What changed — Dominion Energy

Follow

Get changes to Dominion Energy

How often

Double opt-in; one-click unsubscribe in every email. We store only your email and what you follow. More

Or subscribe in a feed reader: RSS / Atom

RSS / Atom feed for this view

Capacity, status, permit, grid-request and construction changes over the last three years, each with its source. A change means the same source reported a new value later; two sources disagreeing is not a change. Follow a facility, company, utility, state or ISO by email, or subscribe to the feed in any RSS reader.

Each change is tagged by evidence: ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. filing, deed, permit or grid recordAnnouncedStated by the company or reported in the press; not yet backed by a filing or grid record. company or press claimEst.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. satellite, model or map inferenceHow levels are assigned

Clear
Changes per month by evidence level. Click a month to filter (showing 2025-02; click it again to clear).
2023-112026-10
This view:Download CSVJSONAPI docs
  1. Feb 4, 2025
    QTS Richmond 1 · VA
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Current IT capacity: 94 MW → 142 MW
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Current facility power: 132 MW → 199 MW
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Buildings operational: 2 → 3
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.New capacity online: Building 3 is operational, based on the building looking complete and the carpark to the south being full. Three more backup generators added to the Building 1 and 2 area, with a lot more construction equipment again …
    Source: Epoch AI
  2. Feb 4, 2025
    QTS Richmond 2 · VA
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Buildings operational: 0 → 2
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Status: Under construction → Operating + expanding
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.New capacity online: Building 1 and 2 are operational, based on the east substation looking complete and the carparks being more full. Building 3 has cooling and generators mostly installed. Building 4 roof is partly completed.