DC
/

Proposed data center — EPLAN-2025-0195

PlannedEst.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.UnclassifiedSiteLoudoun County, Virginia

Proposed data center — EPLAN-2025-0195 is a planned data center in Virginia. Power capacity has not been disclosed or collected yet. Verification: documented development. 7 cited sources.

10% profile completeness
23 claims from 8 sources
Last verified against sources: Oct 12, 2026
Newest dated evidence: Oct 12, 2026
Follow

Get changes to Proposed data center — EPLAN-2025-0195

How often

Double opt-in; one-click unsubscribe in every email. We store only your email and what you follow. More

Or subscribe in a feed reader: RSS / Atom

Cite this
Text
Datacenter Source. “Proposed data center — EPLAN-2025-0195.” /facilities/proposed-data-center-eplan-2025-0195-loudoun-county-va. Data as of 2026-10-12. Accessed 2026-10-12.
BibTeX
@misc{datacentersource_proposed_data_center_eplan_2025_0195_lou_2026,
  title = {{Proposed data center — EPLAN-2025-0195}},
  author = {{Datacenter Source}},
  year = {2026},
  howpublished = {\url{/facilities/proposed-data-center-eplan-2025-0195-loudoun-county-va}},
  note = {Data as of 2026-10-12; accessed 2026-10-12. Compiled from cited sources, including OpenStreetMap contributors (ODbL) and Epoch AI (CC BY 4.0)},
}

Please also cite the original source of any specific figure (linked beside it).

Current facility power
Not yet sourced
Planned capacity
Not yet sourced
Floor area
Not yet sourced
Buildings (planned)
Not yet sourced
Capital cost / investment
Not yet sourced
First operational
Not yet sourced

POWER & GRID

Time-to-power · verification · interconnection
Time to power
H1 2028 – H2 2031
Low confidencewindow, not a prediction
Project verification
Documented development
Permitting documented by permit / site plan.
Current stage
Permitting
Furthest stage with documented evidence
Utility · ISO
Dominion Energy · PJM
Substation: Pleasant View Substation (230 kV) (nearest, unverified)

Power reality

Announced
No record
Interconnection request
No record
Contracted / approved
No record
Under construction
No record
Operational
No record
  • ⚠ No public interconnection record for this load — PJM does not publish large-load requests.
  • ⚠ No recorded land acquisition found.
AI evidence brief
Summarizes only the evidence on this page. Answers citing anything else are rejected automatically.
How the time-to-power window was estimated
Evidence used
  • Current stage: Permitting (furthest stage with documented evidence)[1]
  • No public grid record: No interconnection request or utility contract found; adds uncertainty to the upper bound.
Assumptions
  • From “Permitting”, large loads have typically taken 1.5–4 more years to first power (editorial range; see Methodology).
  • The window is a range of plausible outcomes under these assumptions, not a forecast. It moves as new filings, queue updates or imagery arrive.
Window: H1 2028 – H2 2031

Project verification

Development
  1. Announcedimplied by a later stage
  2. Land acquiredimplied by a later stage
  3. Planning / zoningOct 12, 2026
    Permit / site plan
    • Oct 12, 2026 · Permit / case ZMAP-2022-0021[1]
  4. Permitting2023
    Permit / site plan
    • 2023 · Loudoun County site plan LEGI-2023-0048 — Approved, 67,840 sq ft proposed.[1]
    • 2025 · Permit date[1]
    • 2025 · Loudoun County site plan EPLAN-2025-0195 — Active, 751,902 sq ft proposed.[1]
    • Oct 12, 2026 · Site plan EPLAN-2025-0195: Active[1]
    • Oct 12, 2026 · Permit / case EPLAN-2025-0195[1]
    • Oct 12, 2026 · Site plan LEGI-2023-0048: Approved[1]
    • Oct 12, 2026 · Permit / case LEGI-2023-0048[1]
Grid interconnection
  1. Interconnection application
  2. Feasibility study
  3. System impact study
  4. Facilities study
  5. Interconnection agreement / service contract
Build & energization
  1. Financing
  2. Under construction
  3. Energization
  4. Operational

● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Permit / site plan.

