DC
/

QTS NAL 2 DC1

OperatingEst.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.ColocationBuildingNew Albany, Licking County, Ohio

QTS NAL 2 DC1 is an operating colocation in New Albany, Ohio. Operated or owned by QTS Data Centers. Power capacity has not been disclosed or collected yet. Verification: verified operating. 8 cited sources.

Part of QTS Data Centers — New Albany, OH campus

50% profile completeness
25 claims from 9 sources
Last verified against sources: Oct 12, 2026
Newest dated evidence: Oct 12, 2026
Follow

Get changes to QTS NAL 2 DC1

How often

Double opt-in; one-click unsubscribe in every email. We store only your email and what you follow. More

Or subscribe in a feed reader: RSS / Atom

Cite this
Text
Datacenter Source. “QTS NAL 2 DC1.” /facilities/qts-nal-2-dc1-new-albany-oh. Data as of 2026-10-12. Accessed 2026-10-12.
BibTeX
@misc{datacentersource_qts_nal_2_dc1_new_albany_oh_2026,
  title = {{QTS NAL 2 DC1}},
  author = {{Datacenter Source}},
  year = {2026},
  howpublished = {\url{/facilities/qts-nal-2-dc1-new-albany-oh}},
  note = {Data as of 2026-10-12; accessed 2026-10-12. Compiled from cited sources, including OpenStreetMap contributors (ODbL) and Epoch AI (CC BY 4.0)},
}

Please also cite the original source of any specific figure (linked beside it).

Current facility power
Not yet sourced
Planned capacity
Not yet sourced
Floor area
327,000 sq ft[1]
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Unverifiedestimated
Buildings (planned)
Not yet sourced
Capital cost / investment
Not yet sourced
First operational
Sep 1, 2024[1]
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Likely

POWER & GRID

Time-to-power · verification · interconnection
Time to power
Energized — operating
High confidence
Project verification
Verified operating
Operation documented by government record.
Current stage
Operational
Furthest stage with documented evidence
Utility · ISO
American Electric Power · PJM
Substation: Macy Substation (138 kV) (nearest, unverified)

Power reality

Announced
No record
Interconnection request
No record
Contracted / approved
No record
Under construction
No record
Operational
No record
AI evidence brief
Summarizes only the evidence on this page. Answers citing anything else are rejected automatically.

Project verification

Development
  1. Announcedimplied by a later stage
  2. Land acquiredJun 6, 2024
    Government record
    • Jun 6, 2024 · Land acquisition / deed recorded[2]
    • Jun 6, 2024 · Deed/transfer recorded for parcel 094-107502-00.003 (no sale price disclosed).[2]
    • Oct 12, 2026 · Owner of record in county parcel data[2]
  3. Planning / zoningimplied by a later stage
  4. Permittingimplied by a later stage
Grid interconnection
  1. Interconnection application
  2. Feasibility study
  3. System impact study
  4. Facilities study
  5. Interconnection agreement / service contract
Build & energization
  1. Financing
  2. Under constructionimplied by a later stage
  3. Energizationimplied by a later stage
  4. OperationalOct 12, 2026
    Community map · Government record
    • Oct 12, 2026 · Reported status: operating[1]
    • Oct 12, 2026 · County land use: 305: Research/Chemical Labs[2]

● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Government record, Community map.

Grid path

  1. facility
    QTS NAL 2 DC1
  2. substation
    Macy Substation (138 kV)[1]
    Proximity onlyUnverified
    Nearest mapped substation, 0.17 km away. Proximity does not establish that it serves the site.
  3. transmission
    138 kV line[1]
    Proximity onlyUnverified
    Highest-voltage line mapped within 2 km (0.16 km away). Not confirmed as the supply path.
  4. utility
    American Electric Power[3]
    Service territoryLikely
    Retail service territory containing the site
  5. ISO / RTO
    PJM[4]
    Service territoryLikely
    Balancing authority: PJM
Substation capacity:
not published
Required upgrades:
not yet sourced
Congestion:
not yet sourced (no nodal price data)

Dashed boxes are based on proximity only and do not establish which asset serves the site.

Interconnection records

No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.

On-site & dedicated generation

No on-site, behind-the-meter or dedicated generation found in sources.

LOCAL IMPACT

Water · generation · incentives · regulation · rates

Water & cooling

Not yet collected: we haven't found a source for water use or the cooling type at this site. Know one? Add a source

On-site generation & air permits1

  • Air permit OH0000000145000603[8]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of May 29, 2026.May 29, 2026
    80% Synthetic Minor Emissions · Operating · No Violation Identified · Programs: State Implementation Plan

    ECHO lists “QTS NEW ALBANY I, LLC” at 785 BEECH RD SW, OHIO, 36 m from this facility's mapped location (matched by location; the permit name doesn't identify the operator).

