Anthropic-Amazon New Carlisle
Also known as Project Rainier
Anthropic-Amazon New Carlisle is an operating ai campus in New Carlisle, Indiana. Operated or owned by Amazon Web Services; used by Anthropic. Current power: 1.09 GW (estimated). Planned capacity: 2.2 GW (announced). Verification: verified operating. 13 cited sources.
Follow
Get changes to Anthropic-Amazon New Carlisle
Or subscribe in a feed reader: RSS / Atom
Cite this
Datacenter Source. “Anthropic-Amazon New Carlisle.” /facilities/anthropic-amazon-new-carlisle-new-carlisle-in. Data as of 2026-10-12. Accessed 2026-10-12.
@misc{datacentersource_anthropic_amazon_new_carlisle_new_carlis_2026,
title = {{Anthropic-Amazon New Carlisle}},
author = {{Datacenter Source}},
year = {2026},
howpublished = {\url{/facilities/anthropic-amazon-new-carlisle-new-carlisle-in}},
note = {Data as of 2026-10-12; accessed 2026-10-12. Compiled from cited sources, including OpenStreetMap contributors (ODbL) and Epoch AI (CC BY 4.0)},
}Please also cite the original source of any specific figure (linked beside it).
POWER & GRID
Time-to-power · verification · interconnectionPower reality
Project verification
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- Under constructionFeb 9, 2024
- EnergizationJun 23, 2025
Satellite imagery
- Jun 23, 2025 · Buildings 1-7 are operational. Based on all of the roofs being completed for over 5 months.[1]
- Dec 23, 2025 · Buildings 8-11 are operational, given it's been over 7 months since their roofs were complete, and the backup generators and roof chimneys look complete. The roof is almost complet[1]
- Mar 23, 2026 · Buildings 12-16 are operational. Based on how long previous buildings took, when they were in a similar state to Buildings 12-16 in December.[1]
- OperationalJun 23, 2025
Satellite imagery · News report
- Jun 23, 2025 · Buildings 1-7 are operational. Based on all of the roofs being completed for over 5 months.[1]
- Oct 29, 2025 · Reported status: operating[2]
- Dec 23, 2025 · Buildings 8-11 are operational, given it's been over 7 months since their roofs were complete, and the backup generators and roof chimneys look complete. The roof is almost complet[1]
- Mar 23, 2026 · Buildings 12-16 are operational. Based on how long previous buildings took, when they were in a similar state to Buildings 12-16 in December.[1]
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: News report, Model estimate, Satellite imagery.
Grid path
- →facilityAnthropic-Amazon New Carlisle
- →substationOn-site substation[1]Satellite imageryLikely4 substation outlines traced inside the campus on satellite imagery
- →transmission345 kV line[6]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (0.89 km away). Not confirmed as the supply path.
- →
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
LOCAL IMPACT
Water · generation · incentives · regulation · ratesWater & cooling
Not yet collected: we haven't found a source for water use or the cooling type at this site. Know one? Add a source
On-site generation & air permits
Not yet collected: we haven't found a source for on-site generation or an air permit for this site. Know one? Add a source
Incentives
Not yet collected: we haven't found a source for tax abatements, PILOTs or other incentives for this project. Know one? Add a source
Regulatory events
Not yet collected: we haven't found a source for hearings, rezonings, permits or commission proceedings. Know one? Add a source
Utility & rates1
- Large load tariff settlement[15]AnnouncedStated by the company or reported in the press; not yet backed by a filing or grid record. As of Feb 19, 2025.Feb 19, 2025Indiana Michigan Power (AEP) · Indiana Utility Regulatory Commission · Order approving settlement (with one modification)
“The IURC order approved the terms of the joint settlement, with one modification, and requires new large load customers, including data centers, to make long-term financial commitments proportional to their size.”
Location & imagery
Mapped outline- Coordinates
- 41.67911, -86.47206
- Address
- 55001 Larrison Blvd, New Carlisle, IN 46552[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jun 3, 2026.Likely
- County
- St. Joseph County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. Operator
- 4. Tenant / cloudNot identified
- 5. End customer / workload
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Owner
- Operator
“Amazon has opened a data center on 1,200 acres of land in Indiana”
- Utility
“working with American Electric Power through its Indiana Michigan Power subsidiary”
Power (all fields)
- Current facility power
- 1.09 GW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jun 3, 2026.Likelyestimated
Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.
