xAI QTS Atlanta

OperatingEst.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 10, 2026.AI campusCampusAtlanta, Fulton County, Georgia

xAI QTS Atlanta is an operating ai campus in Atlanta, Georgia. Operated or owned by SpaceXAI (xAI); used by SpaceXAI (xAI). Current power: 24 MW (estimated). Verification: verified operating. 10 cited sources.

70% profile completeness
37 claims from 11 sources
Last verified against sources: Oct 12, 2026
Newest dated evidence: Jul 10, 2026
Follow

Get changes to xAI QTS Atlanta

How often

Double opt-in; one-click unsubscribe in every email. We store only your email and what you follow. More

Or subscribe in a feed reader: RSS / Atom

Cite this
Text
Datacenter Source. “xAI QTS Atlanta.” /facilities/xai-qts-atlanta-atlanta-ga. Data as of 2026-10-12. Accessed 2026-10-12.
BibTeX
@misc{datacentersource_xai_qts_atlanta_atlanta_ga_2026,
  title = {{xAI QTS Atlanta}},
  author = {{Datacenter Source}},
  year = {2026},
  howpublished = {\url{/facilities/xai-qts-atlanta-atlanta-ga}},
  note = {Data as of 2026-10-12; accessed 2026-10-12. Compiled from cited sources, including OpenStreetMap contributors (ODbL) and Epoch AI (CC BY 4.0)},
}

Please also cite the original source of any specific figure (linked beside it).

Current facility power
24 MW[1]
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 10, 2026.Likelyestimated
Planned capacity
Not yet sourced
Building footprint
418,400 sq ft[5]
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Likelyderived
Buildings (planned)
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 10, 2026.Likelyderived
Capital cost / investment
$0.7B[1]
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 10, 2026.Likelyestimated
First operational
Feb 20, 2025[1]
Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 10, 2026.Likelyderived

POWER & GRID

Time-to-power · verification · interconnection
Time to power
Energized — operating
High confidence
Project verification
Verified operating
Operation documented by satellite imagery.
Current stage
Operational
Furthest stage with documented evidence
Utility · ISO
Georgia Power · None (non-RTO region)
Substation: On-site substation (likely QTS Substation #2)

Power reality

Announced
No record
Interconnection request
No record
Contracted / approved
No record
Under construction
No record
Operational
24 MW[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
Estimated from buildings observed operational
AI evidence brief
Summarizes only the evidence on this page. Answers citing anything else are rejected automatically.

Project verification

Development
  1. Announcedimplied by a later stage
  2. Land acquiredimplied by a later stage
  3. Planning / zoningimplied by a later stage
  4. Permittingimplied by a later stage
Grid interconnection
  1. Interconnection application
  2. Feasibility study
  3. System impact study
  4. Facilities study
  5. Interconnection agreement / service contract
Build & energization
  1. Financing
  2. Under constructionJan 23, 2024
    Model estimate · Satellite imagery
    • Jan 23, 2024 · Reported status: under construction[1]
    • Jan 23, 2024 · Construction start[1]
    • Jan 23, 2024 · X Corp's $700 million investment in AI training hardware for the Atlanta data center is approved by the Development Authority of Fulton County ([bond resolution fact sheet](https:/[1]
    • Feb 20, 2025 · Reported status: expanding[1]
  3. EnergizationFeb 20, 2025
    Satellite imagery
    • Feb 20, 2025 · xAI's GPU cluster in the QTS Atlanta building at 1025 Jefferson Street NW is operational around this time. This date is a tentative estimate: Business Insider reported the buildout[1]
  4. OperationalFeb 20, 2025
    Satellite imagery
    • Feb 20, 2025 · xAI's GPU cluster in the QTS Atlanta building at 1025 Jefferson Street NW is operational around this time. This date is a tentative estimate: Business Insider reported the buildout[1]

● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.

Grid path

  1. facility
    xAI QTS Atlanta
  2. substation
    On-site substation (likely QTS Substation #2)[1][5]
    Satellite imageryLikely
    2 substation outlines traced inside the campus on satellite imagery; OSM maps QTS Substation #2 0.11 km away
  3. transmission
    230 kV line[5]
    Proximity onlyUnverified
    Highest-voltage line mapped within 2 km (0.17 km away). Not confirmed as the supply path.
  4. utility
    Georgia Power[2]
    Service territoryLikely
    Retail service territory containing the site
  5. ISO / RTO
    None (non-RTO region)[4]
    Service territoryLikely
    Balancing authority: SOCO
Substation capacity:
not published
Required upgrades:
not yet sourced
Congestion:
not yet sourced (no nodal price data)

Dashed boxes are based on proximity only and do not establish which asset serves the site.

Interconnection records

No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.

On-site & dedicated generation

No on-site, behind-the-meter or dedicated generation found in sources.

