NAO 3
NAO 3 is an operating hyperscale in Ohio. Operated or owned by Meta. Power capacity has not been disclosed or collected yet. Verification: verified operating. 7 cited sources.
Part of Meta Prometheus
Follow
Get changes to NAO 3
Or subscribe in a feed reader: RSS / Atom
Cite this
Datacenter Source. “NAO 3.” /facilities/nao-3-licking-county-oh. Data as of 2026-10-12. Accessed 2026-10-12.
@misc{datacentersource_nao_3_licking_county_oh_2026,
title = {{NAO 3}},
author = {{Datacenter Source}},
year = {2026},
howpublished = {\url{/facilities/nao-3-licking-county-oh}},
note = {Data as of 2026-10-12; accessed 2026-10-12. Compiled from cited sources, including OpenStreetMap contributors (ODbL) and Epoch AI (CC BY 4.0)},
}Please also cite the original source of any specific figure (linked beside it).
POWER & GRID
Time-to-power · verification · interconnectionPower reality
Project verification
- Announcedimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Government record, Community map.
Grid path
- →facilityNAO 3
- →substationUnnamed substation (138 kV)[1]Proximity onlyUnverifiedNearest mapped substation, 0.89 km away. Proximity does not establish that it serves the site.
- →transmissionJug Street - Kirk 345kV transmission line[1]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (0.84 km away). Not confirmed as the supply path.
- →utilityAmerican Electric Power[3]Service territoryLikelyRetail service territory containing the site
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
LOCAL IMPACT
Water · generation · incentives · regulation · ratesWater & cooling
Not yet collected: we haven't found a source for water use or the cooling type at this site. Know one? Add a source
On-site generation & air permits
Not yet collected: we haven't found a source for on-site generation or an air permit for this site. Know one? Add a source
Incentives
Not yet collected: we haven't found a source for tax abatements, PILOTs or other incentives for this project. Know one? Add a source
Regulatory events
Not yet collected: we haven't found a source for hearings, rezonings, permits or commission proceedings. Know one? Add a source
Utility & rates1
- AEP Ohio data center tariff[8]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 9, 2025.Jul 9, 2025American Electric Power · Public Utilities Commission of Ohio · Docket 24-508-EL-ATA · Order issued; moratorium on new data center connections to be lifted
“AEP Ohio is ordered to file updated tariffs and lift its moratorium on connecting new data centers as soon as possible.”
Applies in AEP Ohio's territory (AEP operating company in Ohio).
Location & imagery
Mapped outline- Coordinates
- 40.06568, -82.74903
- County
- Licking County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of record
- 2. Owner / developerNot identified
- 3. Operator
- 4. Tenant / cloudNot identified
- 5. End customer / workloadNot identified
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Property owner of record
- Utility
Most likely retail provider among 2 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: Licking Rural Electric INC.
No tenants or end users identified in our sources yet.
Power (all fields)
- Current facility power
- Not yet sourced
- Planned capacity
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
- PJM[4]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived
Location falls inside this ISO/RTO footprint.
- Balancing authority
- PJM[3]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived
Control area of the containing utility territory.
- Nearest mapped substation
- Unnamed substation (138 kV)[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- 0.9 km[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
- Highest-voltage line nearby
- 345 kV[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
- 10.95¢/kWh[6]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed
Ohio statewide average, July 2026.
- State avg. commercial price
- 14.06¢/kWh[6]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed
Ohio statewide average, July 2026.
- Generation within 50 km
- 21 MW[7]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jan 1, 202502.Confirmedderived
8 EIA-reported plants within 50 km.
- Generation queued in county
- 2.52 GW[5]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Confirmedderived
14 active generation interconnection requests in Licking County: Solar 1,773 MW, Storage 750 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 138 kV line | Transmission line | 0.57 km | 138 kV | [1] |
| Jug Street - Kirk 345kV transmission line · American Electric Power | Transmission line | 0.84 km | 345 kV | [1] |
| Denison Solar Array · AEP Onsite Partners, LLC | Power plant (Solar) | 19.7 km | 2 MW | [7] |
| Dodge Park Engine No 1 · City of Columbus - (OH) | Power plant (Petroleum) | 25.9 km | 2 MW | [7] |
| St-1/1a Engine No 1 · City of Columbus - (OH) | Power plant (Petroleum) | 26.1 km | 1 MW | [7] |
| 3100 Valleyview Drive · Madison Energy Investments LLC | Power plant (Solar) | 26.7 km | 1 MW | [7] |
