Core42 Lake Mariner

OperatingEst.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 23, 2026.AI campusCampusBarker, Niagara County, New York

Core42 Lake Mariner is an operating ai campus in Barker, New York. Operated or owned by Core42; used by G42. Current power: 58 MW (estimated). Verification: verified operating. 10 cited sources.

70% profile completeness
37 claims from 10 sources
Last verified against sources: Oct 12, 2026
Newest dated evidence: Jul 23, 2026
Follow

Get changes to Core42 Lake Mariner

How often

Double opt-in; one-click unsubscribe in every email. We store only your email and what you follow. More

Or subscribe in a feed reader: RSS / Atom

Cite this
Text
Datacenter Source. “Core42 Lake Mariner.” /facilities/core42-lake-mariner-barker-ny. Data as of 2026-10-12. Accessed 2026-10-12.
BibTeX
@misc{datacentersource_core42_lake_mariner_barker_ny_2026,
  title = {{Core42 Lake Mariner}},
  author = {{Datacenter Source}},
  year = {2026},
  howpublished = {\url{/facilities/core42-lake-mariner-barker-ny}},
  note = {Data as of 2026-10-12; accessed 2026-10-12. Compiled from cited sources, including OpenStreetMap contributors (ODbL) and Epoch AI (CC BY 4.0)},
}

Please also cite the original source of any specific figure (linked beside it).

Current facility power
58 MW[1]
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 23, 2026.Likelyestimated
Planned capacity
Not yet sourced
Floor area
Not yet sourced
Buildings (planned)
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 23, 2026.Likelyderived
Capital cost / investment
$2.2B[1]
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 23, 2026.Likelyestimated
First operational
Oct 1, 2025[1]
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 23, 2026.Likelyderived

POWER & GRID

Time-to-power · verification · interconnection
Time to power
Energized — operating
High confidence
Project verification
Verified operating
Operation documented by satellite imagery.
Current stage
Operational
Furthest stage with documented evidence
Utility · ISO
Niagara Mohawk Power Corp. · NYISO
Substation: On-site substation

Power reality

Announced
No record
Interconnection request
No record
Contracted / approved
No record
Under construction
No record
Operational
58 MW[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
Estimated from buildings observed operational
AI evidence brief
Summarizes only the evidence on this page. Answers citing anything else are rejected automatically.

Project verification

Development
  1. Announcedimplied by a later stage
  2. Land acquiredimplied by a later stage
  3. Planning / zoningimplied by a later stage
  4. Permittingimplied by a later stage
Grid interconnection
  1. Interconnection application
  2. Feasibility study
  3. System impact study
  4. Facilities study
  5. Interconnection agreement / service contract
Build & energization
  1. Financing
  2. Under constructionOct 1, 2024
    Model estimate · Satellite imagery
    • Oct 1, 2024 · Reported status: under construction[1]
    • Oct 1, 2024 · Construction start[1]
    • Oct 1, 2024 · Land clearing begins for Building 1, also known as CB-1, the first large AI/HPC building on the site.[1]
    • Oct 1, 2025 · Reported status: expanding[1]
  3. EnergizationOct 1, 2025
    Satellite imagery
    • Oct 1, 2025 · Building 1 is operational. Based on Terawulf [saying](https://investors.terawulf.com/news-events/press-releases/detail/126/terawulf-reports-third-quarter-2025-results) "As of Septe[1]
    • Mar 31, 2026 · Building 2 is operational. On February 26, Terawulf [stated](https://investors.terawulf.com/news-events/press-releases/detail/132/terawulf-reports-fourth-quarter-and-full-year-2025[1]
  4. OperationalOct 1, 2025
    Satellite imagery
    • Oct 1, 2025 · Building 1 is operational. Based on Terawulf [saying](https://investors.terawulf.com/news-events/press-releases/detail/126/terawulf-reports-third-quarter-2025-results) "As of Septe[1]
    • Mar 31, 2026 · Building 2 is operational. On February 26, Terawulf [stated](https://investors.terawulf.com/news-events/press-releases/detail/132/terawulf-reports-fourth-quarter-and-full-year-2025[1]

● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.

Grid path

  1. facility
    Core42 Lake Mariner
  2. substation
    On-site substation[1]
    Satellite imageryLikely
    1 substation outline traced inside the campus on satellite imagery
  3. transmission
    Not identified
    UnknownUnverified
    No transmission line mapped within 2 km.
  4. utility
    Niagara Mohawk Power Corp.[2]
    Service territoryLikely
    Retail service territory containing the site
  5. ISO / RTO
    NYISO[4]
    Service territoryLikely
    Balancing authority: NYIS
Substation capacity:
not published
Required upgrades:
not yet sourced
Congestion:
not yet sourced (no nodal price data)

Dashed boxes are based on proximity only and do not establish which asset serves the site.

Interconnection records

No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.

On-site & dedicated generation

No on-site, behind-the-meter or dedicated generation found in sources.

