Applied Digital

What changed

Developer · also matched as Applied Digital Corporation

Applied Digital is linked to 4 tracked US data centers in 3 states as owner, operator, developer, tenant, utility or other party. Facilities with a disclosed figure add up to 88 MW online and 442 MW in the pipeline (floors: 4 of 4 report power). Every relationship cites its source.

View on map →
Follow

Get changes to Applied Digital

How often

Double opt-in; one-click unsubscribe in every email. We store only your email and what you follow. More

Or subscribe in a feed reader: RSS / Atom

Cite this
Text
Datacenter Source. “Applied Digital: US data center footprint.” /companies/applied-digital. Data as of 2026-10-12. Accessed 2026-10-12.
BibTeX
@misc{datacentersource_applied_digital_2026,
  title = {{Applied Digital: US data center footprint}},
  author = {{Datacenter Source}},
  year = {2026},
  howpublished = {\url{/companies/applied-digital}},
  note = {Data as of 2026-10-12; accessed 2026-10-12. Compiled from cited sources, including OpenStreetMap contributors (ODbL) and Epoch AI (CC BY 4.0)},
}

Please also cite the original source of any specific figure (linked beside it).

Linked facilities
4
States
3
Reported power online (floor)
88 MW
EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.100%
Reported planned capacity (floor)
1.6 GW
ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.100%
This company's facilities:Download CSVJSONAPI docs

Floors, not totals: power sums only facilities with a reported or estimated figure (4 of 4), across all roles (a company can be tenant at one site and owner at another). “—” means not disclosed or not yet collected.

Loading map…

US footprint by state

Relationship graph

Derived from the ownership → operation → tenancy → workload chain at each shared facility, plus company-to-company relationships extracted from cited documents. Speculative links are excluded.

Develops for

  • CoreWeave1 site · Confirmed
    CoreWeave Ellendale ND
FacilityRoleLocationStatusPower
Applied Digital Center, NDDeveloper Center, NDUnknown430 MW planned ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.
Applied Digital Toronto, SDDeveloper Toronto, SDUnknown430 MW planned ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.
Applied Digital AlexandriaDeveloper Alexandria, LAUnknown210 MW planned ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.
CoreWeave Ellendale NDDeveloper Ellendale, NDOperating + expanding88 MW EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.