Grid path

  1. facility
    Proposed data center — EPLAN-2025-0195
  2. substation
    Pleasant View Substation (230 kV)[4]
    Proximity onlyUnverified
    Nearest mapped substation, 1.75 km away. Proximity does not establish that it serves the site.
  3. transmission
    514 (500 kV)[4]
    Proximity onlyUnverified
    Highest-voltage line mapped within 2 km (1.75 km away). Not confirmed as the supply path.
  4. utility
    Dominion Energy[2]
    Service territoryLikely
    Retail service territory containing the site
  5. ISO / RTO
    PJM[3]
    Service territoryLikely
    Balancing authority: PJM
Substation capacity:
not published
Required upgrades:
not yet sourced
Congestion:
not yet sourced (no nodal price data)

Dashed boxes are based on proximity only and do not establish which asset serves the site.

Interconnection records

No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.

On-site & dedicated generation

No on-site, behind-the-meter or dedicated generation found in sources.

LOCAL IMPACT

Water · generation · incentives · regulation · rates

Water & cooling

Not yet collected: we haven't found a source for water use or the cooling type at this site. Know one? Add a source

On-site generation & air permits

Not yet collected: we haven't found a source for on-site generation or an air permit for this site. Know one? Add a source

Incentives

Not yet collected: we haven't found a source for tax abatements, PILOTs or other incentives for this project. Know one? Add a source

Regulatory events2

  • Permit / site plan filed[1]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of 2025.2025

    Loudoun County site plan EPLAN-2025-0195 — Active, 751,902 sq ft proposed.

  • Permit / site plan approved[1]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of 2023.2023

    Loudoun County site plan LEGI-2023-0048 — Approved, 67,840 sq ft proposed.

Utility & rates1

  • GS-5 rate class for customers demanding 25 MW or more[8]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Nov 25, 2025.Nov 25, 2025
    Dominion Energy · Virginia State Corporation Commission · Docket PUR-2025-00058 · Final order issued · effective Jan 1, 2027

    “the new GS-5 rate class will comprise customers demanding 25 megawatts or more. The new rate class will be effective beginning January 1, 2027.”

    Applies to Dominion Energy Virginia's service territory; the facility's utility is the most likely retail provider by location unless a source names it.

Location & imagery

County parcel
Coordinates
39.07092, -77.50952
County
Loudoun County
Photographs

No openly licensed ground-level photos matched to this site yet.

Ownership, operation & customers

  1. 1. Property owner of record
    Not identified
  2. 2. Owner / developer
    Not identified
  3. 3. Operator
    Not identified
  4. 4. Tenant / cloud
    Not identified
  5. 5. End customer / workload
    Not identified
Power supply
Utility:

Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.

All parties with evidence
Utility

Location falls inside this utility's retail service territory.

No tenants or end users identified in our sources yet.

Power (all fields)

Current facility power
Not yet sourced
Planned capacity
Not yet sourced

Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.

Grid & electricity

ISO / RTO
PJM[3]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived

Location falls inside this ISO/RTO footprint.

Balancing authority
PJM[2]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived

Control area of the containing utility territory.

Nearest mapped substation
Pleasant View Substation (230 kV)[4]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived

Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.

Distance to substation
1.8 km[4]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
Highest-voltage line nearby
500 kV[4]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived

Highest-voltage transmission line mapped within 2 km.

State avg. industrial price
10.07¢/kWh[6]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed

Virginia statewide average, July 2026.

State avg. commercial price
11.68¢/kWh[6]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed

Virginia statewide average, July 2026.

