Microsoft SAT14
Microsoft SAT14 is an operating ai campus in San Antonio, Texas. Operated or owned by Microsoft. Current power: 66 MW (estimated). Verification: verified operating. 12 cited sources.
Follow
Get changes to Microsoft SAT14
Or subscribe in a feed reader: RSS / Atom
Cite this
Datacenter Source. “Microsoft SAT14.” /facilities/microsoft-sat14-san-antonio-tx. Data as of 2026-10-12. Accessed 2026-10-12.
@misc{datacentersource_microsoft_sat14_san_antonio_tx_2026,
title = {{Microsoft SAT14}},
author = {{Datacenter Source}},
year = {2026},
howpublished = {\url{/facilities/microsoft-sat14-san-antonio-tx}},
note = {Data as of 2026-10-12; accessed 2026-10-12. Compiled from cited sources, including OpenStreetMap contributors (ODbL) and Epoch AI (CC BY 4.0)},
}Please also cite the original source of any specific figure (linked beside it).
POWER & GRID
Time-to-power · verification · interconnectionPower reality
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- Under constructionFeb 18, 2022
Model estimate · Satellite imagery
- Feb 18, 2022 · Reported status: under construction[1]
- Feb 18, 2022 · Construction start[1]
- Feb 18, 2022 · Land clearing for the site is almost complete. Informed using imagery on [Google Earth](https://earth.google.com/web/@29.476115,-98.68118,277.21295794a,724.52967601d,35y,0h,0t,0r/)[1]
- Jul 1, 2024 · Reported status: expanding[1]
- EnergizationJul 1, 2024
Satellite imagery
- Jul 1, 2024 · Building 1 operational. The first 2 data halls of Building 1 (with chillers already installed) are likely to be already operational. Although construction was completed prior, the [1]
- Mar 31, 2026 · Building 2 fully operational, Building 1 expanded. Construction is already visibly complete. Additionally, construction phases [Phase 2](https://www.tdlr.texas.gov/TABS/Search/Proj[1]
- OperationalJul 1, 2024
Satellite imagery
- Jul 1, 2024 · Building 1 operational. The first 2 data halls of Building 1 (with chillers already installed) are likely to be already operational. Although construction was completed prior, the [1]
- Mar 31, 2026 · Building 2 fully operational, Building 1 expanded. Construction is already visibly complete. Additionally, construction phases [Phase 2](https://www.tdlr.texas.gov/TABS/Search/Proj[1]
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.
Grid path
- →facilityMicrosoft SAT14
- →substationSatellite imageryLikely1 substation outline traced inside the campus on satellite imagery; OSM maps Verde Circle Substation 0.27 km away
- →transmission138 kV line[5]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (0.23 km away). Not confirmed as the supply path.
- →utilityCPS Energy (City of San Antonio)[2]Service territoryLikelyRetail service territory containing the site
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
LOCAL IMPACT
Water · generation · incentives · regulation · ratesWater & cooling
Not yet collected: we haven't found a source for water use or the cooling type at this site. Know one? Add a source
On-site generation & air permits
Not yet collected: we haven't found a source for on-site generation or an air permit for this site. Know one? Add a source
Incentives
Not yet collected: we haven't found a source for tax abatements, PILOTs or other incentives for this project. Know one? Add a source
Regulatory events
Not yet collected: we haven't found a source for hearings, rezonings, permits or commission proceedings. Know one? Add a source
Utility & rates
Not yet collected: we haven't found a source for a large-load tariff or commission docket for CPS Energy (City of San Antonio). Know one? Add a source
Location & imagery
Mapped outline- Coordinates
- 29.47624, -98.68107
- Address
- 3545 Wiseman Boulevard, San Antonio, TX 78251[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Mar 31, 2026.Likely
- County
- Bexar County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workloadNot identified
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Utility
Most likely retail provider among 5 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: Pedernales Electric Coop, INC, Guadalupe Valley Elec Coop INC, Karnes Electric Coop INC, Bandera Electric Coop, INC.
No tenants or end users identified in our sources yet.
Power (all fields)
- Current facility power
- 66 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Mar 31, 2026.Likelyestimated
Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.
- Current IT capacity
- 47 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Mar 31, 2026.Likelyestimated
Estimated IT load currently online, based on buildings observed operational.
