Amazon IAD-145
Amazon IAD-145 is an operating hyperscale in Sterling, Virginia. Operated or owned by Amazon Web Services. Current power: 50 MW (estimated). Verification: verified operating. 9 cited sources.
Part of Amazon Web Services — Sterling, VA campus
Follow
Get changes to Amazon IAD-145
Or subscribe in a feed reader: RSS / Atom
Cite this
Datacenter Source. “Amazon IAD-145.” /facilities/amazon-iad-145-sterling-va. Data as of 2026-10-12. Accessed 2026-10-12.
@misc{datacentersource_amazon_iad_145_sterling_va_2026,
title = {{Amazon IAD-145}},
author = {{Datacenter Source}},
year = {2026},
howpublished = {\url{/facilities/amazon-iad-145-sterling-va}},
note = {Data as of 2026-10-12; accessed 2026-10-12. Compiled from cited sources, including OpenStreetMap contributors (ODbL) and Epoch AI (CC BY 4.0)},
}Please also cite the original source of any specific figure (linked beside it).
POWER & GRID
Time-to-power · verification · interconnectionPower reality
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Permit / site plan, Community map.
Grid path
- →facilityAmazon IAD-145
- →substationUnnamed substation (34.5 kV)[1]Proximity onlyUnverifiedNearest mapped substation, 1.18 km away. Proximity does not establish that it serves the site.
- →transmission230 kV line[1]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (1.28 km away). Not confirmed as the supply path.
- →
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
| Queue | Relationship | Stage | MW req. | MW appr. | Queued | Expected in service | POI / TO | Source · as of |
|---|---|---|---|---|---|---|---|---|
PJM AF1-147 Dulles Solar · Solar | Possibly related generation Speculative Generation request name/developer shares “dulles” with this facility, in the same county. Not confirmed as serving it. | Interconnection agreement executed Engineering and Procurement; feasibility: Document Posted; system impact: Document Posted; facilities: Document Posted; ISA/GIA: Document Posted | 100 ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Oct 12, 2026. | 60 | Sep 20, 2019 | Dec 31, 2023 | Poland Rd-Runway DP 230kV TO: Dominion | [6] Oct 12, 2026 |
On-site & dedicated generation
- PJM AF1-147 Dulles Solar (Solar, 100 MW requested)[6]Generation request name/developer shares “dulles” with this facility, in the same county. Not confirmed as serving it.SolarArrangement unknown100 MWConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Speculative
LOCAL IMPACT
Water · generation · incentives · regulation · ratesWater & cooling
Not yet collected: we haven't found a source for water use or the cooling type at this site. Know one? Add a source
On-site generation & air permits1
- Air permit VA0000005110774153[9]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Apr 24, 2026.Apr 24, 202680% Synthetic Minor Emissions · Operating · No Violation Identified · Programs: State Implementation Plan
ECHO lists “AMAZON DATA SERVICES, INC. IAD-144 IAD-145” at 22945 INTERNATIONAL DRIVE, STERLING, 211 m from this facility's mapped location (matched by location; the permit name matches this facility or its companies).
Incentives
Not yet collected: we haven't found a source for tax abatements, PILOTs or other incentives for this project. Know one? Add a source
Regulatory events
Not yet collected: we haven't found a source for hearings, rezonings, permits or commission proceedings. Know one? Add a source
Utility & rates1
- GS-5 rate class for customers demanding 25 MW or more[10]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Nov 25, 2025.Nov 25, 2025Dominion Energy · Virginia State Corporation Commission · Docket PUR-2025-00058 · Final order issued · effective Jan 1, 2027
“the new GS-5 rate class will comprise customers demanding 25 megawatts or more. The new rate class will be effective beginning January 1, 2027.”
Applies to Dominion Energy Virginia's service territory; the facility's utility is the most likely retail provider by location unless a source names it.
Location & imagery
Mapped outline- Coordinates
- 38.98248, -77.42434
- Address
- 22916 International Drive, Sterling, VA 20166[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Likely
- County
- Loudoun County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of record
- 2. Owner / developerNot identified
- 3. Operator
- 4. Tenant / cloudNot identified
- 5. End customer / workloadNot identified
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Property owner of record
- Operator
- Utility
Most likely retail provider among 2 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: Northern Virginia Elec Coop.
No tenants or end users identified in our sources yet.
Power (all fields)
- Current facility power
- 50 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Likely
- Estimated annual consumption
- 307 GWh/yr[4]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Speculativeestimated
50 MW × 8,760 h × 70% utilization.
- Planned capacity
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
- PJM[5]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived
Location falls inside this ISO/RTO footprint.
- Balancing authority
- PJM[3]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived
Control area of the containing utility territory.