Generation within 50 km
1.57 GW[7]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jan 1, 202502.Confirmedderived

43 EIA-reported plants within 50 km.

Generation queued in county
1.04 GW[5]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Confirmedderived

11 active generation interconnection requests in Loudoun County: Storage 940 MW, Solar 100 MW. Queued projects often don't get built.

Interconnection status
Not yet sourced
Contracted / committed power
Not yet sourced
Nearby infrastructureTypeDistanceVoltage / capacitySource
227;274 · Dominion EnergyTransmission line0.69 km230 kV[4]
203;2098 · Virginia Electric & Power CompanyTransmission line1.72 km230 kV[4]
514 · Virginia Electric & Power CompanyTransmission line1.75 km500 kV[4]
595 · Virginia Electric & Power CompanyTransmission line1.84 km500 kV[4]
500 kV line · Dominion EnergyTransmission line1.84 km500 kV[4]
Brambleton - Goose Creek · Virginia Electric & Power CompanyTransmission line1.94 km500 kV[4]
Potomac Energy Center, LLC · Potomac Energy Center LLCPower plant (Natural Gas)3.4 km766 MW[7]
Montgomery County Resource Recovery · Covanta Montgomery, Inc.Power plant (Biomass)15.2 km54 MW[7]
Dickerson Power · Dickerson Power, LLCPower plant (Natural Gas)15.9 km299 MW[7]
Blake Solar Plant · Horus West Virginia 1, LLCPower plant (Solar)35.2 km80 MW[7]
Nih Cogeneration Facility · National Institutes of HealthPower plant (Natural Gas)36.8 km28 MW[7]
Covanta Alexandria/Arlington Energy · Covanta Alexandria/ArlingtonPower plant (Biomass)44.5 km29 MW[7]
Central Utility Plant At White Oak · GSA Metropolitan Service CenterPower plant (Natural Gas)45.6 km54 MW[7]
Covanta Fairfax Energy · Covanta Fairfax IncPower plant (Biomass)47.8 km98 MW[7]
Pleasant View Substation · Dominion EnergySubstation1.75 km230 kV[4]
Pleasant View Substation · Dominion EnergySubstation1.86 km500 kV[4]
Goose Creek Substation · Dominion EnergySubstation1.97 km500 kV[4]
Ashburn Substation · Dominion EnergySubstation2.38 km230 kV[4]
Cochran Mill Delivery PointSubstation2.71 km230 kV[4]
Belmont Substation · Virginia Electric and Power CompanySubstation2.99 km230 kV[4]
Largest queued generation in this countyFuelQueue statusMWSource
Loudoun 230 kVPJM AG2-285StorageIn study · proposed 2023-12150 MW[5]
Beaumeade 230 kVPJM AG2-287StorageIn study · proposed 2023-12150 MW[5]
New Road StoragePJM AE2-019StorageIA signed · proposed 2026-12120 MW[5]
Dulles SolarPJM AF1-147SolarIA signed · proposed 2023-12100 MW[5]
Roundtable 230 kVPJM AG2-307StorageIn study · proposed 2023-12100 MW[5]
Shelhorn 230 kVPJM AG2-323StorageIn study · proposed 2023-12100 MW[5]

Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.

Construction & permitting

  1. Announced
    —
  2. Land acquired
    —
  3. Permitting
    2025[1]
  4. Construction start
    —
  5. First operational
    —
  6. Expected completion
    —
Permitting status
Site plan EPLAN-2025-0195: Active[1]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Oct 12, 2026.Confirmed
Permit / case numbers
ZMAP-2022-0021, EPLAN-2025-0195, LEGI-2023-0048[1]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Oct 12, 2026.Confirmed
Planned floor area
751,900 sq ft[1]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Oct 12, 2026.Confirmed

Building area proposed in the site plan.

Real estate

Official assessments
Assessor's value for a tax year

None sourced yet

Recorded transactions
Sale prices from recorded deeds

None sourced yet

Model estimates
Our model — not an appraisal

None sourced yet

Annual property tax
Not yet sourced

No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.