LOCAL IMPACT

Water · generation · incentives · regulation · rates

Water & cooling1

  • 0 million gal/day[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 23, 2026.Jul 23, 2026modeled water use

    Epoch AI's modeled estimate at the latest observed milestone, in million gallons per day. Not a permit or metered figure.

On-site generation & air permits

Not yet collected: we haven't found a source for on-site generation or an air permit for this site. Know one? Add a source

Incentives

Not yet collected: we haven't found a source for tax abatements, PILOTs or other incentives for this project. Know one? Add a source

Regulatory events

Not yet collected: we haven't found a source for hearings, rezonings, permits or commission proceedings. Know one? Add a source

Utility & rates

Not yet collected: we haven't found a source for a large-load tariff or commission docket for Niagara Mohawk Power Corp.. Know one? Add a source

Location & imagery

Mapped outline
Coordinates
43.35707, -78.60405
Address
7725 Lake Rd, Barker, NY 14012[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 23, 2026.Likely
County
Niagara County
Photographs

No openly licensed ground-level photos matched to this site yet.

Ownership, operation & customers

  1. 1. Property owner of record
    Not identified
  2. 2. Owner / developer
  3. 3. Operator
    Not identified
  4. 4. Tenant / cloud
    Not identified
  5. 5. End customer / workload
    G42[1]Likely
Power supply
Capital & construction
Investor:

Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.

All parties with evidence
Owner
Core42[1]Confirmed
End user
G42[1]Likely
Utility

Most likely retail provider among 2 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: New York State Elec & Gas Corp.

Investor
Google[1]Confirmed

Power (all fields)

Current facility power
58 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 23, 2026.Likelyestimated

Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.

Current IT capacity
58 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 23, 2026.Likelyestimated

Estimated IT load currently online, based on buildings observed operational.

Estimated annual consumption
356 GWh/yr[3]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Speculativeestimated

58 MW × 8,760 h × 70% utilization.

Planned capacity
Not yet sourced

Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.

Grid & electricity

ISO / RTO
NYISO[4]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived

Location falls inside this ISO/RTO footprint.

Balancing authority
NYIS[2]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived

Control area of the containing utility territory.

State avg. industrial price
10.81¢/kWh[5]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed

New York statewide average, July 2026.

State avg. commercial price
24.18¢/kWh[5]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed

New York statewide average, July 2026.

Generation within 50 km
3.16 GW[6]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jan 1, 202502.Confirmedderived

47 EIA-reported plants within 50 km.

Interconnection status
Not yet sourced
Contracted / committed power
Not yet sourced
Nearby infrastructureTypeDistanceVoltage / capacitySource
Slayton Settlement Road Solar Csg · RPNY Solar 3, LLCPower plant (Solar)17.4 km7 MW[6]
Lockport Energy Associates LP · Lockport Energy Associates LPPower plant (Natural Gas)24.5 km219 MW[6]
Modern Innovative Energy LLC · Innovative Energy Systems IncPower plant (Biomass)34.8 km6 MW[6]
Model City Energy Facility · Model City Energy LLCPower plant (Biomass)34.8 km6 MW[6]
World Generation X · North American Energy ServicesPower plant (Natural Gas)39.9 km52 MW[6]
Lewiston Niagara · New York Power AuthorityPower plant (Pumped Storage)41.4 km240 MW[6]
Robert Moses Niagara · New York Power AuthorityPower plant (Hydroelectric)42.6 km2.44 GW[6]
Reworld Niagara I · Reworld Niagara I, LLCPower plant (Biomass)44.5 km36 MW[6]

Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.

Construction & permitting

  1. Announced
    —
  2. Land acquired
    —
  3. Permitting
    —
  4. Construction start
    Oct 1, 2024[1]
  5. First operational
    Oct 1, 2025[1]
  6. Expected completion
    —
Buildings (planned)
2[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 23, 2026.Likelyderived

Count of building outlines traced on satellite imagery.

Buildings operational
2[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 23, 2026.Likelyestimated
PhaseStatusAdded MWCompleted / expectedSource
Building 1operational19 MWOct 1, 2025[1]
Building 2operational39 MWMar 31, 2026[1]

Real estate

Official assessments
Assessor's value for a tax year

None sourced yet

Recorded transactions
Sale prices from recorded deeds

None sourced yet

Model estimates
Our model — not an appraisal

None sourced yet

Capital cost / investment
$2.2B[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 23, 2026.Likelyestimated

Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.

Annual property tax
Not yet sourced

No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.

Size

Floor area
Not yet sourced

Compute

Chip types
B200[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 23, 2026.Confirmed
Compute (H100-equivalents)
71,800[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 23, 2026.Likelyestimated

What changed (last 3 years)

Follow this facility (RSS)
  • Current IT capacity
    16 MWOct 1, 2025[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→58 MWMar 31, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
  • Current facility power
    19 MWOct 1, 2025[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→58 MWMar 31, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
  • Buildings operational
    0Oct 1, 2024[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→1Oct 1, 2025[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→2Mar 31, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
  • Status
    Under constructionOct 1, 2024[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→Operating + expandingOct 1, 2025[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→OperatingJul 23, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.