- Estimated annual consumption
- 405 GWh/yr[3]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Speculativeestimated
66 MW × 8,760 h × 70% utilization.
- Planned capacity
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
- ERCOT[4]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived
Location falls inside this ISO/RTO footprint.
- Balancing authority
- ERCO[2]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived
Control area of the containing utility territory.
- Nearest mapped substation
- Verde Circle Substation (138 kV)[5]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- 0.3 km[5]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
- Highest-voltage line nearby
- 138 kV[5]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
- 7.07¢/kWh[7]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed
Texas statewide average, July 2026.
- State avg. commercial price
- 8.47¢/kWh[7]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed
Texas statewide average, July 2026.
- Generation within 50 km
- 4.3 GW[8]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jan 1, 202502.Confirmedderived
22 EIA-reported plants within 50 km.
- Generation queued in county
- 4.96 GW[6]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 1, 2026.Confirmedderived
21 active generation interconnection requests in Bexar County: Storage 4,771 MW, Solar 152 MW, Gas 35 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 138 kV line | Transmission line | 0.23 km | 138 kV | [5] |
| Leon Creek · City of San Antonio - (TX) | Power plant (Natural Gas) | 17.1 km | 184 MW | [8] |
| Oci Alamo Solar I Hybrid · OCI Energy LLC | Power plant (Solar) | 32.3 km | 41 MW | [8] |
| Oci Alamo 4, LLC · Consolidated Edison Development Inc. | Power plant (Solar) | 37 km | 40 MW | [8] |
| Ebony Energy Storage · Ebony Energy Storage, LLC | Power plant (Batteries) | 37.1 km | 200 MW | [8] |
| Arthur Von Rosenberg · City of San Antonio - (TX) | Power plant (Natural Gas) | 37.7 km | 518 MW | [8] |
| V H Braunig · City of San Antonio - (TX) | Power plant (Natural Gas) | 37.9 km | 1.05 GW | [8] |
| O W Sommers · City of San Antonio - (TX) | Power plant (Natural Gas) | 39.3 km | 830 MW | [8] |
| J K Spruce · City of San Antonio - (TX) | Power plant (Coal) | 39.6 km | 1.35 GW | [8] |
| Verde Circle Substation · CPS Energy | Substation | 0.27 km | 138 kV | [5] |
| VLSI Substation · CPS Energy | Substation | 0.39 km | 138 kV | [5] |
| Westover Hills Substation · CPS Energy | Substation | 1.4 km | 138 kV | [5] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| Howard Road BESSERCOT 29INR0173 · Project Fast Flow LLC | Storage | In study · proposed 2028-04 | 618 MW | [6] |
| Orbit Energy StorageERCOT 27INR0082 · GCI Orbit Energy Storage, LLC | Storage | In study · proposed 2027-06 | 502 MW | [6] |
| Bernice Energy StorageERCOT 27INR0294 · Bernice Energy Storage LLC | Storage | In study · proposed 2029-02 | 403 MW | [6] |
| Mission Station Energy Storage IERCOT 28INR0474 · Mission Station LLC | Storage | In study · proposed 2030-05 | 375 MW | [6] |
| Mission Station Energy Storage IIERCOT 28INR0475 · Mission Station LLC | Storage | In study · proposed 2030-05 | 375 MW | [6] |
| Quela BESSERCOT 22INR0423 · BRP Quela BESS LLC | Storage | In study · proposed 2027-12 | 301 MW | [6] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction startFeb 18, 2022[1]
- First operationalJul 1, 2024[1]
- Expected completion—
- Buildings (planned)
- 2[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Mar 31, 2026.Likelyderived
Count of building outlines traced on satellite imagery.
- Buildings operational
- 2[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Mar 31, 2026.Likelyestimated
Real estate
None sourced yet
None sourced yet
None sourced yet
- Capital cost / investment
- $1.8B[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Mar 31, 2026.Likelyestimated
Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Floor area
- Not yet sourced
Compute
- Chip types
- H100, B300[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Mar 31, 2026.Confirmed
- Compute (H100-equivalents)
- 45,200[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Mar 31, 2026.Likelyestimated
What changed (last 3 years)
Follow this facility (RSS)- Current IT capacity19 MWJul 1, 2024[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→47 MWMar 31, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
- Current facility power26 MWJul 1, 2024[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→66 MWMar 31, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
- Buildings operational0Feb 18, 2022[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→1Jul 1, 2024[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→2Mar 31, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
- StatusUnder constructionFeb 18, 2022[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→Operating + expandingJul 1, 2024[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→OperatingMar 31, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
Timeline
- Feb 18, 2022[1]
Land clearing for the site is almost complete. Informed using imagery on Google Earth
Building 1 operational. The first 2 data halls of Building 1 (with chillers already installed) are likely to be already operational. Although construction was completed prior, the on-site substation was previously incomplete, so we believe it was only operational at this point.
