xAI QTS Atlanta
xAI QTS Atlanta is an operating ai campus in Atlanta, Georgia. Operated or owned by SpaceXAI (xAI); used by SpaceXAI (xAI). Current power: 24 MW (estimated). Verification: verified operating. 10 cited sources.
Follow
Get changes to xAI QTS Atlanta
Or subscribe in a feed reader: RSS / Atom
Cite this
Datacenter Source. “xAI QTS Atlanta.” /facilities/xai-qts-atlanta-atlanta-ga. Data as of 2026-10-12. Accessed 2026-10-12.
@misc{datacentersource_xai_qts_atlanta_atlanta_ga_2026,
title = {{xAI QTS Atlanta}},
author = {{Datacenter Source}},
year = {2026},
howpublished = {\url{/facilities/xai-qts-atlanta-atlanta-ga}},
note = {Data as of 2026-10-12; accessed 2026-10-12. Compiled from cited sources, including OpenStreetMap contributors (ODbL) and Epoch AI (CC BY 4.0)},
}Please also cite the original source of any specific figure (linked beside it).
POWER & GRID
Time-to-power · verification · interconnectionPower reality
Project verification
- Announcedimplied by a later stage
- Land acquiredimplied by a later stage
- Planning / zoningimplied by a later stage
- Permittingimplied by a later stage
- Interconnection application
- Feasibility study
- System impact study
- Facilities study
- Interconnection agreement / service contract
- Financing
- Under constructionJan 23, 2024
Model estimate · Satellite imagery
- Jan 23, 2024 · Reported status: under construction[1]
- Jan 23, 2024 · Construction start[1]
- Jan 23, 2024 · X Corp's $700 million investment in AI training hardware for the Atlanta data center is approved by the Development Authority of Fulton County ([bond resolution fact sheet](https:/[1]
- Feb 20, 2025 · Reported status: expanding[1]
- EnergizationFeb 20, 2025
Satellite imagery
- Feb 20, 2025 · xAI's GPU cluster in the QTS Atlanta building at 1025 Jefferson Street NW is operational around this time. This date is a tentative estimate: Business Insider reported the buildout[1]
- OperationalFeb 20, 2025
Satellite imagery
- Feb 20, 2025 · xAI's GPU cluster in the QTS Atlanta building at 1025 Jefferson Street NW is operational around this time. This date is a tentative estimate: Business Insider reported the buildout[1]
● documented · ◌ implied by a later stage · ○ no evidence found. Dates are those of the earliest dated evidence, which can be later than when a stage actually began. Evidence classes: Model estimate, Satellite imagery.
Grid path
- →facilityxAI QTS Atlanta
- →substationSatellite imageryLikely2 substation outlines traced inside the campus on satellite imagery; OSM maps QTS Substation #2 0.11 km away
- →transmission230 kV line[5]Proximity onlyUnverifiedHighest-voltage line mapped within 2 km (0.17 km away). Not confirmed as the supply path.
- →
- Substation capacity:
- not published
- Required upgrades:
- not yet sourced
- Congestion:
- not yet sourced (no nodal price data)
Dashed boxes are based on proximity only and do not establish which asset serves the site.
Interconnection records
No interconnection-queue record is linked to this site. Of the ISOs we ingest, only NYISO publishes large-load requests; PJM, ERCOT, MISO, SPP and CAISO queues list generation only.
On-site & dedicated generation
No on-site, behind-the-meter or dedicated generation found in sources.
LOCAL IMPACT
Water · generation · incentives · regulation · ratesWater & cooling
Not yet collected: we haven't found a source for water use or the cooling type at this site. Know one? Add a source
On-site generation & air permits
Not yet collected: we haven't found a source for on-site generation or an air permit for this site. Know one? Add a source
Incentives
Not yet collected: we haven't found a source for tax abatements, PILOTs or other incentives for this project. Know one? Add a source
Regulatory events
Not yet collected: we haven't found a source for hearings, rezonings, permits or commission proceedings. Know one? Add a source
Utility & rates1
- Rules for serving large-load customers through customized contracts[11]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jan 2025.Jan 2025Georgia Power · Georgia Public Service Commission · Approved
“In January, the Georgia PSC approved new rules and regulations that enable Georgia Power to serve large-load customers through customized contracts — including terms such as upfront infrastructure payments, long-term commitments, and financial guarantees”
Location & imagery
Mapped outline- Coordinates
- 33.77710, -84.41949
- Address
- 1025 Jefferson Street NW, Atlanta, GA 30318[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 10, 2026.Likely
- County
- Fulton County
No openly licensed ground-level photos matched to this site yet.
Ownership, operation & customers
- 1. Property owner of recordNot identified
- 2. Owner / developer
- 3. OperatorNot identified
- 4. Tenant / cloudNot identified
- 5. End customer / workload
Each link is sourced separately. The property owner of record is often a special-purpose entity; the same company appearing in two roles is shown only when sources say so.
All parties with evidence
- Owner
- End user
- Utility
Location falls inside this utility's retail service territory.