Timeline

Construction start: Oct 1, 2024[1]
First operational: Oct 1, 2025[1]
  1. Oct 1, 2024[1]

    Land clearing begins for Building 1, also known as CB-1, the first large AI/HPC building on the site.

  2. Oct 1, 202519 MW facility power· 1 buildings operational[1]

    Building 1 is operational. Based on Terawulf saying "As of September 30, 2025, the site has energized 245 MW of Bitcoin-mining capacity and 22.5 MW of HPC capacity." The small "Wulf Den" building was said to be 2 MW of IT power while CB-1 would be 16 MW. This is roughly consistent with 22.5 MW of total facility power. This building is leased to Core42, a subsidiary of UAE-based G42. It likely uses NVIDIA DGX B200 servers.

  3. Mar 2, 202619 MW facility power· 1 buildings operational[1]

    Buildings 1 and 2 both appear to have complete building and cooling equipment, based on satellite imagery. Not considering Building 2 operational yet, due to Terawulf's statement that CB2B is expected in March 2026, and is likely still in commissioning phase.

  4. Mar 31, 202658 MW facility power· 2 buildings operational[1]

    Building 2 is operational. On February 26, Terawulf stated that CB2A is operational, presumably making up half the final capacity. CB2B was expected in March 2026. However, it's notable that a drone video commissioned from RAAD showed no cooling fan movement on May 8th, suggesting it was not in use. This building is leased to Core42, a subsidiary of UAE-based G42. It likely uses NVIDIA DGX B200 servers.

  5. Jul 23, 202658 MW facility power· 2 buildings operational[1]

    Both buildings still operational according to satellite imagery.

All claims (provenance audit)

37
FieldValueSourceConfidenceAs ofStatus
NameCore42 Lake Mariner[1] Likely2026-07-23Shown
StatusUnder construction[1] derivedLikely2024-10-01Superseded / alternative
StatusOperating + expanding[1] derivedLikely2025-10-01Superseded / alternative
StatusOperating + expanding[1] derivedLikely2026-03-02Superseded / alternative
StatusOperating + expanding[1] derivedLikely2026-03-31Superseded / alternative
StatusOperating[1] derivedLikely2026-07-23Shown
Facility typeAI campus[1] derivedLikely2026-07-23Shown
Address7725 Lake Rd, Barker, NY 14012[1] Likely2026-07-23Shown
OwnerCore42Owner: Core42[1] Confirmed2026-07-23Shown
End usersG42Users: G42[1] Likely2026-07-23Shown
UtilityNiagara Mohawk Power Corp.territory 13573: NIAGARA MOHAWK POWER CORP. (INVESTOR OWNED, NATIONAL GRID GROUP[2] derivedUnverified2022Shown
InvestorsGoogleInvestors: Google[1] Confirmed2026-07-23Shown
Current facility power58 MW[1] estimatedLikely2026-07-23Shown
Current facility power19 MW[1] estimatedLikely2025-10-01Superseded / alternative
Current facility power19 MW[1] estimatedLikely2026-03-02Superseded / alternative
Current facility power58 MW[1] estimatedLikely2026-03-31Superseded / alternative
Current IT capacity58 MW[1] estimatedLikely2026-07-23Shown
Current IT capacity16 MW[1] estimatedLikely2025-10-01Superseded / alternative
Current IT capacity16 MW[1] estimatedLikely2026-03-02Superseded / alternative
Current IT capacity58 MW[1] estimatedLikely2026-03-31Superseded / alternative
Estimated annual consumption356 GWh/yr[3] estimatedSpeculative2026-10-12Shown
ISO / RTONYISONEW YORK INDEPENDENT SYSTEM OPERATOR[4] derivedLikely—Shown
Balancing authorityNYIS[2] derivedLikely—Shown
State avg. industrial price10.81¢/kWh[5] Confirmed2026-07Shown
State avg. commercial price24.18¢/kWh[5] Confirmed2026-07Shown
Generation within 50 km3.16 GW[6] derivedConfirmed202502Shown
Buildings (planned)2[1] derivedLikely2026-07-23Shown
Buildings operational2[1] estimatedLikely2026-07-23Shown
Buildings operational0[1] estimatedLikely2024-10-01Superseded / alternative
Buildings operational1[1] estimatedLikely2025-10-01Superseded / alternative
Buildings operational1[1] estimatedLikely2026-03-02Superseded / alternative
Buildings operational2[1] estimatedLikely2026-03-31Superseded / alternative
Capital cost / investment$2.2B[1] estimatedLikely2026-07-23Shown
Compute (H100-equivalents)71,800[1] estimatedLikely2026-07-23Shown
Chip typesB200[1] Confirmed2026-07-23Shown
Construction startOct 1, 2024[1] derivedLikely2026-07-23Shown
First operationalOct 1, 2025[1] derivedLikely2026-07-23Shown