What changed — SpaceXAI (xAI)
Follow
Get changes to SpaceXAI (xAI)
Or subscribe in a feed reader: RSS / Atom
Capacity, status, permit, grid-request and construction changes over the last three years, each with its source. A change means the same source reported a new value later; two sources disagreeing is not a change. Follow a facility, company, utility, state or ISO by email, or subscribe to the feed in any RSS reader.
Each change is tagged by evidence: ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. filing, deed, permit or grid recordAnnouncedStated by the company or reported in the press; not yet backed by a filing or grid record. company or press claimEst.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. satellite, model or map inferenceHow levels are assigned
- Feb 28, 2025Colossus 2 · MS
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Construction started: Land clearing begins next to the existing building.
Source: Epoch AI - Feb 20, 2025xAI QTS Atlanta · GA
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Buildings operational: 0 → 1
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Status: Under construction → Operating + expanding
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.New capacity online: xAI's GPU cluster in the QTS Atlanta building at 1025 Jefferson Street NW is operational around this time. This date is a tentative estimate: Business Insider reported the buildout in February 2025, so the cluster lik…
Source: Epoch AI - Feb 17, 2025Colossus 1 · TN
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Current IT capacity: 139 MW → 278 MW
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Current facility power: 181 MW → 361 MW
Source: Epoch AI