LOCAL IMPACT

Water · generation · incentives · regulation · rates

Water & cooling

Not yet collected: we haven't found a source for water use or the cooling type at this site. Know one? Add a source

On-site generation & air permits

Not yet collected: we haven't found a source for on-site generation or an air permit for this site. Know one? Add a source

Incentives

Not yet collected: we haven't found a source for tax abatements, PILOTs or other incentives for this project. Know one? Add a source

Regulatory events

Not yet collected: we haven't found a source for hearings, rezonings, permits or commission proceedings. Know one? Add a source

Utility & rates1

  • Rules for serving large-load customers through customized contracts[11]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jan 2025.Jan 2025
    Georgia Power · Georgia Public Service Commission · Approved

    “In January, the Georgia PSC approved new rules and regulations that enable Georgia Power to serve large-load customers through customized contracts — including terms such as upfront infrastructure payments, long-term commitments, and financial guarantees”

Location & imagery

Mapped outline
Coordinates
33.77710, -84.41949
Address
1025 Jefferson Street NW, Atlanta, GA 30318[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 10, 2026.Likely
County
Fulton County
Photographs

No openly licensed ground-level photos matched to this site yet.

Ownership, operation & customers

  1. 1. Property owner of record
    Not identified
  2. 2. Owner / developer
  3. 3. Operator
    Not identified
  4. 4. Tenant / cloud
    Not identified
  5. 5. End customer / workload
Power supply
Utility:

Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.

All parties with evidence
Owner
End user
Utility

Location falls inside this utility's retail service territory.

Power (all fields)

Current facility power
24 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 10, 2026.Likelyestimated

Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.

Current IT capacity
17 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 10, 2026.Likelyestimated

Estimated IT load currently online, based on buildings observed operational.

Estimated annual consumption
147 GWh/yr[3]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Speculativeestimated

24 MW × 8,760 h × 70% utilization.

Planned capacity
Not yet sourced

Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.

Grid & electricity

ISO / RTO
None (non-RTO region)[4]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived

Outside all ISO/RTO footprints; balancing authority shown separately.

Balancing authority
SOCO[2]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived

Control area of the containing utility territory.

Nearest mapped substation
QTS Substation #2 (115 kV)[5]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived

Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.

Distance to substation
0.1 km[5]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
Highest-voltage line nearby
230 kV[5]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived

Highest-voltage transmission line mapped within 2 km.

State avg. industrial price
10.03¢/kWh[6]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed

Georgia statewide average, July 2026.

State avg. commercial price
12.54¢/kWh[6]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed

Georgia statewide average, July 2026.

Generation within 50 km
2.61 GW[7]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jan 1, 202502.Confirmedderived

22 EIA-reported plants within 50 km.

Interconnection status
Not yet sourced
Contracted / committed power
Not yet sourced
Nearby infrastructureTypeDistanceVoltage / capacitySource
115 kV line · Georgia PowerTransmission line0.12 km115 kV[5]
230 kV lineTransmission line0.17 km230 kV[5]
Cnn Center · RREF IV-P CP III Marietta Street LLCPower plant (Petroleum)3 km13 MW[7]
Jack Mcdonough · Georgia Power CoPower plant (Natural Gas)7.4 km2.54 GW[7]
Emory Decatur Hospital · DeKalb Regional Health SystemPower plant (Petroleum)12.7 km4 MW[7]
Mas Asb Cogen Plant · Cube District Energy, LLCPower plant (Natural Gas)13.8 km7 MW[7]
Morgan Falls · Georgia Power CoPower plant (Hydroelectric)21.5 km11 MW[7]
Solar Bess Hybrid · Cobb Electric Membership CorporationPower plant (Solar)25.8 km3 MW[7]
Hewlett Packard Enterprise · SWVP Alpharetta Owners, LLCPower plant (Petroleum)37.1 km8 MW[7]
State Farm Support Center East · State Farm Mutual Auto Ins CoPower plant (Petroleum)37.9 km11 MW[7]
QTS Substation #2 · Georgia PowerSubstation0.11 km115 kV[5]
Unnamed substationSubstation0.36 km—[5]
QTS Substation #1 · Georgia PowerSubstation0.38 km115 kV[5]
Georgia Power Company substation · Georgia Power CompanySubstation1.05 km230 kV[5]
Georgia Power substation · Georgia PowerSubstation1.07 km230 kV[5]
Unnamed substationSubstation1.26 km230 kV[5]

Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.

Construction & permitting

  1. Announced
    —
  2. Land acquired
    —
  3. Permitting
    —
  4. Construction start
    Jan 23, 2024[1]
  5. First operational
    Feb 20, 2025[1]
  6. Expected completion
    —
Buildings (planned)
1[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 10, 2026.Likelyderived

Count of building outlines traced on satellite imagery.

Buildings operational
1[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 10, 2026.Likelyestimated
PhaseStatusAdded MWCompleted / expectedSource
Building 1operational24 MWFeb 20, 2025[1]

Real estate

Official assessments
Assessor's value for a tax year

None sourced yet

Recorded transactions
Sale prices from recorded deeds

None sourced yet

Model estimates
Our model — not an appraisal

None sourced yet

Capital cost / investment
$0.7B[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 10, 2026.Likelyestimated

Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.

