likely retail provider among 5 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: Heart of Texas Electric Coop, Bartlett Electric Coop, INC, Oncor Electric Delivery Company LLC, City of Bartlett - (Tx).
Power (all fields)
- Current facility power
- 231 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 30, 2026.Likelyestimated
Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.
- Current IT capacity
- 178 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 30, 2026.Likelyestimated
Estimated IT load currently online, based on buildings observed operational.
- Estimated annual consumption
- 1,416 GWh/yr[3]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Speculativeestimated
231 MW × 8,760 h × 70% utilization.
- Planned capacity
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
- ERCOT[4]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived
Location falls inside this ISO/RTO footprint.
- Balancing authority
- ERCO[2]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived
Control area of the containing utility territory.
- Nearest mapped substation
- Unnamed substation (138 kV)[5]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- 0.4 km[5]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
- Highest-voltage line nearby
- 138 kV[5]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
- 7.07¢/kWh[7]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed
Texas statewide average, July 2026.
- State avg. commercial price
- 8.47¢/kWh[7]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed
Texas statewide average, July 2026.
- Generation within 50 km
- 3.35 GW[8]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jan 1, 202502.Confirmedderived
20 EIA-reported plants within 50 km.
- Generation queued in county
- 2.34 GW[6]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 1, 2026.Confirmedderived
9 active generation interconnection requests in Bell County: Storage 1,439 MW, Gas 637 MW, Solar 264 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 138 kV line | Transmission line | 0.33 km | 138 kV | [5] |
| Temple Power Station · Temple Generation Holdings LLC | Power plant (Natural Gas) | 9.7 km | 1.58 GW | [8] |
| Big Elm Solar · Big Elm Solar, LLC | Power plant (Solar) | 14.6 km | 200 MW | [8] |
| Five Wells Solar Center - Hybrid · Five Wells Solar Center, LLC | Power plant (Solar) | 18.1 km | 579 MW | [8] |
| Orion III Solar Project · Ben Milam Solar 3 LLC | Power plant (Solar) | 30.1 km | 250 MW | [8] |
| Bpl Crown Solar LLC · BPL Crown Solar LLC | Power plant (Solar) | 36.4 km | 100 MW | [8] |
| Bpl Sol Solar LLC · BPL Sol Solar LLC | Power plant (Solar) | 36.4 km | 100 MW | [8] |
| Orion I Solar Project · Ben Milam Solar 1 LLC | Power plant (Solar) | 38.2 km | 200 MW | [8] |
| Orion II Solar Project · Ben Milam Solar 2 LLC | Power plant (Solar) | 43 km | 250 MW | [8] |
| Unnamed substation | Substation | 0.35 km | 138 kV | [5] |
| Unnamed substation | Substation | 0.41 km | 138 kV | [5] |
| Unnamed substation | Substation | 0.77 km | 138 kV | [5] |
| Unnamed substation | Substation | 0.93 km | 138 kV | [5] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| Riviera GasERCOT 29INR0206 · BKV-BPP Power | Gas | In study · proposed 2030-06 | 637 MW | [6] |
| Lavita BESSERCOT 26INR0465 · Lavita BESS, LLC | Storage | In study · proposed 2028-07 | 606 MW | [6] |
| Bell County Morgan StorageERCOT 26INR0615 · DM-BCTRM, LLC | Storage | In study · proposed 2029-12 | 256 MW | [6] |
| Bell County Leifester StorageERCOT 26INR0614 · DM-BCRCML, LLC | Storage | In study · proposed 2029-09 | 205 MW | [6] |
| Goldeneye BESSERCOT 25INR0100 · Black Mountain Energy Storage II | Storage | IA signed · proposed 2028-05 | 202 MW | [6] |
| Cosper SolarERCOT 25INR0281 · Gransolar Texas Twenty LLC | Solar | IA signed · proposed 2027-11 | 148 MW | [6] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction startApr 1, 2022[1]
- First operationalDec 9, 2025[1]
- Expected completion—
- Buildings (planned)
- 3[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 30, 2026.Likelyderived
Count of building outlines traced on satellite imagery.
- Buildings operational
- 3[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 30, 2026.Likelyestimated
Real estate
None sourced yet
None sourced yet
None sourced yet
- Capital cost / investment
- $6.7B[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 30, 2026.Likelyestimated
Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Building footprint
- 666,600 sq ft[5]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Likelyderived
Sum of 2 building outlines mapped in OpenStreetMap within this campus.
- Floor area
- Not yet sourced
Compute
- Chip types
- B300[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 30, 2026.Confirmed
- Compute (H100-equivalents)
- 202,500[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 30, 2026.Likelyestimated
What changed (last 3 years)
Follow this facility (RSS)- Current IT capacity152 MWDec 9, 2025[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→178 MWSep 30, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
- Current facility power198 MWDec 9, 2025[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→231 MWSep 30, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
- Compute (H100-equivalents)173,200Feb 24, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→202,500Sep 30, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
- Capital cost / investment$5.8BFeb 24, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→$6.7BSep 30, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
- Buildings operational0Apr 1, 2022[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→2Dec 9, 2025[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→3Sep 30, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
- StatusUnder constructionApr 1, 2022[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→Operating + expandingDec 9, 2025[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→OperatingSep 30, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
Timeline
- Apr 1, 2022[1]
Land clearing begins.