- Current IT capacity
- 910 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jun 3, 2026.Likelyestimated
Estimated IT load currently online, based on buildings observed operational.
- Planned capacity
- Estimated annual consumption
- 6,696 GWh/yr[3]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Speculativeestimated
1092 MW × 8,760 h × 70% utilization.
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
- PJM[4]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived
Location falls inside this ISO/RTO footprint.
- Balancing authority
- PJM[5]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived
Control area of the containing utility territory.
- Nearest mapped substation
- Unnamed substation (345 kV)[6]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- 1.2 km[6]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
- Highest-voltage line nearby
- 345 kV[6]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
- 9.16¢/kWh[8]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed
Indiana statewide average, July 2026.
- State avg. commercial price
- 13.30¢/kWh[8]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed
Indiana statewide average, July 2026.
- Generation within 50 km
- 4.7 GW[9]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jan 1, 202502.Confirmedderived
22 EIA-reported plants within 50 km.
- Generation queued in county
- 2.71 GW[7]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Confirmedderived
14 active generation interconnection requests in St. Joseph County: Solar 790 MW, Gas 786 MW, Solar + storage 588 MW, Storage 542 MW. Queued projects often don't get built.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 345 kV line | Transmission line | 0.89 km | 345 kV | [6] |
| St Joseph Energy Center · St Joseph Energy Center LLC | Power plant (Natural Gas) | 2.3 km | 715 MW | [9] |
| Honeysuckle Solar Farm · Lightsource Renewable Energy Asset Management, LLC | Power plant (Solar) | 4.5 km | 150 MW | [9] |
| University of Notre Dame · University of Notre Dame | Power plant (Natural Gas) | 19.8 km | 39 MW | [9] |
| Indeck Niles Energy Center · Indeck Niles, LLC | Power plant (Natural Gas) | 29.1 km | 1.08 GW | [9] |
| St. Joseph Solar · Indiana Michigan Power Co | Power plant (Solar) | 30.7 km | 20 MW | [9] |
| Donald C Cook · Indiana Michigan Power Co | Power plant (Nuclear) | 33.9 km | 2.18 GW | [9] |
| Bremen · Indiana Municipal Power Agency | Power plant (Solar) | 35.2 km | 7 MW | [9] |
| Michigan City · Northern Indiana Pub Serv Co | Power plant (Coal) | 36.5 km | 455 MW | [9] |
| Unnamed substation | Substation | 1.22 km | 345 kV | [6] |
| Unnamed substation | Substation | 1.27 km | 345 kV | [6] |
| Unnamed substation | Substation | 1.41 km | 345 kV | [6] |
| Unnamed substation | Substation | 1.99 km | 34.5 kV | [6] |
| Edison Substation · AEP Ohio | Substation | 2.35 km | 138 kV | [6] |
| Elderberry Substation · AEP Ohio | Substation | 2.4 km | 345 kV | [6] |
| Largest queued generation in this county | Fuel | Queue status | MW | Source |
|---|---|---|---|---|
| Elderberry 345 kVPJM AG2-562 | Gas | In study · proposed 2022-10 | 786 MW | [7] |
| Olive - Dumont 345 kVPJM AH2-112 | Solar + storage | In study · proposed 2026-02 | 250 MW | [7] |
| Northern St. Joseph 138 kVPJM AH2-347 | Storage | In study · proposed 2025-03 | 200 MW | [7] |
| New Carlisle 138 kVPJM AH1-479 | Storage | In study · proposed 2023-09 | 192 MW | [7] |
| Honeysuckle Solar ProjectPJM AF1-158 | Solar + storage | Under construction · proposed 2025-01 | 150 MW | [7] |
| Dumont 345 kVPJM AG2-230 | Solar | In study · proposed 2024-12 | 150 MW | [7] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction startSep 2024[2]
- First operationalOct 2025[2]
- Expected completionMar 17, 2028[1]Projected
- Planned capacity
- Buildings (planned)
| Phase | Status | Added MW | Completed / expected | Source |
|---|---|---|---|---|
| Buildings 1–7 | operational | 478 MW | Jun 23, 2025 | [1] |
| Buildings 8–11 | operational | 273 MW | Dec 23, 2025 | [1] |
| Buildings 12–16 | operational | 341 MW | Mar 23, 2026 | [1] |
| Buildings 17–18 | under construction | 152 MW | Oct 19, 2026 (projected) | [1] |
| Buildings 19–32 | under construction | 1.07 GW | Mar 17, 2028 (projected) | [1] |
Real estate
None sourced yet
None sourced yet
None sourced yet
- Site area
- 1,200 acres[2]AnnouncedStated by the company or reported in the press; not yet backed by a filing or grid record. As of Oct 29, 2025.Confirmed
“a data center on 1,200 acres of land in Indiana”
- Capital cost / investment
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Building footprint
- 1.47M sq ft[6]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Likelyderived
Sum of 7 building outlines mapped in OpenStreetMap within this campus.