Incentives

Not yet collected: we haven't found a source for tax abatements, PILOTs or other incentives for this project. Know one? Add a source

Regulatory events

Not yet collected: we haven't found a source for hearings, rezonings, permits or commission proceedings. Know one? Add a source

Utility & rates1

  • AEP Ohio data center tariff[9]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 9, 2025.Jul 9, 2025
    American Electric Power · Public Utilities Commission of Ohio · Docket 24-508-EL-ATA · Order issued; moratorium on new data center connections to be lifted

    “AEP Ohio is ordered to file updated tariffs and lift its moratorium on connecting new data centers as soon as possible.”

    Applies in AEP Ohio's territory (AEP operating company in Ohio).

Location & imagery

Mapped outline
Coordinates
40.05579, -82.75661
Address
785 Beech Road Southwest, New Albany, OH 43054[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Likely
County
Licking County
Photographs

No openly licensed ground-level photos matched to this site yet.

Ownership, operation & customers

  1. 1. Property owner of record
  2. 2. Owner / developer
    Not identified
  3. 3. Operator
  4. 4. Tenant / cloud
    Not identified
  5. 5. End customer / workload
    Not identified
Power supply
Utility:

Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.

All parties with evidence
Property owner of record
Operator
Utility

Most likely retail provider among 2 overlapping service territories (largest retail sales; territory polygons are approximate). Also overlapping: Licking Rural Electric INC.

No tenants or end users identified in our sources yet.

Power (all fields)

Current facility power
Not yet sourced
Planned capacity
Not yet sourced

Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.

Grid & electricity

ISO / RTO
PJM[4]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived

Location falls inside this ISO/RTO footprint.

Balancing authority
PJM[3]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived

Control area of the containing utility territory.

Nearest mapped substation
Macy Substation (138 kV)[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived

Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.

Distance to substation
0.2 km[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
Highest-voltage line nearby
138 kV[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived

Highest-voltage transmission line mapped within 2 km.

State avg. industrial price
10.95¢/kWh[6]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed

Ohio statewide average, July 2026.

State avg. commercial price
14.06¢/kWh[6]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed

Ohio statewide average, July 2026.

Generation within 50 km
25 MW[7]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jan 1, 202502.Confirmedderived

9 EIA-reported plants within 50 km.

Generation queued in county
2.52 GW[5]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Confirmedderived

14 active generation interconnection requests in Licking County: Solar 1,773 MW, Storage 750 MW. Queued projects often don't get built.

Interconnection status
Not yet sourced
Contracted / committed power
Not yet sourced
Nearby infrastructureTypeDistanceVoltage / capacitySource
138 kV lineTransmission line0.16 km138 kV[1]
Denison Solar Array · AEP Onsite Partners, LLCPower plant (Solar)20.4 km2 MW[7]
Dodge Park Engine No 1 · City of Columbus - (OH)Power plant (Petroleum)24.8 km2 MW[7]
St-1/1a Engine No 1 · City of Columbus - (OH)Power plant (Petroleum)25 km1 MW[7]
Renick Run Pumping Station 03-04 · City of Columbus - (OH)Power plant (Petroleum)25.9 km2 MW[7]
Ps St-8 Engine No 1 · City of Columbus - (OH)Power plant (Petroleum)27 km2 MW[7]
O'Shaughnessy Hydro · City of Columbus - (OH)Power plant (Hydroelectric)33.3 km5 MW[7]
Suburban Landfill Gas Recovery · WM Renewable Energy LLCPower plant (Biomass)46.4 km6 MW[7]
Igs Cmh4, LLC · Greenbacker Renewable Energy CorporationPower plant (Solar)49.4 km4 MW[7]
Macy Substation · American Electric PowerSubstation0.17 km138 kV[1]
QTS NAL-2 Substation · Quality Technology ServicesSubstation0.17 km138 kV[1]
Brie Substation · American Electric PowerSubstation0.84 km138 kV[1]
Unnamed substationSubstation0.91 km138 kV[1]
Unnamed substationSubstation0.93 km138 kV[1]
Unnamed substationSubstation0.96 km138 kV[1]
Largest queued generation in this countyFuelQueue statusMWSource
Centerburg 138 kVPJM AI2-088SolarIn study · proposed 2025-12413 MW[5]
Centerburg 138 kVPJM AG1-034SolarIn study · proposed 2023-10363 MW[5]
Centerburg 138 kVPJM AH1-036StorageIn study · proposed 2024-07278 MW[5]
Centerburg 138 kVPJM AG1-024SolarIn study · proposed 2023-10235 MW[5]
Flint GridPJM AF1-062StorageIA signed · proposed 2026-11200 MW[5]
Jug Street 138 kVPJM AI2-226StorageIn study · proposed 2022-08200 MW[5]

Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.