Annual property tax
Not yet sourced

No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.

Size

Building footprint
418,400 sq ft[5]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Likelyderived

Sum of 2 building outlines mapped in OpenStreetMap within this campus.

Floor area
Not yet sourced

Compute

Chip types
H100, A100[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 10, 2026.Confirmed
Compute (H100-equivalents)
11,500[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 10, 2026.Likelyestimated

What changed (last 3 years)

Follow this facility (RSS)
  • Buildings operational
    0Jan 23, 2024[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→1Feb 20, 2025[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
  • Status
    Under constructionJan 23, 2024[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→Operating + expandingFeb 20, 2025[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→OperatingJul 10, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.

Timeline

Construction start: Jan 23, 2024[1]
First operational: Feb 20, 2025[1]
  1. Jan 23, 2024[1]

    X Corp's $700 million investment in AI training hardware for the Atlanta data center is approved by the Development Authority of Fulton County (bond resolution fact sheet).

  2. Feb 20, 202524 MW facility power· 1 buildings operational[1]

    xAI's GPU cluster in the QTS Atlanta building at 1025 Jefferson Street NW is operational around this time. This date is a tentative estimate: Business Insider reported the buildout in February 2025, so the cluster likely came online around or shortly after then, though the exact date is not disclosed. The cluster comprises 11,000 NVIDIA H100 and about 1,448 A100 GPUs, based on documents submitted to Develop Fulton as reported by Business Insider. xAI occupies part of this multi-tenant building, so its cooling is not attributed to xAI alone.

  3. Aug 21, 202524 MW facility power· 1 buildings operational[1]

    No significant change to the building since the cluster became operational.

  4. Jul 10, 202624 MW facility power· 1 buildings operational[1]

    No significant change to the building since the August 2025 image.

Buildings on this campus

2

All claims (provenance audit)

37
FieldValueSourceConfidenceAs ofStatus
NamexAI QTS Atlanta[1] Likely2026-07-10Shown
StatusUnder construction[1] derivedLikely2024-01-23Superseded / alternative
StatusOperating + expanding[1] derivedLikely2025-02-20Superseded / alternative
StatusOperating + expanding[1] derivedLikely2025-08-21Superseded / alternative
StatusOperating[1] derivedLikely2026-07-10Shown
Facility typeAI campus[1] derivedLikely2026-07-10Shown
Address1025 Jefferson Street NW, Atlanta, GA 30318[1] Likely2026-07-10Shown
OwnerSpaceXAI (xAI)Owner: SpaceXAI[1] Confirmed2026-07-10Shown
End usersSpaceXAI (xAI)Users: SpaceXAI[1] Confirmed2026-07-10Shown
UtilityGeorgia Powerterritory 7140: GEORGIA POWER CO (INVESTOR OWNED, SOUTHERN COMPANY)[2] derivedLikely2022Shown
Current facility power24 MW[1] estimatedLikely2026-07-10Shown
Current facility power24 MW[1] estimatedLikely2025-02-20Superseded / alternative
Current facility power24 MW[1] estimatedLikely2025-08-21Superseded / alternative
Current IT capacity17 MW[1] estimatedLikely2026-07-10Shown
Current IT capacity17 MW[1] estimatedLikely2025-02-20Superseded / alternative
Current IT capacity17 MW[1] estimatedLikely2025-08-21Superseded / alternative
Estimated annual consumption147 GWh/yr[3] estimatedSpeculative2026-10-12Shown
ISO / RTONone (non-RTO region)[4] derivedLikely—Shown
Balancing authoritySOCO[2] derivedLikely—Shown
Nearest mapped substationQTS Substation #2 (115 kV)way/1007825572[5] derivedLikely2026-09-28Shown
Distance to substation0.1 km[5] derivedLikely2026-09-28Shown
Highest-voltage line nearby230 kV[5] derivedLikely2026-09-28Shown
State avg. industrial price10.03¢/kWh[6] Confirmed2026-07Shown
State avg. commercial price12.54¢/kWh[6] Confirmed2026-07Shown
Generation within 50 km2.61 GW[7] derivedConfirmed202502Shown
Buildings (planned)1[1] derivedLikely2026-07-10Shown
Buildings operational1[1] estimatedLikely2026-07-10Shown
Buildings operational0[1] estimatedLikely2024-01-23Superseded / alternative
Buildings operational1[1] estimatedLikely2025-02-20Superseded / alternative
Buildings operational1[1] estimatedLikely2025-08-21Superseded / alternative
Building footprint418,400 sq ftway/1566676867 way/1566676868[5] derivedLikely2026-10-12Shown
Capital cost / investment$0.7B[1] estimatedLikely2026-07-10Shown
Compute (H100-equivalents)11,500[1] estimatedLikely2026-07-10Shown
Chip typesH100[1] Confirmed2026-07-10Shown
Chip typesA100[1] Confirmed2026-07-10Shown
Construction startJan 23, 2024[1] derivedLikely2026-07-10Shown
First operationalFeb 20, 2025[1] derivedLikely2026-07-10Shown