Core42 Lake Mariner
Core42 Lake Mariner is an operating ai campus in Barker, New York. Operated or owned by Core42; used by G42. Current power: 58 MW (estimated). Verification: verified operating. 10 cited sources.
Follow
Get changes to Core42 Lake Mariner
Or subscribe in a feed reader: RSS / Atom
Cite this
Datacenter Source. “Core42 Lake Mariner.” /facilities/core42-lake-mariner-barker-ny. Data as of 2026-10-12. Accessed 2026-10-12.
@misc{datacentersource_core42_lake_mariner_barker_ny_2026,
title = {{Core42 Lake Mariner}},
author = {{Datacenter Source}},
year = {2026},
howpublished = {\url{/facilities/core42-lake-mariner-barker-ny}},
note = {Data as of 2026-10-12; accessed 2026-10-12. Compiled from cited sources, including OpenStreetMap contributors (ODbL) and Epoch AI (CC BY 4.0)},
}Please also cite the original source of any specific figure (linked beside it).
POWER & GRID
Time-to-power · verification · interconnectionPower reality
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- Under constructionOct 1, 2024
- EnergizationOct 1, 2025
Satellite imagery
- Oct 1, 2025 · Building 1 is operational. Based on Terawulf [saying](https://investors.terawulf.com/news-events/press-releases/detail/126/terawulf-reports-third-quarter-2025-results) "As of Septe[1]
- Mar 31, 2026 · Building 2 is operational. On February 26, Terawulf [stated](https://investors.terawulf.com/news-events/press-releases/detail/132/terawulf-reports-fourth-quarter-and-full-year-2025[1]
- OperationalOct 1, 2025
Satellite imagery
- Oct 1, 2025 · Building 1 is operational. Based on Terawulf [saying](https://investors.terawulf.com/news-events/press-releases/detail/126/terawulf-reports-third-quarter-2025-results) "As of Septe[1]
- Mar 31, 2026 · Building 2 is operational. On February 26, Terawulf [stated](https://investors.terawulf.com/news-events/press-releases/detail/132/terawulf-reports-fourth-quarter-and-full-year-2025[1]
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.
Grid path
- →facilityCore42 Lake Mariner
- →substationOn-site substation[1]Satellite imageryLikely1 substation outline traced inside the campus on satellite imagery
- →transmissionNot identifiedUnknownUnverifiedNo transmission line mapped within 2 km.
- →utilityNiagara Mohawk Power Corp.[2]Service territoryLikelyRetail service territory containing the site
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
LOCAL IMPACT
Water · generation · incentives · regulation · ratesWater & cooling1
- 0 million gal/day[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 23, 2026.Jul 23, 2026modeled water use
Epoch AI's modeled estimate at the latest observed milestone, in million gallons per day. Not a permit or metered figure.
On-site generation & air permits
Not yet collected: we haven't found a source for on-site generation or an air permit for this site. Know one? Add a source
Incentives
Not yet collected: we haven't found a source for tax abatements, PILOTs or other incentives for this project. Know one? Add a source
Regulatory events
Not yet collected: we haven't found a source for hearings, rezonings, permits or commission proceedings. Know one? Add a source
Utility & rates
Not yet collected: we haven't found a source for a large-load tariff or commission docket for Niagara Mohawk Power Corp.. Know one? Add a source
Location & imagery
Mapped outline- Coordinates
- 43.35707, -78.60405
- Address
- 7725 Lake Rd, Barker, NY 14012[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 23, 2026.Likely
- County
- Niagara County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workload
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Utility
Most likely retail provider among 2 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: New York State Elec & Gas Corp.
Power (all fields)
- Current facility power
- 58 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 23, 2026.Likelyestimated
Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.
- Current IT capacity
- 58 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 23, 2026.Likelyestimated
Estimated IT load currently online, based on buildings observed operational.
- Estimated annual consumption
- 356 GWh/yr[3]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Speculativeestimated
58 MW × 8,760 h × 70% utilization.
- Planned capacity
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
- NYISO[4]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived
Location falls inside this ISO/RTO footprint.
- Balancing authority
- NYIS[2]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived
Control area of the containing utility territory.
- State avg. industrial price
- 10.81¢/kWh[5]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed
New York statewide average, July 2026.
- State avg. commercial price
- 24.18¢/kWh[5]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed
New York statewide average, July 2026.
- Generation within 50 km
- 3.16 GW[6]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jan 1, 202502.Confirmedderived
47 EIA-reported plants within 50 km.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| Slayton Settlement Road Solar Csg · RPNY Solar 3, LLC | Power plant (Solar) | 17.4 km | 7 MW | [6] |
| Lockport Energy Associates LP · Lockport Energy Associates LP | Power plant (Natural Gas) | 24.5 km | 219 MW | [6] |
| Modern Innovative Energy LLC · Innovative Energy Systems Inc | Power plant (Biomass) | 34.8 km | 6 MW | [6] |
| Model City Energy Facility · Model City Energy LLC | Power plant (Biomass) | 34.8 km | 6 MW | [6] |
| World Generation X · North American Energy Services | Power plant (Natural Gas) | 39.9 km | 52 MW | [6] |
| Lewiston Niagara · New York Power Authority | Power plant (Pumped Storage) | 41.4 km | 240 MW | [6] |
| Robert Moses Niagara · New York Power Authority | Power plant (Hydroelectric) | 42.6 km | 2.44 GW | [6] |
| Reworld Niagara I · Reworld Niagara I, LLC | Power plant (Biomass) | 44.5 km | 36 MW | [6] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction startOct 1, 2024[1]
- First operationalOct 1, 2025[1]
- Expected completion—
- Buildings (planned)
- 2[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 23, 2026.Likelyderived
Count of building outlines traced on satellite imagery.