- Nearest mapped substation
- Unnamed substation (34.5 kV)[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- 1.2 km[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
- Highest-voltage line nearby
- 230 kV[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
- 10.07¢/kWh[7]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed
Virginia statewide average, July 2026.
- State avg. commercial price
- 11.68¢/kWh[7]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed
Virginia statewide average, July 2026.
- Generation within 50 km
- 1.63 GW[8]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jan 1, 202502.Confirmedderived
65 EIA-reported plants within 50 km.
- Generation queued in county
- 1.04 GW[6]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Confirmedderived
11 active generation interconnection requests in Loudoun County: Storage 940 MW, Solar 100 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 230 kV line | Transmission line | 1.28 km | 230 kV | [1] |
| 2079;2194 · Dominion Energy | Transmission line | 1.35 km | 230 kV | [1] |
| 2194 | Transmission line | 1.37 km | 230 kV | [1] |
| 2079 · Dominion Energy | Transmission line | 1.37 km | 230 kV | [1] |
| 2150 · Dominion Energy | Transmission line | 1.41 km | 230 kV | [1] |
| 2081 | Transmission line | 1.43 km | 230 kV | [1] |
| Potomac Energy Center, LLC · Potomac Energy Center LLC | Power plant (Natural Gas) | 13.4 km | 766 MW | [8] |
| Montgomery County Resource Recovery · Covanta Montgomery, Inc. | Power plant (Biomass) | 24.4 km | 54 MW | [8] |
| Dickerson Power · Dickerson Power, LLC | Power plant (Natural Gas) | 25.5 km | 299 MW | [8] |
| Nih Cogeneration Facility · National Institutes of Health | Power plant (Natural Gas) | 28.6 km | 28 MW | [8] |
| Covanta Alexandria/Arlington Energy · Covanta Alexandria/Arlington | Power plant (Biomass) | 32.6 km | 29 MW | [8] |
| Covanta Fairfax Energy · Covanta Fairfax Inc | Power plant (Biomass) | 35.7 km | 98 MW | [8] |
| Central Utility Plant At White Oak · GSA Metropolitan Service Center | Power plant (Natural Gas) | 38.7 km | 54 MW | [8] |
| Blake Solar Plant · Horus West Virginia 1, LLC | Power plant (Solar) | 47.1 km | 80 MW | [8] |
| Unnamed substation | Substation | 1.18 km | 34.5 kV | [1] |
| Davis Drive Substation · Virginia Electric & Power Company | Substation | 1.34 km | 230 kV | [1] |
| Sterling Park Substation · Dominion Energy | Substation | 1.39 km | 230 kV | [1] |
| Global Plaza Substation · Dominion Energy | Substation | 1.49 km | 230 kV | [1] |
| Ocean Court Substation | Substation | 1.83 km | 230 kV | [1] |
| Pacific Substation · Dominion Energy | Substation | 1.93 km | 230 kV | [1] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| Loudoun 230 kVPJM AG2-285 | Storage | In study · proposed 2023-12 | 150 MW | [6] |
| Beaumeade 230 kVPJM AG2-287 | Storage | In study · proposed 2023-12 | 150 MW | [6] |
| New Road StoragePJM AE2-019 | Storage | IA signed · proposed 2026-12 | 120 MW | [6] |
| Dulles SolarPJM AF1-147 | Solar | IA signed · proposed 2023-12 | 100 MW | [6] |
| Roundtable 230 kVPJM AG2-307 | Storage | In study · proposed 2023-12 | 100 MW | [6] |
| Shelhorn 230 kVPJM AG2-323 | Storage | In study · proposed 2023-12 | 100 MW | [6] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction start—
- First operational—
- Expected completion—
- Permit / case numbers
- B80346860100[2]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Oct 12, 2026.Confirmed
Real estate
None sourced yet
None sourced yet
None sourced yet
| Parcel | Record owner | Acres | Zoning / use | Building sq ft | Source |
|---|---|---|---|---|---|
| 034365461000 Loudoun County, VA | DULLES NCP LLC Project: Jk Corporate Campus | 13 | IP (ZRTD-2018-0002) · Data Center | 203,200 built | [2] |
- Site area
- 13 acres[2]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Oct 12, 2026.Confirmed
Legal acreage of the parcel(s).
- Zoning
- IP[2]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Oct 12, 2026.Confirmed
- Land use
- Data Center[2]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Oct 12, 2026.Confirmed
- Annual property tax
- Not yet sourced
Size
- Floor area
- 203,200 sq ft[2]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Oct 12, 2026.Confirmed
Building area on the county's data-center parcel inventory (from building permits).
- Building footprint
- 103,800 sq ft[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Likelyderived
Computed from the mapped OSM building outline.
- Parcel / land records
- MCPI 034365461000 (Loudoun County)[2]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Oct 12, 2026.Confirmed
What changed (last 3 years)
Follow this facility (RSS)No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.
