Salt Lake City
Market boundary: facilities within 55 km of the metro center (editorial definition).
Online = operating sites; pipeline = remaining planned MW at sites under construction or planned. Percentages under each total show how much of it is backed by each evidence level.
ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. filing, deed, permit or grid recordAnnouncedStated by the company or reported in the press; not yet backed by a filing or grid record. company or press claimEst.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. satellite, model or map inferenceHow levels are assignedConstruction pipeline by expected completion
MW from phases with a projected completion date
Power reality
Announced capacity vs. what grid records, construction and operation document. Facility-level sums; sources differ in coverage.
How to read this
Each bar sums one kind of evidence across facilities. Announced is the largest MW a company, utility, government or press source reported. Interconnection requests are MW in active large-load queue requests. Of the grid operators we ingest, only NYISO publishes these project by project. Contracted / approved means an executed interconnection agreement or a reported utility or power contract. Under construction and Operational come from construction records, imagery or operator reports.
The gap between announced and documented MW is capacity that has been claimed but not yet backed by a grid, construction or operating record. It is not proof a project won't happen. On-site generation is listed separately and never added to grid capacity. Method
Time to power puts each site's pending MW (announced minus operational) into a bucket by the midpoint of its evidence-based window. The window starts at the furthest documented stage and adds editorial ranges for what remains (e.g. announced: 2–5 yrs; land acquired: 2–4.5 yrs; planning / zoning: 1.75–4 yrs). Insufficient evidence means no dated stage evidence, not a delay. Windows are ranges, not forecasts. All ranges and rules
- Announced457 MW
- Interconnection requests—
- Contracted / approved—
- Under construction411 MW
- Operational179 MW
Bucketed by the midpoint of each site's evidence-based window. Windows are ranges, not forecasts.
No large gaps in this scope.
Coverage
How much of this scope our sources describe. Low coverage means data isn't disclosed or not yet collected, not that there's nothing there.
Confirmed evidence = at least one fact about the facility itself from a filing, deed, permit, interconnection record, or government or utility record. Regional context (state prices, nearby plants, utility territory maps) doesn't count. Most facilities come from OpenStreetMap, which records that a building exists but rarely its power, owner or status.
Largest operators & owners
Online + pipeline MW at linked facilities
- Meta179 MW + 0 MW · 6 sites
- Flexential— · 5 sites
- DataBank— · 5 sites
Largest customers & end users
Tenants and workload owners, where sourced
- Meta179 MW + 0 MW · 1 sites
Utility exposure
Most likely retail utility by location (approximate)
- PacifiCorp179 MW + 411 MW · 21 sites
Grid operators (ISO / RTO)
By facility location
- None (non-RTO region)179 MW + 411 MW · 21 sites
Largest facilities
By online + pipeline MW; badge = evidence behind each figure
| Facility | Status | Online | Pipeline |
|---|---|---|---|
| QTS Eagle Mountain | Under constructionEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. | — | 411 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. |
| Meta Eagle Mountain | OperatingEstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. | 179 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. | — |
Facilities by status
- Operating20
- Under construction1
Campuses & sites (11)
Campus pages list their buildings
- QTS Eagle Mountain · 411 MW pipeline EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
- Meta Eagle Mountain179 MW online EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
- eBaybuilding
- Ebaybuilding
- FiberState Datacenterbuilding
- Flexential Salt Lake City - Downtownbuilding
- Flexential Salt Lake City - Fair Parkbuilding
- Flexential Salt Lake City - Lindonsite
- Flexential Salt Lake City - Millcreekbuilding
- Flexential Salt Lake City - South Valleybuilding
- Verizonbuilding