What changed — Dominion Energy
Follow
Get changes to Dominion Energy
Or subscribe in a feed reader: RSS / Atom
Capacity, status, permit, grid-request and construction changes over the last three years, each with its source. A change means the same source reported a new value later; two sources disagreeing is not a change. Follow a facility, company, utility, state or ISO by email, or subscribe to the feed in any RSS reader.
Each change is tagged by evidence: ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. filing, deed, permit or grid recordAnnouncedStated by the company or reported in the press; not yet backed by a filing or grid record. company or press claimEst.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. satellite, model or map inferenceHow levels are assigned
- Oct 7, 2024NTT VA10 · VA
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Land acquired: Deed recorded for parcel 7397-56-8403 (owner of record: Ntt Global Data Centers Va10 LLC Attn: Legal Dept).
- Oct 1, 2024Google Arcola · VA
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Construction started: Building 1 foundation started
Source: Epoch AI - Oct 1, 2024STACK Infrastructure NVA02 · VA
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Buildings operational: 0 → 1
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Status: Under construction → Operating + expanding
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.New capacity online: Building 1 is operational, which is assumed to be three months after the last backup diesel generators are finished. The generators were first seen to be finished July 1 from satellite imagery (a clear image of this c…
Source: Epoch AI