Google is an operating hyperscale in Ohio. Operated or owned by Google. Power capacity has not been disclosed or collected yet. Verification: verified operating. 7 cited sources.
Part of Google Columbus
Follow
Get changes to Google
Or subscribe in a feed reader: RSS / Atom
Cite this
Datacenter Source. “Google.” /facilities/google-franklin-county-oh. Data as of 2026-10-12. Accessed 2026-10-12.
@misc{datacentersource_google_franklin_county_oh_2026,
title = {{Google}},
author = {{Datacenter Source}},
year = {2026},
howpublished = {\url{/facilities/google-franklin-county-oh}},
note = {Data as of 2026-10-12; accessed 2026-10-12. Compiled from cited sources, including OpenStreetMap contributors (ODbL) and Epoch AI (CC BY 4.0)},
}Please also cite the original source of any specific figure (linked beside it).
POWER & GRID
Time-to-power · verification · interconnectionPower reality
Project verification
- Announcedimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- Under constructionimplied by a later stage
- Energizationimplied by a later stage
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Government record, Community map.
Grid path
- →facilityGoogle
- →substationUnnamed substation (138 kV)[1]Proximity onlyUnverifiedNearest mapped substation, 0.18 km away. Proximity does not establish that it serves the site.
- →transmission345 kV line[1]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (1.87 km away). Not confirmed as the supply path.
- →utilityAmerican Electric Power[3]Service territoryLikelyRetail service territory containing the site
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
LOCAL IMPACT
Water · generation · incentives · regulation · ratesWater & cooling
Not yet collected: we haven't found a source for water use or the cooling type at this site. Know one? Add a source
On-site generation & air permits
Not yet collected: we haven't found a source for on-site generation or an air permit for this site. Know one? Add a source
Incentives
Not yet collected: we haven't found a source for tax abatements, PILOTs or other incentives for this project. Know one? Add a source
Regulatory events
Not yet collected: we haven't found a source for hearings, rezonings, permits or commission proceedings. Know one? Add a source
Utility & rates1
- AEP Ohio data center tariff[8]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 9, 2025.Jul 9, 2025American Electric Power · Public Utilities Commission of Ohio · Docket 24-508-EL-ATA · Order issued; moratorium on new data center connections to be lifted
“AEP Ohio is ordered to file updated tariffs and lift its moratorium on connecting new data centers as soon as possible.”
Applies in AEP Ohio's territory (AEP operating company in Ohio).
Location & imagery
Mapped outline- Coordinates
- 39.85238, -82.99465
- County
- Franklin County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of record
- 2. Owner / developerNot identified
- 3. Operator
- 4. Tenant / cloudNot identified
- 5. End customer / workloadNot identified
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Property owner of record
- Utility
Location falls inside this utility's retail service territory.
No tenants or end users identified in our sources yet.
Power (all fields)
- Current facility power
- Not yet sourced
- Planned capacity
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
- PJM[4]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived
Location falls inside this ISO/RTO footprint.
- Balancing authority
- PJM[3]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived
Control area of the containing utility territory.
- Nearest mapped substation
- Unnamed substation (138 kV)[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- 0.2 km[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
- Highest-voltage line nearby
- 345 kV[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
- 10.95¢/kWh[6]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed
Ohio statewide average, July 2026.
- State avg. commercial price
- 14.06¢/kWh[6]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed
Ohio statewide average, July 2026.
- Generation within 50 km
- 1.98 GW[7]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jan 1, 202502.Confirmedderived
15 EIA-reported plants within 50 km.
- Generation queued in county
- 1.66 GW[5]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Confirmedderived
8 active generation interconnection requests in Franklin County: Solar 845 MW, Storage 810 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 138 kV line | Transmission line | 0.2 km | 138 kV | [1] |
| Cyprus 138kV Extension · American Electric Power | Transmission line | 0.49 km | 138 kV | [1] |
| 345 kV line · American Electric Power | Transmission line | 1.87 km | 345 kV | [1] |
| Darby Power, LLC · Darby Power, LLC | Power plant (Natural Gas) | 22 km | 480 MW | [7] |
| Big Plain Solar, LLC · Leeward Asset Management, LLC | Power plant (Solar) | 28.5 km | 196 MW | [7] |
| Fox Squirrel Solar · EDF Renewable Asset Holdings, Inc. | Power plant (Solar) | 32.9 km | 577 MW | [7] |
| O'Shaughnessy Hydro · City of Columbus - (OH) | Power plant (Hydroelectric) | 35.3 km | 5 MW | [7] |
