DataOne Vineland
DataOne Vineland is an operating ai campus in New Jersey. Operated or owned by Nebius. Power capacity has not been disclosed or collected yet. Verification: unverified. 6 cited sources.
Part of Microsoft-Nebius New Jersey
Follow
Get changes to DataOne Vineland
Or subscribe in a feed reader: RSS / Atom
Cite this
Datacenter Source. “DataOne Vineland.” /facilities/dataone-vineland-cumberland-county-nj. Data as of 2026-10-12. Accessed 2026-10-12.
@misc{datacentersource_dataone_vineland_cumberland_county_nj_2026,
title = {{DataOne Vineland}},
author = {{Datacenter Source}},
year = {2026},
howpublished = {\url{/facilities/dataone-vineland-cumberland-county-nj}},
note = {Data as of 2026-10-12; accessed 2026-10-12. Compiled from cited sources, including OpenStreetMap contributors (ODbL) and Epoch AI (CC BY 4.0)},
}Please also cite the original source of any specific figure (linked beside it).
POWER & GRID
Time-to-power · verification · interconnectionPower reality
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- Under constructionimplied by a later stage
- Energizationimplied by a later stage
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Community map.
Grid path
- →facilityDataOne Vineland
- →substationLincoln 3/Clayville Substation (138 kV)[1]Proximity onlyUnverifiedNearest mapped substation, 0.21 km away. Proximity does not establish that it serves the site.
- →transmissionNot identifiedUnknownUnverifiedNo transmission line mapped within 2 km.
- →utilityCity of Vineland - (Nj)[2]Service territoryLikelyRetail service territory containing the site
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
| Queue | Relationship | Stage | MW req. | MW appr. | Queued | Expected in service | POI / TO | Source · as of |
|---|---|---|---|---|---|---|---|---|
PJM V2-041 Vineland-Mays Landing · Solar | Possibly related generation Speculative Generation request name/developer shares “vineland” with this facility, in the same county. Not confirmed as serving it. | In service In Service; feasibility: Document Posted; system impact: Document Posted; facilities: Not Required; ISA/GIA: Wholesale Market Participation Agreement | 4 ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Oct 12, 2026. | 1.52 | Jul 29, 2009 | In service Sep 30, 2011 | Clayville 12kV TO: AEC | [4] Oct 12, 2026 |
On-site & dedicated generation
- Clayville (Natural Gas, 55 MW) is 0.4 km away[6]EIA plant within 1.5 km; proximity does not establish that it supplies the facilityNatural gasCo-located55 MWConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Unverified
- PJM V2-041 Vineland-Mays Landing (Solar, 4 MW requested)[4]Generation request name/developer shares “vineland” with this facility, in the same county. Not confirmed as serving it.SolarArrangement unknown4 MWConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Speculative
LOCAL IMPACT
Water · generation · incentives · regulation · ratesWater & cooling
Not yet collected: we haven't found a source for water use or the cooling type at this site. Know one? Add a source
On-site generation & air permits1
- Clayville (Natural Gas, 55 MW) is 0.4 km away55 MW[6]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Natural gas · Co-located
Incentives
Not yet collected: we haven't found a source for tax abatements, PILOTs or other incentives for this project. Know one? Add a source
Regulatory events
Not yet collected: we haven't found a source for hearings, rezonings, permits or commission proceedings. Know one? Add a source
Utility & rates
Not yet collected: we haven't found a source for a large-load tariff or commission docket for City of Vineland - (Nj). Know one? Add a source
Location & imagery
Mapped outline- Coordinates
- 39.42756, -75.01689
- County
- Cumberland County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developerNot identified
- 3. Operator
- 4. Tenant / cloudNot identified
- 5. End customer / workloadNot identified
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Utility
Location falls inside this utility's retail service territory.
No tenants or end users identified in our sources yet.
Power (all fields)
- Current facility power
- Not yet sourced
- Planned capacity
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
- PJM[3]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived
Location falls inside this ISO/RTO footprint.
- Balancing authority
- PJM[2]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived
Control area of the containing utility territory.
- Nearest mapped substation
- Lincoln 3/Clayville Substation (138 kV)[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- 0.2 km[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
- State avg. industrial price
- 15.63¢/kWh[5]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed
New Jersey statewide average, July 2026.
- State avg. commercial price
- 19.17¢/kWh[5]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed
New Jersey statewide average, July 2026.
