DC
/

Meta Huntsville Data center

OperatingEst.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.HyperscaleBuildingMadison County, Alabama

Meta Huntsville Data center is an operating hyperscale in Alabama. Operated or owned by Meta. Power capacity has not been disclosed or collected yet. Verification: unverified. 5 cited sources.

Part of Meta — Madison County, AL campus

20% profile completeness
14 claims from 5 sources
Last verified against sources: Oct 12, 2026
Newest dated evidence: Oct 12, 2026
Follow

Get changes to Meta Huntsville Data center

How often

Double opt-in; one-click unsubscribe in every email. We store only your email and what you follow. More

Or subscribe in a feed reader: RSS / Atom

Cite this
Text
Datacenter Source. “Meta Huntsville Data center.” /facilities/meta-huntsville-data-center-madison-county-al-3. Data as of 2026-10-12. Accessed 2026-10-12.
BibTeX
@misc{datacentersource_meta_huntsville_data_center_madison_coun_2026,
  title = {{Meta Huntsville Data center}},
  author = {{Datacenter Source}},
  year = {2026},
  howpublished = {\url{/facilities/meta-huntsville-data-center-madison-county-al-3}},
  note = {Data as of 2026-10-12; accessed 2026-10-12. Compiled from cited sources, including OpenStreetMap contributors (ODbL) and Epoch AI (CC BY 4.0)},
}

Please also cite the original source of any specific figure (linked beside it).

Current facility power
Not yet sourced
Planned capacity
Not yet sourced
Building footprint
859,200 sq ft[1]
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Likelyderived
Buildings (planned)
Not yet sourced
Capital cost / investment
Not yet sourced
First operational
Not yet sourced

POWER & GRID

Time-to-power · verification · interconnection
Time to power
Operating (community-mapped, unverified)
Low confidence
Project verification
Unverified
Evidence is limited to community map.
Current stage
Operational
Furthest stage with documented evidence
Utility · ISO
City of Huntsville - (Al) · None (non-RTO region)
Substation: Flash Substation (161 kV) (nearest, unverified)

Power reality

Announced
No record
Interconnection request
No record
Contracted / approved
No record
Under construction
No record
Operational
No record
AI evidence brief
Summarizes only the evidence on this page. Answers citing anything else are rejected automatically.

Project verification

Development
  1. Announcedimplied by a later stage
  2. Land acquiredimplied by a later stage
  3. Planning / zoningimplied by a later stage
  4. Permittingimplied by a later stage
Grid interconnection
  1. Interconnection application
  2. Feasibility study
  3. System impact study
  4. Facilities study
  5. Interconnection agreement / service contract
Build & energization
  1. Financing
  2. Under constructionimplied by a later stage
  3. Energizationimplied by a later stage
  4. OperationalOct 12, 2026
    Community map
    • Oct 12, 2026 · Reported status: operating[1]

● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Community map.

Grid path

  1. facility
    Meta Huntsville Data center
  2. substation
    Flash Substation (161 kV)[1]
    Proximity onlyUnverified
    Nearest mapped substation, 0.33 km away. Proximity does not establish that it serves the site.
  3. transmission
    161 kV line[1]
    Proximity onlyUnverified
    Highest-voltage line mapped within 2 km (0.29 km away). Not confirmed as the supply path.
  4. utility
    City of Huntsville - (Al)[2]
    Service territoryLikely
    Retail service territory containing the site
  5. ISO / RTO
    None (non-RTO region)[3]
    Service territoryLikely
    Balancing authority: TVA
Substation capacity:
not published
Required upgrades:
not yet sourced
Congestion:
not yet sourced (no nodal price data)

Dashed boxes are based on proximity only and do not establish which asset serves the site.

Interconnection records

No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.

On-site & dedicated generation

  • Tai Huntsville Solar Hybrid (Solar, 32 MW) is 1.2 km away[5]
    EIA plant within 1.5 km; proximity does not establish that it supplies the facility
    SolarCo-located32 MWConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Unverified

LOCAL IMPACT

Water · generation · incentives · regulation · rates

Water & cooling

Not yet collected: we haven't found a source for water use or the cooling type at this site. Know one? Add a source

On-site generation & air permits1

  • Tai Huntsville Solar Hybrid (Solar, 32 MW) is 1.2 km away32 MW[5]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Solar · Co-located

Incentives

Not yet collected: we haven't found a source for tax abatements, PILOTs or other incentives for this project. Know one? Add a source

Regulatory events

Not yet collected: we haven't found a source for hearings, rezonings, permits or commission proceedings. Know one? Add a source

Utility & rates

Not yet collected: we haven't found a source for a large-load tariff or commission docket for City of Huntsville - (Al). Know one? Add a source

Location & imagery

Mapped outline
Coordinates
34.84044, -86.62885
County
Madison County
Photographs

No openly licensed ground-level photos matched to this site yet.