Construction & permitting

  1. Announced
    —
  2. Land acquired
    Jun 6, 2024[2]
  3. Permitting
    —
  4. Construction start
    —
  5. First operational
    Sep 1, 2024[1]
  6. Expected completion
    —

Real estate

Official assessments
Assessor's value for a tax year
  • $27.8M[2]
    Market value · tax year current (2026) · parcel 094-107502-00.003
  • $3.8M[2]
    Market value — land · tax year current (2026) · parcel 094-107502-00.003
  • $24M[2]
    Market value — improvements · tax year current (2026) · parcel 094-107502-00.003
Recorded transactions
Sale prices from recorded deeds

None sourced yet

Model estimates
Our model — not an appraisal

None sourced yet

ParcelRecord ownerAcresZoning / useBuilding sq ftSource
094-107502-00.003
Licking County, OH
QTS NEW ALBANY II DC1 LLC
6601 COLLEGE BLVD , OVERLAND PARK, KS
18.85305: Research/Chemical Labs—[2]
Site area
18.9 acres[2]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Oct 12, 2026.Confirmed

Sum of county land area across parcels.

Land use
305: Research/Chemical Labs[2]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Oct 12, 2026.Confirmed
Annual property tax
Not yet sourced
Nearby comparable transactions

Size

Floor area
327,000 sq ft[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Unverifiedestimated

Estimated as footprint × 2 mapped floors; gross, not leasable, area.

Building footprint
163,500 sq ft[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Likelyderived

Computed from the mapped OSM building outline.

Floors
2[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Likely
Parcel / land records
094-107502-00.003 (Licking County)[2]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Oct 12, 2026.Confirmed

What changed (last 3 years)

Follow this facility (RSS)

No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.

Timeline

First operational: Sep 1, 2024[1]
  1. Jun 6, 2024[2]

    Deed/transfer recorded for parcel 094-107502-00.003 (no sale price disclosed).

Other buildings on this campus

3

All claims (provenance audit)

25
FieldValueSourceConfidenceAs ofStatus
NameQTS NAL 2 DC1way/1425043212 name=QTS NAL 2 DC1[1] Likely2026-10-12Shown
StatusOperating[1] derivedUnverified2026-10-12Shown
Facility typeColocation[1] derivedUnverified2026-10-12Shown
Address785 Beech Road Southwest, New Albany, OH 43054[1] Likely2026-10-12Shown
Property owner of recordQts New Albany II Dc1 LLCParcel 094-107502-00.003: QTS NEW ALBANY II DC1 LLC[2] Confirmed2026-10-12Shown
OperatorQTS Data Centersoperator=Quality Technology Services[1] Likely2026-10-12Shown
UtilityAmerican Electric Powerterritory 14006: OHIO POWER CO (INVESTOR OWNED, AMERICAN ELECTRIC POWER CO)[3] derivedUnverified2022Shown
ISO / RTOPJMPJM INTERCONNECTION, LLC[4] derivedLikely—Shown
Balancing authorityPJM[3] derivedLikely—Shown
Nearest mapped substationMacy Substation (138 kV)way/1428407720[1] derivedLikely2026-09-28Shown
Distance to substation0.2 km[1] derivedLikely2026-09-28Shown
Highest-voltage line nearby138 kV[1] derivedLikely2026-09-28Shown
Generation queued in county2.52 GW[5] derivedConfirmed2026-10-12Shown
State avg. industrial price10.95¢/kWh[6] Confirmed2026-07Shown
State avg. commercial price14.06¢/kWh[6] Confirmed2026-07Shown
Generation within 50 km25 MW[7] derivedConfirmed202502Shown
Floor area327,000 sq ft[1] estimatedUnverified2026-10-12Shown
Building footprint163,500 sq ft[1] derivedLikely2026-10-12Shown
Floors2building:levels=2[1] Likely2026-10-12Shown
Site area18.9 acres[2] Confirmed2026-10-12Shown
Parcel / land records094-107502-00.003 (Licking County)[2] Confirmed2026-10-12Shown
Assessed value (official)$27.8M[2] Confirmed2026Shown
Land use305: Research/Chemical Labs[2] Confirmed2026-10-12Shown
Land acquiredJun 6, 2024[2] derivedConfirmed2026-10-12Shown
First operationalSep 1, 2024start_date=2024-09-01[1] Likely2026-10-12Shown