Building 2 chiller installation is a little more than halfway complete, and chiller installation for the last data hall of Building 1 is also around halfway complete.
No more visible construction around either building, just a little equipment. Roads fully built around buildings as well.
Building 2 fully operational, Building 1 expanded. Construction is already visibly complete. Additionally, construction phases Phase 2, Phase 3, and Phase 4 on TDLR that collectively represent the completion of the site have a completion date of 2026-03-31.
All claims (provenance audit)
40| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Microsoft SAT14 | [1] | Likely | 2026-03-31 | Shown |
| Status | Under construction | [1] derived | Likely | 2022-02-18 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2024-07-01 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-08-03 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-02-28 | Superseded / alternative |
| Status | Operating | [1] derived | Likely | 2026-03-31 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-03-31 | Shown |
| Address | 3545 Wiseman Boulevard, San Antonio, TX 78251 | [1] | Likely | 2026-03-31 | Shown |
| Owner | MicrosoftOwner: Microsoft | [1] | Confirmed | 2026-03-31 | Shown |
| Utility | CPS Energy (City of San Antonio)territory 16604: CITY OF SAN ANTONIO - (TX) (MUNICIPAL, CITY OF SAN ANTONIO - (T | [2] derived | Unverified | 2022 | Shown |
| Current facility power | 66 MW | [1] estimated | Likely | 2026-03-31 | Shown |
| Current facility power | 26 MW | [1] estimated | Likely | 2024-07-01 | Superseded / alternative |
| Current facility power | 26 MW | [1] estimated | Likely | 2025-08-03 | Superseded / alternative |
| Current facility power | 26 MW | [1] estimated | Likely | 2026-02-28 | Superseded / alternative |
| Current IT capacity | 47 MW | [1] estimated | Likely | 2026-03-31 | Shown |
| Current IT capacity | 19 MW | [1] estimated | Likely | 2024-07-01 | Superseded / alternative |
| Current IT capacity | 19 MW | [1] estimated | Likely | 2025-08-03 | Superseded / alternative |
| Current IT capacity | 19 MW | [1] estimated | Likely | 2026-02-28 | Superseded / alternative |
| Estimated annual consumption | 405 GWh/yr | [3] estimated | Speculative | 2026-10-12 | Shown |
| ISO / RTO | ERCOTELECTRIC RELIABILITY COUNCIL OF TEXAS, INC. | [4] derived | Likely | — | Shown |
| Balancing authority | ERCO | [2] derived | Likely | — | Shown |
| Nearest mapped substation | Verde Circle Substation (138 kV)way/1344369108 | [5] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.3 km | [5] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 138 kV | [5] derived | Likely | 2026-09-28 | Shown |
| Generation queued in county | 4.96 GW | [6] derived | Confirmed | 2026-10-01 | Shown |
| State avg. industrial price | 7.07¢/kWh | [7] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 8.47¢/kWh | [7] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 4.3 GW | [8] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 2 | [1] derived | Likely | 2026-03-31 | Shown |
| Buildings operational | 2 | [1] estimated | Likely | 2026-03-31 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2022-02-18 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2024-07-01 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2025-08-03 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2026-02-28 | Superseded / alternative |
| Capital cost / investment | $1.8B | [1] estimated | Likely | 2026-03-31 | Shown |
| Compute (H100-equivalents) | 45,200 | [1] estimated | Likely | 2026-03-31 | Shown |
| Chip types | H100 | [1] | Confirmed | 2026-03-31 | Shown |
| Chip types | B300 | [1] | Confirmed | 2026-03-31 | Shown |
| Construction start | Feb 18, 2022 | [1] derived | Likely | 2026-03-31 | Shown |
| First operational | Jul 1, 2024 | [1] derived | Likely | 2026-03-31 | Shown |