QTS Eagle Mountain
QTS Eagle Mountain is an under construction ai campus in Eagle Mountain, Utah. Planned capacity: 411 MW (estimated). Verification: under construction. 8 cited sources.
Follow
Get changes to QTS Eagle Mountain
Or subscribe in a feed reader: RSS / Atom
Cite this
Datacenter Source. “QTS Eagle Mountain.” /facilities/qts-eagle-mountain-eagle-mountain-ut. Data as of 2026-10-12. Accessed 2026-10-12.
@misc{datacentersource_qts_eagle_mountain_eagle_mountain_ut_2026,
title = {{QTS Eagle Mountain}},
author = {{Datacenter Source}},
year = {2026},
howpublished = {\url{/facilities/qts-eagle-mountain-eagle-mountain-ut}},
note = {Data as of 2026-10-12; accessed 2026-10-12. Compiled from cited sources, including OpenStreetMap contributors (ODbL) and Epoch AI (CC BY 4.0)},
}Please also cite the original source of any specific figure (linked beside it).
POWER & GRID
Time-to-power · verification · interconnectionPower reality
- ⚠ No public interconnection record for this load — None (non-RTO region) does not publish large-load requests.
- ⚠ No permit record linked to this site yet.
How the time-to-power window was estimated
- From “Under construction”, large loads have typically taken 0.5–2 more years to first power (editorial range; see Methodology).
- Construction to first power typically takes 1.25–2.5 years.
- The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.
Grid path
- →facilityQTS Eagle Mountain
- →substationOn-site substation[1]Satellite imageryLikely1 substation outline traced inside the campus on satellite imagery
- →transmission345 kV line[4]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (0.7 km away). Not confirmed as the supply path.
- →
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
LOCAL IMPACT
Water · generation · incentives · regulation · ratesWater & cooling1
- Air-cooled (chillers / dry coolers)[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of May 2, 2026.May 2, 2026cooling
“Satellite imagery shows construction vehicles and concrete pads with no air cooled chiller units indicating Buildings 1 and 2 cooling install continues.”
Named in Epoch AI's satellite-imagery notes for this date.
On-site generation & air permits
Not yet collected: we haven't found a source for on-site generation or an air permit for this site. Know one? Add a source
Incentives
Not yet collected: we haven't found a source for tax abatements, PILOTs or other incentives for this project. Know one? Add a source
Regulatory events
Not yet collected: we haven't found a source for hearings, rezonings, permits or commission proceedings. Know one? Add a source
Utility & rates
Not yet collected: we haven't found a source for a large-load tariff or commission docket for PacifiCorp. Know one? Add a source
Location & imagery
Mapped outline- Coordinates
- 40.26596, -112.03057
- Address
- 652 E Hyperscale Way, Eagle Mountain, UT 84013[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of May 2, 2026.Likely
- County
- Utah County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workload
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
Power (all fields)
- Planned capacity
- 411 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of May 2, 2026.Likelyestimated
Projected facility power at the last tracked milestone (2027-07-01); not necessarily full build-out.
- Current facility power
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
- None (non-RTO region)[3]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived
Outside all ISO/RTO footprints; balancing authority shown separately.
- Balancing authority
- PACW, PACE[2]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived
Control area of the containing utility territory.
- Nearest mapped substation
- Unnamed substation (345 kV)[4]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- 0.7 km[4]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
- Highest-voltage line nearby
- 345 kV[4]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
- 9.10¢/kWh[5]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed
Utah statewide average, July 2026.
- State avg. commercial price
- 10.85¢/kWh[5]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed
Utah statewide average, July 2026.