- Floor area
- Not yet sourced
Compute
- Project
- Project Rainier[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jun 3, 2026.Confirmed
- Chip types
- Compute (H100-equivalents)
- 685,900[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jun 3, 2026.Likelyestimated
What changed (last 3 years)
Follow this facility (RSS)- Current IT capacity398 MWJun 23, 2025[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→626 MWDec 23, 2025[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→910 MWMar 23, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
- Current facility power478 MWJun 23, 2025[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→751 MWDec 23, 2025[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→1.09 GWMar 23, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
- Planned capacity2.2 GWOct 2025[2]AnnouncedStated by the company or reported in the press; not yet backed by a filing or grid record.→2.2 GWOct 2025[10]AnnouncedStated by the company or reported in the press; not yet backed by a filing or grid record.→2.31 GWJun 3, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
- Capital cost / investment$11BOct 2025[2]AnnouncedStated by the company or reported in the press; not yet backed by a filing or grid record.→$11BOct 2025[10]AnnouncedStated by the company or reported in the press; not yet backed by a filing or grid record.→$34.5BJun 3, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
- Buildings (planned)30Oct 2025[2]AnnouncedStated by the company or reported in the press; not yet backed by a filing or grid record.→30Oct 2025[10]AnnouncedStated by the company or reported in the press; not yet backed by a filing or grid record.→18Jun 3, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
- Buildings operational0Feb 9, 2024[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→7Jun 23, 2025[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→7Oct 2025[2]AnnouncedStated by the company or reported in the press; not yet backed by a filing or grid record.→7Oct 2025[10]AnnouncedStated by the company or reported in the press; not yet backed by a filing or grid record.→11Dec 23, 2025[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→16Mar 23, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
- StatusUnder constructionFeb 9, 2024[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→Operating + expandingJun 23, 2025[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→OperatingOct 29, 2025[10]AnnouncedStated by the company or reported in the press; not yet backed by a filing or grid record.→OperatingOct 29, 2025[2]AnnouncedStated by the company or reported in the press; not yet backed by a filing or grid record.
Timeline
- Feb 9, 2024[1]
Land clearing begins in the northern section
- Jun 10, 2024[1]
Land clearing begins in the southern section
- May 10, 2025[1]
Roof complete on building 11
Buildings 1-7 are operational. Based on all of the roofs being completed for over 5 months.
Roof complete on building 16. Generators are being installed for buildings 8-15. In the north, Building 17 and 18 are under construction. To the south of buildings 8-16, a concrete pad is visible, and an expanded car park next to it.
Confirmation that nearly 500,000 chips are operational, which fits buildings 1-7. In an interview, AWS CEO says "they're already running...about 500,000 [Trainium2] chips in Indiana today".
Buildings 8-11 are operational, given it's been over 7 months since their roofs were complete, and the backup generators and roof chimneys look complete. The roof is almost complete for Building 17 and 18.
Buildings 12-16 still have a few generators that look incomplete, so they are unlikely to be operational just yet. Buildings 17-18 still have ongoing roof work, no generators. Just south of Buildings 9-16, the outlines of a site for Buildings 19-32 are taking shape.
