Compare Virginia vs Texas vs Georgia vs Ohio
Side-by-side capacity, pipeline, the announced-vs-documented gap, time to power and evidence coverage. MW figures are floors: they sum only facilities that disclose a figure, so a low number with low coverage means “not collected”, not “small”. Data as of Oct 12, 2026.
| Metric | Virginia | Texas | Georgia | Ohio |
|---|---|---|---|---|
| Facilities tracked | 482 | 195 | 58 | 99 |
| Power online (floor) Operating sites with a figure; evidence mix below | 5.43 GW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.100% | 1.82 GW AnnouncedStated by the company or reported in the press; not yet backed by a filing or grid record.11%EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.89% | 923 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.100% | 1.8 GW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.100% |
| Pipeline (floor) Planned MW at sites under construction or planned | 628 MW | 8.14 GW | — | 1.84 GW |
| Announced Largest MW reported by a company, utility, government or press source | 1.42 GW | 12.49 GW | 10 MW | 3.72 GW |
| Documented Per site: grid-backed MW, or operational + under-construction MW | 7.64 GW | 7.71 GW | 923 MW | 3.63 GW |
| Announced, no grid/construction/operating record Sites announced ≥ 100 MW with nothing documented yet | — | 4.36 GW | — | 650 MW |
| Pending MW: < 1 year Announced minus operational, by time-to-power bucket | — | 5.98 GW | — | 870 MW |
| Pending MW: 1–2 years Announced minus operational, by time-to-power bucket | 628 MW | 3.01 GW | — | 966 MW |
| Pending MW: 2–4 years Announced minus operational, by time-to-power bucket | — | 2.16 GW | — | 650 MW |
| Pending MW: 4+ years Announced minus operational, by time-to-power bucket | — | — | — | — |
| Pending MW: Insufficient evidence Announced minus operational, by time-to-power bucket | — | — | — | — |
| Facilities with a power figure | 21% (102) | 12% (24) | 7% (4) | 11% (11) |
| Facilities with confirmed evidence | 87% (417) | 8% (15) | 0% (0) | 67% (66) |