- Buildings operational
- 2[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 23, 2026.Likelyestimated
Real estate
None sourced yet
None sourced yet
None sourced yet
- Capital cost / investment
- $2.2B[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 23, 2026.Likelyestimated
Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Floor area
- Not yet sourced
Compute
- Chip types
- B200[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 23, 2026.Confirmed
- Compute (H100-equivalents)
- 71,800[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 23, 2026.Likelyestimated
What changed (last 3 years)
Follow this facility (RSS)- Current IT capacity16 MWOct 1, 2025[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→58 MWMar 31, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
- Current facility power19 MWOct 1, 2025[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→58 MWMar 31, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
- Buildings operational0Oct 1, 2024[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→1Oct 1, 2025[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→2Mar 31, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
- StatusUnder constructionOct 1, 2024[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→Operating + expandingOct 1, 2025[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→OperatingJul 23, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
Timeline
- Oct 1, 2024[1]
Land clearing begins for Building 1, also known as CB-1, the first large AI/HPC building on the site.
Building 1 is operational. Based on Terawulf saying "As of September 30, 2025, the site has energized 245 MW of Bitcoin-mining capacity and 22.5 MW of HPC capacity." The small "Wulf Den" building was said to be 2 MW of IT power while CB-1 would be 16 MW. This is roughly consistent with 22.5 MW of total facility power. This building is leased to Core42, a subsidiary of UAE-based G42. It likely uses NVIDIA DGX B200 servers.
Buildings 1 and 2 both appear to have complete building and cooling equipment, based on satellite imagery. Not considering Building 2 operational yet, due to Terawulf's statement that CB2B is expected in March 2026, and is likely still in commissioning phase.
Building 2 is operational. On February 26, Terawulf stated that CB2A is operational, presumably making up half the final capacity. CB2B was expected in March 2026. However, it's notable that a drone video commissioned from RAAD showed no cooling fan movement on May 8th, suggesting it was not in use. This building is leased to Core42, a subsidiary of UAE-based G42. It likely uses NVIDIA DGX B200 servers.
Both buildings still operational according to satellite imagery.
All claims (provenance audit)
37| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Core42 Lake Mariner | [1] | Likely | 2026-07-23 | Shown |
| Status | Under construction | [1] derived | Likely | 2024-10-01 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-10-01 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-03-02 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-03-31 | Superseded / alternative |
| Status | Operating | [1] derived | Likely | 2026-07-23 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-07-23 | Shown |
| Address | 7725 Lake Rd, Barker, NY 14012 | [1] | Likely | 2026-07-23 | Shown |
| Owner | Core42Owner: Core42 | [1] | Confirmed | 2026-07-23 | Shown |
| End users | G42Users: G42 | [1] | Likely | 2026-07-23 | Shown |
| Utility | Niagara Mohawk Power Corp.territory 13573: NIAGARA MOHAWK POWER CORP. (INVESTOR OWNED, NATIONAL GRID GROUP | [2] derived | Unverified | 2022 | Shown |
| Investors | GoogleInvestors: Google | [1] | Confirmed | 2026-07-23 | Shown |
| Current facility power | 58 MW | [1] estimated | Likely | 2026-07-23 | Shown |
| Current facility power | 19 MW | [1] estimated | Likely | 2025-10-01 | Superseded / alternative |
| Current facility power | 19 MW | [1] estimated | Likely | 2026-03-02 | Superseded / alternative |
| Current facility power | 58 MW | [1] estimated | Likely | 2026-03-31 | Superseded / alternative |
| Current IT capacity | 58 MW | [1] estimated | Likely | 2026-07-23 | Shown |
| Current IT capacity | 16 MW | [1] estimated | Likely | 2025-10-01 | Superseded / alternative |
| Current IT capacity | 16 MW | [1] estimated | Likely | 2026-03-02 | Superseded / alternative |
| Current IT capacity | 58 MW | [1] estimated | Likely | 2026-03-31 | Superseded / alternative |
| Estimated annual consumption | 356 GWh/yr | [3] estimated | Speculative | 2026-10-12 | Shown |
| ISO / RTO | NYISONEW YORK INDEPENDENT SYSTEM OPERATOR | [4] derived | Likely | — | Shown |
| Balancing authority | NYIS | [2] derived | Likely | — | Shown |
| State avg. industrial price | 10.81¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 24.18¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 3.16 GW | [6] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 2 | [1] derived | Likely | 2026-07-23 | Shown |
| Buildings operational | 2 | [1] estimated | Likely | 2026-07-23 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2024-10-01 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2025-10-01 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2026-03-02 | Superseded / alternative |
| Buildings operational | 2 | [1] estimated | Likely | 2026-03-31 | Superseded / alternative |
| Capital cost / investment | $2.2B | [1] estimated | Likely | 2026-07-23 | Shown |
| Compute (H100-equivalents) | 71,800 | [1] estimated | Likely | 2026-07-23 | Shown |
| Chip types | B200 | [1] | Confirmed | 2026-07-23 | Shown |
| Construction start | Oct 1, 2024 | [1] derived | Likely | 2026-07-23 | Shown |
| First operational | Oct 1, 2025 | [1] derived | Likely | 2026-07-23 | Shown |