Power (all fields)
- Current facility power
- 24 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 10, 2026.Likelyestimated
Estimated total facility power (IT plus cooling and overhead) at the latest observed milestone.
- Current IT capacity
- 17 MW[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 10, 2026.Likelyestimated
Estimated IT load currently online, based on buildings observed operational.
- Estimated annual consumption
- 147 GWh/yr[3]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Speculativeestimated
24 MW × 8,760 h × 70% utilization.
- Planned capacity
- Not yet sourced
Capacity figures are nameplate or contracted; annual consumption is a labeled model estimate, not metered data.
Grid & electricity
- ISO / RTO
- None (non-RTO region)[4]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived
Outside all ISO/RTO footprints; balancing authority shown separately.
- Balancing authority
- SOCO[2]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Likelyderived
Control area of the containing utility territory.
- Nearest mapped substation
- QTS Substation #2 (115 kV)[5]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
Nearest substation mapped in OpenStreetMap; proximity does not establish which substation serves the site.
- Distance to substation
- 0.1 km[5]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
- Highest-voltage line nearby
- 230 kV[5]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Sep 28, 2026.Likelyderived
Highest-voltage transmission line mapped within 2 km.
- State avg. industrial price
- 10.03¢/kWh[6]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed
Georgia statewide average, July 2026.
- State avg. commercial price
- 12.54¢/kWh[6]ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. As of Jul 2026.Confirmed
Georgia statewide average, July 2026.
- Generation within 50 km
- 2.61 GW[7]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jan 1, 202502.Confirmedderived
22 EIA-reported plants within 50 km.
- Interconnection status
- Not yet sourced
- Contracted / committed power
- Not yet sourced
| Nearby infrastructure | Type | Distance | Voltage / capacity | Source |
|---|---|---|---|---|
| 115 kV line · Georgia Power | Transmission line | 0.12 km | 115 kV | [5] |
| 230 kV line | Transmission line | 0.17 km | 230 kV | [5] |
| Cnn Center · RREF IV-P CP III Marietta Street LLC | Power plant (Petroleum) | 3 km | 13 MW | [7] |
| Jack Mcdonough · Georgia Power Co | Power plant (Natural Gas) | 7.4 km | 2.54 GW | [7] |
| Emory Decatur Hospital · DeKalb Regional Health System | Power plant (Petroleum) | 12.7 km | 4 MW | [7] |
| Mas Asb Cogen Plant · Cube District Energy, LLC | Power plant (Natural Gas) | 13.8 km | 7 MW | [7] |
| Morgan Falls · Georgia Power Co | Power plant (Hydroelectric) | 21.5 km | 11 MW | [7] |
| Solar Bess Hybrid · Cobb Electric Membership Corporation | Power plant (Solar) | 25.8 km | 3 MW | [7] |
| Hewlett Packard Enterprise · SWVP Alpharetta Owners, LLC | Power plant (Petroleum) | 37.1 km | 8 MW | [7] |
| State Farm Support Center East · State Farm Mutual Auto Ins Co | Power plant (Petroleum) | 37.9 km | 11 MW | [7] |
| QTS Substation #2 · Georgia Power | Substation | 0.11 km | 115 kV | [5] |
| Unnamed substation | Substation | 0.36 km | — | [5] |
| QTS Substation #1 · Georgia Power | Substation | 0.38 km | 115 kV | [5] |
| Georgia Power Company substation · Georgia Power Company | Substation | 1.05 km | 230 kV | [5] |
| Georgia Power substation · Georgia Power | Substation | 1.07 km | 230 kV | [5] |
| Unnamed substation | Substation | 1.26 km | 230 kV | [5] |
Utility, ISO and nearby assets are derived from the site's location. Proximity to a substation or line doesn't establish the interconnection; that needs a utility filing or interconnection-queue record. Queue requests are applications, not commitments — most never reach operation.
Construction & permitting
- Announced—
- Land acquired—
- Permitting—
- Construction startJan 23, 2024[1]
- First operationalFeb 20, 2025[1]
- Expected completion—
- Buildings (planned)
- 1[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 10, 2026.Likelyderived
Count of building outlines traced on satellite imagery.
- Buildings operational
- 1[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 10, 2026.Likelyestimated
| Phase | Status | Added MW | Completed / expected | Source |
|---|---|---|---|---|
| Building 1 | operational | 24 MW | Feb 20, 2025 | [1] |
Real estate
None sourced yet
None sourced yet
None sourced yet
- Capital cost / investment
- $0.7B[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 10, 2026.Likelyestimated
Modeled total capital cost (2025 USD) of capacity currently operational, incl. compute hardware.
- Annual property tax
- Not yet sourced
No county parcel or assessor records linked yet. County records are currently ingested for Loudoun County, VA and Maricopa County, AZ.
Size
- Building footprint
- 418,400 sq ft[5]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Oct 12, 2026.Likelyderived
Sum of 2 building outlines mapped in OpenStreetMap within this campus.