- Feb 5, 2023[1]
A traditional H-shaped Meta data center is partially built.
- Apr 1, 2023[1]
The traditional Meta data center has been demolished mid-construction, in favor of Meta's new AI-optimized design.
- Nov 15, 2025[1]
Building 1 and 2 look complete from outside, with all electrical and cooling equipment installed. Space is cleared for Building 3.
Building 1 and 2 are operational. Activity related to the air quality permit (namely, emergency diesel generators) was reported to have started as of 2025-12-09. This is our best estimate, but note that the planned completion date in this regulatory filing is 2026-03-01.
Building 3 is under construction. An outline is visible for the building which has similar dimensions to those deployed at the Meta Prometheus site.
Building 3 is operational. Based on the stated completion date in this regulatory filing
All claims (provenance audit)
44| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Meta Temple | [1] | Likely | 2026-09-30 | Shown |
| Status | Under construction | [1] derived | Likely | 2022-04-01 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2023-02-05 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2023-04-01 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2025-11-15 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-12-09 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-02-24 | Superseded / alternative |
| Status | Operating | [1] derived | Likely | 2026-09-30 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-09-30 | Shown |
| Address | 2310 Eberhardt Rd, Temple, TX 76504 | [1] | Likely | 2026-09-30 | Shown |
| Owner | MetaOwner: Meta | [1] | Confirmed | 2026-09-30 | Shown |
| End users | MetaUsers: Meta | [1] | Confirmed | 2026-09-30 | Shown |
| Utility | Pedernales Electric Coop, INCterritory 14626: PEDERNALES ELECTRIC COOP, INC (COOPERATIVE, PEDERNALES ELECTRIC | [2] derived | Unverified | 2022 | Shown |
| Construction | JE DunnConstruction companies: JE Dunn | [1] | Confirmed | 2026-09-30 | Shown |
| Current facility power | 231 MW | [1] estimated | Likely | 2026-09-30 | Shown |
| Current facility power | 198 MW | [1] estimated | Likely | 2025-12-09 | Superseded / alternative |
| Current facility power | 198 MW | [1] estimated | Likely | 2026-02-24 | Superseded / alternative |
| Current IT capacity | 178 MW | [1] estimated | Likely | 2026-09-30 | Shown |
| Current IT capacity | 152 MW | [1] estimated | Likely | 2025-12-09 | Superseded / alternative |
| Current IT capacity | 152 MW | [1] estimated | Likely | 2026-02-24 | Superseded / alternative |
| Estimated annual consumption | 1,416 GWh/yr | [3] estimated | Speculative | 2026-10-12 | Shown |
| ISO / RTO | ERCOTELECTRIC RELIABILITY COUNCIL OF TEXAS, INC. | [4] derived | Likely | — | Shown |
| Balancing authority | ERCO | [2] derived | Likely | — | Shown |
| Nearest mapped substation | Unnamed substation (138 kV)way/1469988913 | [5] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.4 km | [5] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 138 kV | [5] derived | Likely | 2026-09-28 | Shown |
| Generation queued in county | 2.34 GW | [6] derived | Confirmed | 2026-10-01 | Shown |
| State avg. industrial price | 7.07¢/kWh | [7] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 8.47¢/kWh | [7] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 3.35 GW | [8] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 3 | [1] derived | Likely | 2026-09-30 | Shown |
| Buildings operational | 3 | [1] estimated | Likely | 2026-09-30 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2022-04-01 | Superseded / alternative |
| Buildings operational | 0 | [1] estimated | Likely | 2023-02-05 | Superseded / alternative |
| Buildings operational | 0 | [1] estimated | Likely | 2023-04-01 | Superseded / alternative |
| Buildings operational | 0 | [1] estimated | Likely | 2025-11-15 | Superseded / alternative |
| Buildings operational | 2 | [1] estimated | Likely | 2025-12-09 | Superseded / alternative |
| Buildings operational | 2 | [1] estimated | Likely | 2026-02-24 | Superseded / alternative |
| Building footprint | 666,600 sq ftway/1469988846 way/1469988847 | [5] derived | Likely | 2026-10-12 | Shown |
| Capital cost / investment | $6.7B | [1] estimated | Likely | 2026-09-30 | Shown |
| Compute (H100-equivalents) | 202,500 | [1] estimated | Likely | 2026-09-30 | Shown |
| Chip types | B300 | [1] | Confirmed | 2026-09-30 | Shown |
| Construction start | Apr 1, 2022 | [1] derived | Likely | 2026-09-30 | Shown |
| First operational | Dec 9, 2025 | [1] derived | Likely | 2026-09-30 | Shown |