| Atlanta Farms Solar · Dominion Renewable Energy | Power plant (Solar) | 36 km | 200 MW | [7] |
| Yellowbud Solar, LLC · Yellowbud Solar LLC | Power plant (Solar) | 39.4 km | 274 MW | [7] |
| Madison Fields Solar Project, LLC · Madison Fields Solar Project, LLC | Power plant (Solar) | 48.7 km | 180 MW | [7] |
| Salt City Solar Project - Hybrid · Salt City Solar LLC | Power plant (Solar) | 48.7 km | 50 MW | [7] |
| Unnamed substation | Substation | 0.18 km | 138 kV | [1] |
| Cyprus Switching Station · AEP Ohio | Substation | 0.5 km | 138 kV | [1] |
| Unnamed substation | Substation | 0.63 km | 138 kV | [1] |
| Unnamed substation | Substation | 0.7 km | 138 kV | [1] |
| Parsons Substation · AEP Ohio | Substation | 0.83 km | 138 kV | [1] |
| Unnamed substation | Substation | 2.85 km | 69 kV | [1] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| Beatty 345 kVPJM AG2-376 | Storage | In study · proposed 2024-11 | 400 MW | [5] |
| Cole 345 kVPJM AH1-318 | Storage | In study · proposed 2025-12 | 310 MW | [5] |
| Cole Road 345 kVPJM AI2-171 | Solar | In study · proposed 2023-12 | 310 MW | [5] |
| Cole 345 kVPJM AF1-275 | Solar | In study · proposed 2022-12 | 250 MW | [5] |
| Pleasant Prairie SolarPJM AE2-214 | Solar | IA signed · proposed 2026-12 | 200 MW | [5] |
| Hayden 345 kVPJM AH1-270 | Solar | In study · proposed 2023-12 | 85 MW | [5] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquiredJun 8, 2022[2]
- Permitting—
- Construction start—
- First operational—
- Expected completion—
Real estate
None sourced yet
None sourced yet
| Parcel | Record owner | Acres | Zoning / use | Building sq ft | Source |
|---|---|---|---|---|---|
| 510-180711 Franklin County, OH | MAGELLAN ENTERPRISES LLC Tax bills to: GOOGLE LLC PO BOX 28190 SCOTTSDALE AZ 85255-0153 | 480.39 | data center | 1,172,656 | [2] |
- Site area
- 480.4 acres[2]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Oct 12, 2026.Confirmed
Sum of county land area across parcels.
- Land use
- data center[2]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Oct 12, 2026.Confirmed
- Annual property tax
- Not yet sourced
- Amazon Web Services · 26.8 km · parcel 050-011455$226,596 · Oct 18, 2022 [2]
- DartPoints Dublin · 29.3 km · parcel 273-001702$15.3M · Oct 29, 2020 [2]
- Google NBY-4 · 29.9 km · parcel 222-004984$27.4M · Dec 13, 2018 [2]
- TJX Corporate Techno · 32.1 km · parcel 222-004441$2.1M · Jul 23, 2010 [2]
- Compugen New Albany · 32.1 km · parcel 222-004644$2.2M · Oct 1, 2014 [2]
- Compugen New Albany · 32.4 km · parcel 222-001940$6.8M · Feb 6, 2023 [2]
Size
- Floor area
- 1.17M sq ft[2]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Oct 12, 2026.Confirmed
Building area in county assessment records.
- Building footprint
- 290,200 sq ft[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Likelyderived
Computed from the mapped OSM building outline.
- Parcel / land records
- 510-180711 (Franklin County)[2]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Oct 12, 2026.Confirmed
What changed (last 3 years)
Follow this facility (RSS)No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.
Timeline
- Jun 8, 2022[2]
Deed/transfer recorded for parcel 510-180711 (no sale price disclosed).
Other buildings on this campus
2- Google ColumbusOperating + expanding
- Google Lockbourne, OHOperating
All claims (provenance audit)
22| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Googleway/1252196814 name=Google | [1] | Likely | 2026-10-12 | Shown |
| Status | Operating | [1] derived | Unverified | 2026-10-12 | Shown |
| Facility type | Hyperscale | [1] derived | Unverified | 2026-10-12 | Shown |
| Property owner of record | Magellan Enterprises LLCParcel 510-180711: MAGELLAN ENTERPRISES LLC (tax mailing name: GOOGLE LLC) | [2] | Confirmed | 2026-10-12 | Shown |
| Operator | Googleoperator=Google | [1] | Likely | 2026-10-12 | Shown |
| Utility | American Electric Powerterritory 14006: OHIO POWER CO (INVESTOR OWNED, AMERICAN ELECTRIC POWER CO) | [3] derived | Likely | 2022 | Shown |
| ISO / RTO | PJMPJM INTERCONNECTION, LLC | [4] derived | Likely | — | Shown |
| Balancing authority | PJM | [3] derived | Likely | — | Shown |
| Nearest mapped substation | Unnamed substation (138 kV)way/1302788522 | [1] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.2 km | [1] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 345 kV | [1] derived | Likely | 2026-09-28 | Shown |
| Generation queued in county | 1.66 GW | [5] derived | Confirmed | 2026-10-12 | Shown |
| State avg. industrial price | 10.95¢/kWh | [6] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 14.06¢/kWh | [6] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 1.98 GW | [7] derived | Confirmed | 202502 | Shown |
| Floor area | 1.17M sq ft | [2] | Confirmed | 2026-10-12 | Shown |
| Building footprint | 290,200 sq ft | [1] derived | Likely | 2026-10-12 | Shown |
| Site area | 480.4 acres | [2] | Confirmed | 2026-10-12 | Shown |
| Parcel / land records | 510-180711 (Franklin County) | [2] | Confirmed | 2026-10-12 | Shown |
| Assessed value (official) | $242.1M | [2] | Confirmed | 2026 | Shown |
| Land use | data center | [2] | Confirmed | 2026-10-12 | Shown |
| Land acquired | Jun 8, 2022 | [2] derived | Confirmed | 2026-10-12 | Shown |