Buildings 12-16 are operational. Based on how long previous buildings took, when they were in a similar state to Buildings 12-16 in December.
Buildings 17-18 fully roofed but still having surrounding generators/cooling under construction. Cleared land for buildings 19-32 is still bare, with no building foundations visible yet. Based on satellite imagery.
Buildings 17-18 are operational. This is an estimate based on a rule of thumb of "operational 5 months after roof is complete", assuming the roofs took one more month after 2025-12-23. Also added four more months to account for commissioning and adjacent cooling units not being complete yet.
Buildings 19-32 are operational. This is an estimate based on how long Buildings 1-16 took to become operational. In May 2026, the foundation of several buildings and a substation was visible at the site of Buildings 19-32. Buildings 1-16 took 1 year and 10 months to go from a similar state to operational. So we add 1 year and 10 months to May 2026 to get this date estimate. The power capacity is based on an air quality permit filed in May 2026, and the compute capacity is based on Trainium3 chips.
Buildings on this campus
1- Amazon AWS Data CenterOperating
All claims (provenance audit)
79| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | Anthropic-Amazon New Carlisle | [1] | Likely | 2026-06-03 | Shown |
| Also known as | Project Rainier | [2] | Confirmed | 2025-10-29 | Shown |
| Status | Under construction | [1] derived | Likely | 2024-02-09 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2024-06-10 | Superseded / alternative |
| Status | Under construction | [1] derived | Likely | 2025-05-10 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-06-23 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-09-26 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-10-17 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-12-23 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-02-09 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-03-23 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2026-06-03 | Superseded / alternative |
| Status | Operating | [2] AI-extracted | Likely | 2025-10-29 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-06-03 | Shown |
| Project | Project Rainier | [1] | Confirmed | 2026-06-03 | Shown |
| Address | 55001 Larrison Blvd, New Carlisle, IN 46552 | [1] | Likely | 2026-06-03 | Shown |
| Owner | Amazon Web ServicesOwner: Amazon | [1] | Confirmed | 2026-06-03 | Shown |
| Operator | Amazon Web Services | [2] AI-extracted | Likely | 2025-10-29 | Shown |
| End users | AnthropicUsers: Anthropic | [1] | Confirmed | 2026-06-03 | Shown |
| End users | Anthropic | [2] | Confirmed | 2025-10-29 | Shown |
| End users | Anthropic | [2] AI-extracted | Likely | 2025-10-29 | Shown |
| Utility | Indiana Michigan Power (AEP) | [2] | Likely | 2025-10-29 | Shown |
| Utility | Indiana Michigan Power (AEP) | [2] AI-extracted | Likely | 2025-10-29 | Shown |
| Current facility power | 1.09 GW | [1] estimated | Likely | 2026-06-03 | Shown |
| Current facility power | 478 MW | [1] estimated | Likely | 2025-06-23 | Superseded / alternative |
| Current facility power | 478 MW | [1] estimated | Likely | 2025-09-26 | Superseded / alternative |
| Current facility power | 478 MW | [1] estimated | Likely | 2025-10-17 | Superseded / alternative |
| Current facility power | 751 MW | [1] estimated | Likely | 2025-12-23 | Superseded / alternative |
| Current facility power | 751 MW | [1] estimated | Likely | 2026-02-09 | Superseded / alternative |
| Current facility power | 1.09 GW | [1] estimated | Likely | 2026-03-23 | Superseded / alternative |
| Current IT capacity | 910 MW | [1] estimated | Likely | 2026-06-03 | Shown |
| Current IT capacity | 398 MW | [1] estimated | Likely | 2025-06-23 | Superseded / alternative |
| Current IT capacity | 398 MW | [1] estimated | Likely | 2025-09-26 | Superseded / alternative |
| Current IT capacity | 398 MW | [1] estimated | Likely | 2025-10-17 | Superseded / alternative |