Ownership, operation & customers

  1. 1. Property owner of record
    Not identified
  2. 2. Owner / developer
    Not identified
  3. 3. Operator
    Meta[1]Likely
  4. 4. Tenant / cloud
    Not identified
  5. 5. End customer / workload
    Not identified

Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.

All parties with evidence
Operator
Meta[1]Likely
Utility

Location falls inside this utility's retail service territory.

No tenants or end users identified in our sources yet.

Power (all fields)

Current facility power
Not yet sourced
Planned capacity
Not yet sourced

Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.

Grid & electricity

ISO / RTO
None (non-RTO region)[3]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived

Outside all ISO/RTO footprints; balancing authority shown separately.

Balancing authority
TVA[2]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived

Control area of the containing utility territory.

Nearest mapped substation
Flash Substation (161 kV)[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived

Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.

Distance to substation
0.3 km[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
Highest-voltage line nearby
161 kV[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived

Highest-voltage transmission line mapped within 2 km.

State avg. industrial price
8.42¢/kWh[4]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed

Alabama statewide average, July 2026.

State avg. commercial price
14.83¢/kWh[4]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed

Alabama statewide average, July 2026.

Generation within 50 km
5.45 GW[5]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jan 1, 202502.Confirmedderived

8 EIA-reported plants within 50 km.

Interconnection status
Not yet sourced
Contracted / committed power
Not yet sourced
Nearby infrastructureTypeDistanceVoltage / capacitySource
161 kV lineTransmission line0.29 km161 kV[1]
Tai Huntsville Solar Hybrid · TAI Huntsville Solar, LLCPower plant (Solar)1.2 km32 MW[5]
Cumblerland Land Holdings, LLC · Cumberland Land Holdings, LLCPower plant (Solar)25 km15 MW[5]
Redstone Arsenal Hybrid · MN8 Energy LLCPower plant (Solar)25.6 km8 MW[5]
Elora Solar · Elora SolarPower plant (Solar)35.9 km150 MW[5]
Decatur Energy Center · Decatur Energy Center LLCPower plant (Natural Gas)42.9 km800 MW[5]
Morgan Energy Center · Morgan Energy Center LLCPower plant (Natural Gas)45.6 km782 MW[5]
Browns Ferry · Tennessee Valley AuthorityPower plant (Nuclear)47.3 km3.66 GW[5]
Decatur-Morgan CO Lfg Recovery Project · Energy Developments, Inc d/b/a EDLPower plant (Biomass)49.4 km2 MW[5]
Flash Substation · MetaSubstation0.33 km161 kV[1]
Liberty Hill SubstationSubstation1.25 km161 kV[1]
Gladstone Switching Station · Tennessee Valley AuthoritySubstation1.26 km161 kV[1]
Unnamed substationSubstation1.89 km—[1]

Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.

Construction & permitting

  1. Announced
    —
  2. Land acquired
    —
  3. Permitting
    —
  4. Construction start
    —
  5. First operational
    —
  6. Expected completion
    —

Real estate

Official assessments
Assessor's value for a tax year

None sourced yet

Recorded transactions
Sale prices from recorded deeds

None sourced yet

Model estimates
Our model — not an appraisal

None sourced yet

Annual property tax
Not yet sourced

No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.

Size

Building footprint
859,200 sq ft[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Likelyderived

Computed from the mapped OSM building outline.

Floor area
Not yet sourced

What changed (last 3 years)

Follow this facility (RSS)

No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.

Timeline

No dated events sourced yet.

Other buildings on this campus

1

All claims (provenance audit)

14
FieldValueSourceConfidenceAs ofStatus
NameMeta Huntsville Data centerway/1160814416 name=Meta Huntsville Data center[1] Likely2026-10-12Shown
StatusOperating[1] derivedUnverified2026-10-12Shown
Facility typeHyperscale[1] derivedUnverified2026-10-12Shown
OperatorMetaoperator=Meta[1] Likely2026-10-12Shown
UtilityCity of Huntsville - (Al)territory 9094: CITY OF HUNTSVILLE - (AL) (MUNICIPAL, CITY OF HUNTSVILLE - (AL))[2] derivedLikely2022Shown
ISO / RTONone (non-RTO region)[3] derivedLikely—Shown
Balancing authorityTVA[2] derivedLikely—Shown
Nearest mapped substationFlash Substation (161 kV)way/1160814404[1] derivedLikely2026-09-28Shown
Distance to substation0.3 km[1] derivedLikely2026-09-28Shown
Highest-voltage line nearby161 kV[1] derivedLikely2026-09-28Shown
State avg. industrial price8.42¢/kWh[4] Confirmed2026-07Shown
State avg. commercial price14.83¢/kWh[4] Confirmed2026-07Shown
Generation within 50 km5.45 GW[5] derivedConfirmed202502Shown
Building footprint859,200 sq ft[1] derivedLikely2026-10-12Shown