| Renick Run Pumping Station 03-04 · City of Columbus - (OH) | Power plant (Petroleum) | 27 km | 2 MW | [7] |
| Ps St-8 Engine No 1 · City of Columbus - (OH) | Power plant (Petroleum) | 28.1 km | 2 MW | [7] |
| O'Shaughnessy Hydro · City of Columbus - (OH) | Power plant (Hydroelectric) | 33.6 km | 5 MW | [7] |
| Suburban Landfill Gas Recovery · WM Renewable Energy LLC | Power plant (Biomass) | 46.2 km | 6 MW | [7] |
| Unnamed substation | Substation | 0.89 km | 138 kV | [1] |
| Brie Substation · American Electric Power | Substation | 0.9 km | 138 kV | [1] |
| QTS NAL-1 Substation · Quality Technology Services | Substation | 1.03 km | 138 kV | [1] |
| Babbitt Substation · American Electric Power | Substation | 1.06 km | 138 kV | [1] |
| Macy Substation · American Electric Power | Substation | 1.12 km | 138 kV | [1] |
| Babbitt Substation · American Electric Power | Substation | 1.13 km | 345 kV | [1] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| Centerburg 138 kVPJM AI2-088 | Solar | In study · proposed 2025-12 | 413 MW | [5] |
| Centerburg 138 kVPJM AG1-034 | Solar | In study · proposed 2023-10 | 363 MW | [5] |
| Centerburg 138 kVPJM AH1-036 | Storage | In study · proposed 2024-07 | 278 MW | [5] |
| Centerburg 138 kVPJM AG1-024 | Solar | In study · proposed 2023-10 | 235 MW | [5] |
| Flint GridPJM AF1-062 | Storage | IA signed · proposed 2026-11 | 200 MW | [5] |
| Jug Street 138 kVPJM AI2-226 | Storage | In study · proposed 2022-08 | 200 MW | [5] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquiredSep 27, 2023[2]
- Permitting—
- Construction start—
- First operational—
- Expected completion—
Real estate
None sourced yet
None sourced yet
| Parcel | Record owner | Acres | Zoning / use | Building sq ft | Source |
|---|---|---|---|---|---|
| 094-106914-00.000 Licking County, OH | SIDECAT LLC 1601 WILLOW PARK RD , MENLO PARK, CA | 214.46 | 305: Research/Chemical Labs | — | [2] |
- Site area
- 214.5 acres[2]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Oct 12, 2026.Confirmed
Sum of county land area across parcels.
- Land use
- 305: Research/Chemical Labs[2]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Oct 12, 2026.Confirmed
- Annual property tax
- Not yet sourced
- NAO 1/NAO 2 · 0.3 km · parcel 094-107100-00.001$36.4M · Aug 10, 2017 [2]
- LCO 1 · 0.8 km · parcel 094-106782-00.000$34.3M · May 23, 2019 [2]
- Amazon Web Services CMH50 · 3.2 km · parcel 095-111744-00.000$12.8M · Jul 23, 2015 [2]
Size
- Building footprint
- 366,300 sq ft[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Likelyderived
Computed from the mapped OSM building outline.
- Parcel / land records
- 094-106914-00.000 (Licking County)[2]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Oct 12, 2026.Confirmed
- Floor area
- Not yet sourced
What changed (last 3 years)
Follow this facility (RSS)No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.
Timeline
- Sep 27, 2023[2]
Deed/transfer recorded for parcel 094-106914-00.000 (no sale price disclosed).
Other buildings on this campus
5- Meta PrometheusOperating + expanding · 95,300 sq ft footprint
- NAO 1/NAO 2Operating · 664,000 sq ft footprint
- NAO 5/NAO 6Operating · 609,500 sq ft footprint
- LCO 1Operating · 366,000 sq ft footprint
- LCO 2Operating · 304,500 sq ft footprint
All claims (provenance audit)
21| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | NAO 3way/802160675 name=NAO 3 | [1] | Likely | 2026-10-12 | Shown |
| Status | Operating | [1] derived | Unverified | 2026-10-12 | Shown |
| Facility type | Hyperscale | [1] derived | Unverified | 2026-10-12 | Shown |
| Property owner of record | Sidecat LLCParcel 094-106914-00.000: SIDECAT LLC | [2] | Confirmed | 2026-10-12 | Shown |
| Operator | Metaoperator=Meta | [1] | Likely | 2026-10-12 | Shown |
| Utility | American Electric Powerterritory 14006: OHIO POWER CO (INVESTOR OWNED, AMERICAN ELECTRIC POWER CO) | [3] derived | Unverified | 2022 | Shown |
| ISO / RTO | PJMPJM INTERCONNECTION, LLC | [4] derived | Likely | — | Shown |
| Balancing authority | PJM | [3] derived | Likely | — | Shown |
| Nearest mapped substation | Unnamed substation (138 kV)way/1428407099 | [1] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.9 km | [1] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 345 kV | [1] derived | Likely | 2026-09-28 | Shown |
| Generation queued in county | 2.52 GW | [5] derived | Confirmed | 2026-10-12 | Shown |
| State avg. industrial price | 10.95¢/kWh | [6] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 14.06¢/kWh | [6] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 21 MW | [7] derived | Confirmed | 202502 | Shown |
| Building footprint | 366,300 sq ft | [1] derived | Likely | 2026-10-12 | Shown |
| Site area | 214.5 acres | [2] | Confirmed | 2026-10-12 | Shown |
| Parcel / land records | 094-106914-00.000 (Licking County) | [2] | Confirmed | 2026-10-12 | Shown |
| Assessed value (official) | $459.6M | [2] | Confirmed | 2026 | Shown |
| Land use | 305: Research/Chemical Labs | [2] | Confirmed | 2026-10-12 | Shown |
| Land acquired | Sep 27, 2023 | [2] derived | Confirmed | 2026-10-12 | Shown |