Timeline
No dated events sourced yet.
Other buildings on this campus
29- Amazon IAD-76Operating · 138,300 sq ft footprint
- Amazon IAD-12Operating · 149,800 sq ft footprint
- Amazon IAD-16Operating · 75,900 sq ft footprint
- Amazon IAD-15Operating · 103,600 sq ft footprint
- Amazon IAD-87Operating · 147,600 sq ft footprint
- Amazon IAD-88Operating · 147,700 sq ft footprint
- Amazon IAD-57Operating · 116,700 sq ft footprint
- Proposed data center — Summit At DullesPlanned · 136,200 sq ft footprint
- Proposed data center — Sdc AshburnPlanned · 163,000 sq ft footprint
- Amazon IAD-56Operating · 78,600 sq ft footprint
- Amazon IAD-58Operating · 137,000 sq ft footprint
- Amazon IAD-51Operating · 64,200 sq ft footprint
- Amazon IAD-146Operating · 103,200 sq ft footprint
- Amazon IAD-147Operating · 102,900 sq ft footprint
- Amazon IAD-192Operating · 133,100 sq ft footprint
- Amazon IAD-214Operating · 113,600 sq ft footprint
- Amazon IAD-285Under construction · 130,800 sq ft footprint
- Proposed data center — Stack Broad Run Land CondoPlanned · 129,000 sq ft footprint
- Amazon IAD-144Operating · 150,600 sq ft footprint
- Amazon IAD-140Operating · 215,400 sq ft footprint
- Amazon IAD-141Operating · 217,200 sq ft footprint
- Amazon IAD-175Operating · 86,600 sq ft footprint
- Amazon IAD-143Operating · 132,700 sq ft footprint
- Amazon IAD-142Operating · 129,800 sq ft footprint
- Amazon IAD-603Operating · 14,800 sq ft footprint
- Amazon IAD-608Operating · 14,100 sq ft footprint
- Amazon IAD-90Operating · 148,000 sq ft footprint
- Amazon IAD-91Operating · 149,700 sq ft footprint
- Amazon IAD-92Operating · 150,100 sq ft footprint
All claims (provenance audit)
26| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Amazon IAD-145way/744491691 name=Amazon IAD-145 | [1] | Likely | 2026-10-12 | Shown |
| Status | Operating | [1] derived | Unverified | 2026-10-12 | Shown |
| Status | Operating | [2] derived | Confirmed | 2026-10-12 | Shown |
| Facility type | Hyperscale | [1] derived | Unverified | 2026-10-12 | Shown |
| Address | 22916 International Drive, Sterling, VA 20166 | [1] | Likely | 2026-10-12 | Shown |
| Property owner of record | Dulles Ncp LLCMCPI 034365461000: DULLES NCP LLC | [2] | Confirmed | 2026-10-12 | Shown |
| Operator | Amazon Web Servicesoperator=Amazon Web Services | [1] | Likely | 2026-10-12 | Shown |
| Utility | Dominion Energyterritory 19876: VIRGINIA ELECTRIC & POWER CO (INVESTOR OWNED, DOMINION RESOURCE | [3] derived | Unverified | 2022 | Shown |
| Current facility power | 50 MWinput:electricity=50 MW | [1] | Likely | 2026-10-12 | Shown |
| Estimated annual consumption | 307 GWh/yr | [4] estimated | Speculative | 2026-10-12 | Shown |
| ISO / RTO | PJMPJM INTERCONNECTION, LLC | [5] derived | Likely | — | Shown |
| Balancing authority | PJM | [3] derived | Likely | — | Shown |
| Nearest mapped substation | Unnamed substation (34.5 kV)way/1022744253 | [1] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 1.2 km | [1] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 230 kV | [1] derived | Likely | 2026-09-28 | Shown |
| Generation queued in county | 1.04 GW | [6] derived | Confirmed | 2026-10-12 | Shown |
| State avg. industrial price | 10.07¢/kWh | [7] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 11.68¢/kWh | [7] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 1.63 GW | [8] derived | Confirmed | 202502 | Shown |
| Permit / case numbers | B80346860100 | [2] | Confirmed | 2026-10-12 | Shown |
| Floor area | 203,200 sq ft | [2] | Confirmed | 2026-10-12 | Shown |
| Building footprint | 103,800 sq ft | [1] derived | Likely | 2026-10-12 | Shown |
| Site area | 13 acres | [2] | Confirmed | 2026-10-12 | Shown |
| Parcel / land records | MCPI 034365461000 (Loudoun County) | [2] | Confirmed | 2026-10-12 | Shown |
| Zoning | IP | [2] | Confirmed | 2026-10-12 | Shown |
| Land use | Data Center | [2] | Confirmed | 2026-10-12 | Shown |