New York

Datacenter Source tracks 39 data centers in New York, including 2 AI campuses. Facilities that disclose power add up to 107 MW online and 392 MW in the pipeline. These are floors, not market size: 5% of facilities have a power figure. Largest operators by tracked MW: AI XPV Platform, Core42 and Digital Realty. 441 MW has been announced; 107 MW is documented as operational.

Follow

Get changes to New York

How often

Double opt-in; one-click unsubscribe in every email. We store only your email and what you follow. More

Or subscribe in a feed reader: RSS / Atom

Cite this
Text
Datacenter Source. “New York data centers.” /states/NY. Data as of 2026-10-12. Accessed 2026-10-12.
BibTeX
@misc{datacentersource_state_NY_2026,
  title = {{New York data centers}},
  author = {{Datacenter Source}},
  year = {2026},
  howpublished = {\url{/states/NY}},
  note = {Data as of 2026-10-12; accessed 2026-10-12. Compiled from cited sources, including OpenStreetMap contributors (ODbL) and Epoch AI (CC BY 4.0)},
}

Please also cite the original source of any specific figure (linked beside it).

What changedView on map →
New York facilities:Download CSVJSONAPI docs
Floors, not market size. MW totals only add up facilities that disclose a figure (5% of 39 here); most sites don't, so the real totals are higher. “—” means not disclosed or not yet collected, never zero. CoverageData as of Oct 12, 2026
Facilities
39
2 campuses
Power online (floor)
107 MW
2 sites reporting
EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.100%
Under construction (floor)
392 MW
planned MW at active sites
EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.100%
Planned
—
0 planned sites (MW not disclosed)
AI campuses
2
107 MW online · 392 MW pipeline
AI compute
0.13M
H100-equivalents (est.)
Capital (reported + est.)
$3.8B

Online = operating sites; pipeline = remaining planned MW at sites under construction or planned. Percentages under each total show how much of it is backed by each evidence level. Average industrial electricity price: 10.81¢/kWh (EIA).

ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. filing, deed, permit or grid recordAnnouncedStated by the company or reported in the press; not yet backed by a filing or grid record. company or press claimEst.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. satellite, model or map inferenceHow levels are assigned

AI data center capacity over time

Facility power at satellite-tracked AI campuses (Epoch AI timelines), quarterly

0 MW125 MW250 MW375 MW500 MW2026202720282029
Observed (satellite-tracked) Projected

Construction pipeline by expected completion

MW from phases with a projected completion date

2026
2027

Power reality

Announced capacity vs. what grid records, construction and operation document. Facility-level sums; sources differ in coverage.

How to read this

Each bar sums one kind of evidence across facilities. Announced is the largest MW a company, utility, government or press source reported. Interconnection requests are MW in active large-load queue requests. Of the grid operators we ingest, only NYISO publishes these project by project. Contracted / approved means an executed interconnection agreement or a reported utility or power contract. Under construction and Operational come from construction records, imagery or operator reports.

The gap between announced and documented MW is capacity that has been claimed but not yet backed by a grid, construction or operating record. It is not proof a project won't happen. On-site generation is listed separately and never added to grid capacity. Method

Time to power puts each site's pending MW (announced minus operational) into a bucket by the midpoint of its evidence-based window. The window starts at the furthest documented stage and adds editorial ranges for what remains (e.g. announced: 2–5 yrs; land acquired: 2–4.5 yrs; planning / zoning: 1.75–4 yrs). Insufficient evidence means no dated stage evidence, not a delay. Windows are ranges, not forecasts. All ranges and rules

  • Announced441 MW
  • Interconnection requests—
  • Contracted / approved—
  • Under construction392 MW
  • Operational107 MW
Pending MW by time to power

Bucketed by the midpoint of each site's evidence-based window. Windows are ranges, not forecasts.

Largest gaps: announced vs documented

No large gaps in this scope.

Verified operating: 2Unverified: 37

Coverage

How much of this scope our sources describe. Low coverage means data isn't disclosed or not yet collected, not that there's nothing there.

Data as of Oct 12, 2026
Facilities with a power figure5% (2 of 39)
EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.100%
Facilities with confirmed evidence0% (0 of 39)
Only estimated evidence (mapping or models)100% (39 of 39)

Confirmed evidence = at least one fact about the facility itself from a filing, deed, permit, interconnection record, or government or utility record. Regional context (state prices, nearby plants, utility territory maps) doesn't count. Most facilities come from OpenStreetMap, which records that a building exists but rarely its power, owner or status.

Coverage by Markets
MarketsFacilitiesWith powerConfirmed
New York / New Jersey120%(low)0%

Markets

Click through to drill down

Data as of Oct 12, 2026
Online Under construction + planned
NameFacilitiesOnlinePipeline
New York / New Jersey12——

Largest operators & owners

Online + pipeline MW at linked facilities

Online Under construction + planned

Largest customers & end users

Tenants and workload owners, where sourced

Online Under construction + planned
  • Anthropic49 MW + 392 MW · 1 sites
  • G4258 MW + 0 MW · 1 sites

Utility exposure

Most likely retail utility by location (approximate)

Online Under construction + planned

Grid operators (ISO / RTO)

By facility location

Online Under construction + planned
  • NYISO107 MW + 392 MW · 39 sites

Largest facilities

By online + pipeline MW; badge = evidence behind each figure

Data as of Oct 12, 2026
FacilityStatusOnlinePipeline
Anthropic Lake MarinerOperating + expandingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.49 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.392 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
Core42 Lake MarinerOperatingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.58 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.—

Facilities by status

  • Operating38
  • Operating + expanding1

Counties

Local impact

Water, on-site generation and air permits, incentives, regulatory events and large-load tariffs, where a source documents them. Counts are of sourced records, not of the state's totals.

Water & cooling

0 M gal/day modeled at 2 sites EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.

On-site generation & air permits

13 sites with documented on-site generation (MW not reported)

Incentives

Not yet collected

Utility & rates: large-load tariffs

Not yet collected for this state's utilities.

Regulatory events

Not yet collected