| Current IT capacity | 626 MW | [1] estimated | Likely | 2025-12-23 | Superseded / alternative |
| Current IT capacity | 626 MW | [1] estimated | Likely | 2026-02-09 | Superseded / alternative |
| Current IT capacity | 910 MW | [1] estimated | Likely | 2026-03-23 | Superseded / alternative |
| Planned capacity | 2.31 GW | [1] estimated | Likely | 2026-06-03 | Superseded / alternative |
| Planned capacity | 2.2 GW | [2] | Confirmed | 2025-10-29 | Shown |
| Planned capacity | 2.2 GW | [2] AI-extracted | Likely | 2025-10 | Superseded / alternative |
| Estimated annual consumption | 6,696 GWh/yr | [3] estimated | Speculative | 2026-10-12 | Shown |
| ISO / RTO | PJMPJM INTERCONNECTION, LLC | [4] derived | Likely | — | Shown |
| Balancing authority | PJM | [5] derived | Likely | — | Shown |
| Nearest mapped substation | Unnamed substation (345 kV)way/1466907498 | [6] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 1.2 km | [6] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 345 kV | [6] derived | Likely | 2026-09-28 | Shown |
| Generation queued in county | 2.71 GW | [7] derived | Confirmed | 2026-10-12 | Shown |
| State avg. industrial price | 9.16¢/kWh | [8] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 13.30¢/kWh | [8] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 4.7 GW | [9] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 18 | [1] derived | Likely | 2026-06-03 | Superseded / alternative |
| Buildings (planned) | 30 | [2] | Confirmed | 2025-10-29 | Shown |
| Buildings (planned) | 30 | [2] AI-extracted | Likely | 2025-10 | Superseded / alternative |
| Buildings operational | 16 | [1] estimated | Likely | 2026-06-03 | Superseded / alternative |
| Buildings operational | 0 | [1] estimated | Likely | 2024-02-09 | Superseded / alternative |
| Buildings operational | 0 | [1] estimated | Likely | 2024-06-10 | Superseded / alternative |
| Buildings operational | 0 | [1] estimated | Likely | 2025-05-10 | Superseded / alternative |
| Buildings operational | 7 | [1] estimated | Likely | 2025-06-23 | Superseded / alternative |
| Buildings operational | 7 | [1] estimated | Likely | 2025-09-26 | Superseded / alternative |
| Buildings operational | 7 | [1] estimated | Likely | 2025-10-17 | Superseded / alternative |
| Buildings operational | 11 | [1] estimated | Likely | 2025-12-23 | Superseded / alternative |
| Buildings operational | 11 | [1] estimated | Likely | 2026-02-09 | Superseded / alternative |
| Buildings operational | 16 | [1] estimated | Likely | 2026-03-23 | Superseded / alternative |
| Buildings operational | 7 | [2] | Confirmed | 2025-10-29 | Shown |
| Buildings operational | 7 | [2] AI-extracted | Likely | 2025-10 | Superseded / alternative |
| Building footprint | 1.47M sq ftway/1471517731 way/1471517732 way/1471517733 way/1471517734 way/1471517735 way/1 | [6] derived | Likely | 2026-10-12 | Shown |
| Site area | 1,200 acres | [2] | Confirmed | 2025-10-29 | Shown |
| Site area | 1,200 acres | [2] AI-extracted | Likely | 2025-10 | Superseded / alternative |
| Capital cost / investment | $34.5B | [1] estimated | Likely | 2026-06-03 | Superseded / alternative |
| Capital cost / investment | $11B | [2] | Confirmed | 2025-10-29 | Shown |
| Capital cost / investment | $11B | [2] AI-extracted | Likely | 2025-10 | Superseded / alternative |
| Compute (H100-equivalents) | 685,900 | [1] estimated | Likely | 2026-06-03 | Shown |
| Chip types | Trainium2 | [1] | Confirmed | 2026-06-03 | Shown |
| Chip types | Trainium2 | [2] | Confirmed | 2025-10-29 | Shown |
| Construction start | Feb 9, 2024 | [1] derived | Likely | 2026-06-03 | Superseded / alternative |
| Construction start | Sep 2024 | [2] | Confirmed | 2025-10-29 | Shown |
| First operational | Jun 23, 2025 | [1] derived | Likely | 2026-06-03 | Superseded / alternative |
| First operational | Oct 2025 | [2] AI-extracted | Likely | 2025-10-29 | Shown |
| Expected completion | Mar 17, 2028 | [1] estimated | Speculative | 2026-06-03 | Shown |