- Generation within 50 km
- 1.72 GW[6]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jan 1, 202502.Confirmedderived
21 EIA-reported plants within 50 km.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 345 kV line | Transmission line | 0.7 km | 345 kV | [4] |
| Lake Side Power Plant · PacifiCorp | Power plant (Natural Gas) | 24.6 km | 1.18 GW | [6] |
| Byu Central Heating Plant · Brigham Young University (BYU) | Power plant (Natural Gas) | 32.7 km | 14 MW | [6] |
| Nebo Power Station · Utah Associated Mun Power Sys | Power plant (Natural Gas) | 34.2 km | 130 MW | [6] |
| Whitehead · City of Springville - (UT) | Power plant (Natural Gas) | 36.1 km | 24 MW | [6] |
| Spanish Fork Wind Park 2 LLC · Spanish Fork Wind Park 2, LLC | Power plant (Wind) | 43.8 km | 19 MW | [6] |
| West Valley Generation Project · Utah Municipal Power Agency | Power plant (Natural Gas) | 44.6 km | 185 MW | [6] |
| Murray Turbine · City of Murray - (UT) | Power plant (Natural Gas) | 46.5 km | 36 MW | [6] |
| Clover Creek Solar Community Solar · AES Distributed Energy | Power plant (Solar) | 48.8 km | 80 MW | [6] |
| Unnamed substation | Substation | 0.72 km | 345 kV | [4] |
| PacifiCorp substation · PacifiCorp | Substation | 1.17 km | 345 kV | [4] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction startOct 1, 2023[1]
- First operationalDec 31, 2026[1]Projected
- Expected completionJul 1, 2027[1]Projected
- Planned capacity
- 411 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of May 2, 2026.Likelyestimated
Projected facility power at the last tracked milestone (2027-07-01); not necessarily full build-out.
- Buildings (planned)
- 2[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of May 2, 2026.Likelyderived
Count of building outlines traced on satellite imagery.
- Buildings operational
- 0[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of May 2, 2026.Likelyestimated
Real estate
None sourced yet
None sourced yet
None sourced yet
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Floor area
- Not yet sourced
Compute
- Chip types
- B300[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of May 2, 2026.Confirmed
What changed (last 3 years)
Follow this facility (RSS)No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.
Timeline
- Oct 1, 2023[1]
First signs of site preparation show up on satellite imagery.
- Sep 8, 2025[1]
Site preparation continues. Outline of a first building that is not the data center of interest Buildings 1 or 2 is visible.
- May 2, 2026[1]
Building 1 roof finished. Satellite imagery shows construction vehicles and concrete pads with no air cooled chiller units indicating Buildings 1 and 2 cooling install continues. On the other side of each building, emergency generator install continues as well.
We estimate Buildings 1 and 2 will be fully operational by the end of 2026 because there are at least seven months since cooling and emergency generators have started to be installed. This estimate is also in line with similar QTS data center campus construction timelines.
We estimate Building 3 will be fully operational by H2 2027 following a similar time line to Buildings 1 and 2 of 14 months from land clearing to operational.
All claims (provenance audit)
26| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | QTS Eagle Mountain | [1] | Likely | 2026-05-02 | Shown |
| Status | Under construction | [1] derived | Likely | 2023-10-01 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2025-09-08 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2026-05-02 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-05-02 | Shown |
| Address | 652 E Hyperscale Way, Eagle Mountain, UT 84013 | [1] | Likely | 2026-05-02 | Shown |
| Owner | MetaOwner: Meta | [1] | Speculative | 2026-05-02 | Shown |
| End users | MetaUsers: Meta | [1] | Speculative | 2026-05-02 | Shown |
| Utility | PacifiCorpterritory 14354: PACIFICORP (INVESTOR OWNED, PACIFICORP) | [2] derived | Likely | 2022 | Shown |
| Planned capacity | 411 MW | [1] estimated | Likely | 2026-05-02 | Shown |
| ISO / RTO | None (non-RTO region) | [3] derived | Likely | — | Shown |
| Balancing authority | PACW, PACE | [2] derived | Likely | — | Shown |
| Nearest mapped substation | Unnamed substation (345 kV)way/1473440687 | [4] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.7 km | [4] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 345 kV | [4] derived | Likely | 2026-09-28 | Shown |
| State avg. industrial price | 9.10¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 10.85¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 1.72 GW | [6] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 2 | [1] derived | Likely | 2026-05-02 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2026-05-02 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2023-10-01 | Superseded / alternative |
| Buildings operational | 0 | [1] estimated | Likely | 2025-09-08 | Superseded / alternative |
| Chip types | B300 | [1] | Confirmed | 2026-05-02 | Shown |
| Construction start | Oct 1, 2023 | [1] derived | Likely | 2026-05-02 | Shown |
| First operational | Dec 31, 2026 | [1] estimated | Speculative | 2026-05-02 | Shown |
| Expected completion | Jul 1, 2027 | [1] estimated | Speculative | 2026-05-02 | Shown |