- Floor area
- Not yet sourced
Compute
- Chip types
- H100, A100[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 10, 2026.Confirmed
- Compute (H100-equivalents)
- 11,500[1]Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. As of Jul 10, 2026.Likelyestimated
What changed (last 3 years)
Follow this facility (RSS)- Buildings operational
- StatusUnder constructionJan 23, 2024[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→Operating + expandingFeb 20, 2025[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.→OperatingJul 10, 2026[1]EstimatedModeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.
Timeline
- Jan 23, 2024[1]
X Corp's $700 million investment in AI training hardware for the Atlanta data center is approved by the Development Authority of Fulton County (bond resolution fact sheet).
xAI's GPU cluster in the QTS Atlanta building at 1025 Jefferson Street NW is operational around this time. This date is a tentative estimate: Business Insider reported the buildout in February 2025, so the cluster likely came online around or shortly after then, though the exact date is not disclosed. The cluster comprises 11,000 NVIDIA H100 and about 1,448 A100 GPUs, based on documents submitted to Develop Fulton as reported by Business Insider. xAI occupies part of this multi-tenant building, so its cooling is not attributed to xAI alone.
No significant change to the building since the cluster became operational.
No significant change to the building since the August 2025 image.
Buildings on this campus
2- QTS Atlanta Data Center 1Operating · 721,600 sq ft footprint
- QTS Atlanta Data Center 2Operating · 275,500 sq ft footprint
All claims (provenance audit)
37| Field | Value | Source | Confidence | As of | Status |
|---|---|---|---|---|---|
| Name | xAI QTS Atlanta | [1] | Likely | 2026-07-10 | Shown |
| Status | Under construction | [1] derived | Likely | 2024-01-23 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-02-20 | Superseded / alternative |
| Status | Operating + expanding | [1] derived | Likely | 2025-08-21 | Superseded / alternative |
| Status | Operating | [1] derived | Likely | 2026-07-10 | Shown |
| Facility type | AI campus | [1] derived | Likely | 2026-07-10 | Shown |
| Address | 1025 Jefferson Street NW, Atlanta, GA 30318 | [1] | Likely | 2026-07-10 | Shown |
| Owner | SpaceXAI (xAI)Owner: SpaceXAI | [1] | Confirmed | 2026-07-10 | Shown |
| End users | SpaceXAI (xAI)Users: SpaceXAI | [1] | Confirmed | 2026-07-10 | Shown |
| Utility | Georgia Powerterritory 7140: GEORGIA POWER CO (INVESTOR OWNED, SOUTHERN COMPANY) | [2] derived | Likely | 2022 | Shown |
| Current facility power | 24 MW | [1] estimated | Likely | 2026-07-10 | Shown |
| Current facility power | 24 MW | [1] estimated | Likely | 2025-02-20 | Superseded / alternative |
| Current facility power | 24 MW | [1] estimated | Likely | 2025-08-21 | Superseded / alternative |
| Current IT capacity | 17 MW | [1] estimated | Likely | 2026-07-10 | Shown |
| Current IT capacity | 17 MW | [1] estimated | Likely | 2025-02-20 | Superseded / alternative |
| Current IT capacity | 17 MW | [1] estimated | Likely | 2025-08-21 | Superseded / alternative |
| Estimated annual consumption | 147 GWh/yr | [3] estimated | Speculative | 2026-10-12 | Shown |
| ISO / RTO | None (non-RTO region) | [4] derived | Likely | — | Shown |
| Balancing authority | SOCO | [2] derived | Likely | — | Shown |
| Nearest mapped substation | QTS Substation #2 (115 kV)way/1007825572 | [5] derived | Likely | 2026-09-28 | Shown |
| Distance to substation | 0.1 km | [5] derived | Likely | 2026-09-28 | Shown |
| Highest-voltage line nearby | 230 kV | [5] derived | Likely | 2026-09-28 | Shown |
| State avg. industrial price | 10.03¢/kWh | [6] | Confirmed | 2026-07 | Shown |
| State avg. commercial price | 12.54¢/kWh | [6] | Confirmed | 2026-07 | Shown |
| Generation within 50 km | 2.61 GW | [7] derived | Confirmed | 202502 | Shown |
| Buildings (planned) | 1 | [1] derived | Likely | 2026-07-10 | Shown |
| Buildings operational | 1 | [1] estimated | Likely | 2026-07-10 | Shown |
| Buildings operational | 0 | [1] estimated | Likely | 2024-01-23 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2025-02-20 | Superseded / alternative |
| Buildings operational | 1 | [1] estimated | Likely | 2025-08-21 | Superseded / alternative |
| Building footprint | 418,400 sq ftway/1566676867 way/1566676868 | [5] derived | Likely | 2026-10-12 | Shown |
| Capital cost / investment | $0.7B | [1] estimated | Likely | 2026-07-10 | Shown |
| Compute (H100-equivalents) | 11,500 | [1] estimated | Likely | 2026-07-10 | Shown |
| Chip types | H100 | [1] | Confirmed | 2026-07-10 | Shown |
| Chip types | A100 | [1] | Confirmed | 2026-07-10 | Shown |
| Construction start | Jan 23, 2024 | [1] derived | Likely | 2026-07-10 | Shown |
| First operational | Feb 20, 2025 | [1] derived | Likely | 2026-07-10 | Shown |