Size

Planned floor area
751,900 sq ft[1]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Oct 12, 2026.Confirmed

Building area proposed in the site plan.

Floor area
Not yet sourced

What changed (last 3 years)

Follow this facility (RSS)
  • Permitting status
    Site plan EPLAN-2025-0195: ActiveSep 27, 2026[1]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.→Site plan LEGI-2023-0048: ApprovedSep 27, 2026[1]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.→Site plan EPLAN-2025-0195: ActiveOct 5, 2026[1]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.→Site plan LEGI-2023-0048: ApprovedOct 5, 2026[1]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.→Site plan EPLAN-2025-0195: ActiveOct 12, 2026[1]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.→Site plan LEGI-2023-0048: ApprovedOct 12, 2026[1]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.
  • Planned floor area
    751,900 sq ftSep 27, 2026[1]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.→67,800 sq ftSep 27, 2026[1]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.→751,900 sq ftOct 5, 2026[1]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.→67,800 sq ftOct 5, 2026[1]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.→751,900 sq ftOct 12, 2026[1]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.→67,800 sq ftOct 12, 2026[1]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.

Timeline

  1. 2025[1]

    Loudoun County site plan EPLAN-2025-0195 — Active, 751,902 sq ft proposed.

  2. 2023[1]

    Loudoun County site plan LEGI-2023-0048 — Approved, 67,840 sq ft proposed.

All claims (provenance audit)

23
FieldValueSourceConfidenceAs ofStatus
NameProposed data center — EPLAN-2025-0195[1] derivedConfirmed2026-10-12Shown
StatusPlanned[1] derivedConfirmed2026-10-12Shown
StatusPlanned[1] derivedConfirmed2026-10-12Superseded / alternative
UtilityDominion Energyterritory 19876: VIRGINIA ELECTRIC & POWER CO (INVESTOR OWNED, DOMINION RESOURCE[2] derivedLikely2022Shown
ISO / RTOPJMPJM INTERCONNECTION, LLC[3] derivedLikely—Shown
Balancing authorityPJM[2] derivedLikely—Shown
Nearest mapped substationPleasant View Substation (230 kV)way/45842846[4] derivedLikely2026-09-28Shown
Distance to substation1.8 km[4] derivedLikely2026-09-28Shown
Highest-voltage line nearby500 kV[4] derivedLikely2026-09-28Shown
Generation queued in county1.04 GW[5] derivedConfirmed2026-10-12Shown
State avg. industrial price10.07¢/kWh[6] Confirmed2026-07Shown
State avg. commercial price11.68¢/kWh[6] Confirmed2026-07Shown
Generation within 50 km1.57 GW[7] derivedConfirmed202502Shown
Permitting statusSite plan EPLAN-2025-0195: ActiveApplication EPLAN-2025-0195, zoning case ZMAP-2022-0021[1] Confirmed2026-10-12Shown
Permitting statusSite plan LEGI-2023-0048: ApprovedApplication LEGI-2023-0048, zoning case ZMAP-2022-0021[1] Confirmed2026-10-12Superseded / alternative
Permit / case numbersEPLAN-2025-0195[1] Confirmed2026-10-12Shown
Permit / case numbersZMAP-2022-0021[1] Confirmed2026-10-12Shown
Permit / case numbersLEGI-2023-0048[1] Confirmed2026-10-12Shown
Permit / case numbersZMAP-2022-0021[1] Confirmed2026-10-12Shown
Planned floor area751,900 sq ft[1] Confirmed2026-10-12Shown
Planned floor area67,800 sq ft[1] Confirmed2026-10-12Superseded / alternative
Permit / site plan filed2025[1] derivedConfirmed2026-10-12Shown
Permit / site plan filed2023[1] derivedConfirmed2026-10-12Superseded / alternative