- Generation within 50 km
- 5.11 GW[6]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jan 1, 202502.Confirmedderived
61 EIA-reported plants within 50 km.
- Generation queued in county
- 424 MW[4]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Confirmedderived
12 active generation interconnection requests in Cumberland County: Solar 324 MW, Storage 100 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| Clayville · City of Vineland - (NJ) | Power plant (Natural Gas) | 0.4 km | 55 MW | [6] |
| Sherman Avenue · Calpine New Jersey Generation LLC | Power plant (Natural Gas) | 4.4 km | 87 MW | [6] |
| Howard Down · City of Vineland - (NJ) | Power plant (Natural Gas) | 7 km | 55 MW | [6] |
| Cumberland (Nj) · Calpine New Jersey Generation LLC | Power plant (Natural Gas) | 7.3 km | 187 MW | [6] |
| Pseg Salem Generating Station · PSEG Nuclear LLC | Power plant (Nuclear) | 44.7 km | 2.32 GW | [6] |
| Pseg Hope Creek Generating Station · PSEG Nuclear LLC | Power plant (Nuclear) | 44.9 km | 1.17 GW | [6] |
| West Deptford Energy Station · West Deptford Energy LLC | Power plant (Natural Gas) | 49.2 km | 735 MW | [6] |
| Garrison Energy Center LLC · Garrison Energy Center LLC | Power plant (Natural Gas) | 49.4 km | 309 MW | [6] |
| Lincoln 3/Clayville Substation · Vineland Municipal Electric Utility | Substation | 0.21 km | 138 kV | [1] |
| Lincoln/Clayville Substation · Vineland Municipal Electric Utility | Substation | 0.33 km | 69 kV | [1] |
| Wheaton Substation | Substation | 2.03 km | 69 kV | [1] |
| Unnamed substation | Substation | 2.19 km | 69 kV | [1] |
| Butler Substation · Vineland Municipal Electric Utility | Substation | 2.26 km | 69 kV | [1] |
| Unnamed substation | Substation | 2.56 km | 69 kV | [1] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| Buckshutem Solar IPJM AE1-179 | Solar | IA signed · proposed 2027-01 | 60 MW | [4] |
| South Millville - Newport 69 kVPJM AI2-385 | Solar | In study · proposed 2025-03 | 60 MW | [4] |
| Sherman Ave - West Vineland 69 kVPJM AF1-238 - moved to TC1 | Storage | In study · proposed 2023-05 | 50 MW | [4] |
| Nabb Solar ProjectPJM AE1-240 | Solar | Suspended · proposed 2024-10 | 50 MW | [4] |
| Carlls Corner - Sherman Ave 69 kVPJM AI2-387 | Solar | In study · proposed 2024-12 | 50 MW | [4] |
| Roadstown 69 kVPJM AG2-241 | Solar | In study · proposed 2023-09 | 47 MW | [4] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction start—
- First operational—
- Expected completion—
Real estate
None sourced yet
None sourced yet
None sourced yet
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Building footprint
- 115,800 sq ft[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Likelyderived
Computed from the mapped OSM building outline.
- Floor area
- Not yet sourced
What changed (last 3 years)
Follow this facility (RSS)No tracked changes yet. Values are recorded on every data refresh, so changes will appear here over time.
Timeline
No dated events sourced yet.
Other buildings on this campus
1- Microsoft-Nebius New JerseyOperating
All claims (provenance audit)
14| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | DataOne Vinelandway/1553894888 name=DataOne Vineland | [1] | Likely | 2026-10-12 | Shown |
| Status | Operating | [1] derived | Unverified | 2026-10-12 | Shown |
| Facility type | AI campus | [1] derived | Unverified | 2026-10-12 | Shown |
| Operator | Nebiusoperator=Nebius | [1] | Likely | 2026-10-12 | Shown |
| Utility | City of Vineland - (Nj)territory 19856: CITY OF VINELAND - (NJ) (MUNICIPAL, CITY OF VINELAND - (NJ)) | [2] derived | Likely | 2022 | Shown |
| ISO / RTO | PJMPJM INTERCONNECTION, LLC | [3] derived | Likely | — | Shown |
| Balancing authority | PJM | [2] derived | Likely | — | Shown |
| Nearest mapped substation | Lincoln 3/Clayville Substation (138 kV)way/1099917639 | [1] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.2 km | [1] derived | Likely | 2026-09-28 | Shown |
| Generation queued in county | 424 MW | [4] derived | Confirmed | 2026-10-12 | Shown |
| State avg. industrial price | 15.63¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 19.17¢/kWh | [5] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 5.11 GW | [6] derived | Confirmed | 202502 | Shown |
| Building footprint | 115,800 sq ft | [1] derived | Likely | 2026-10-12 | Shown |