What changed — Oracle
Follow
Get changes to Oracle
Or subscribe in a feed reader: RSS / Atom
Capacity, status, permit, grid-request and construction changes over the last three years, each with its source. A change means the same source reported a new value later; two sources disagreeing is not a change. Follow a facility, company, utility, state or ISO by email, or subscribe to the feed in any RSS reader.
Each change is tagged by evidence: ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. filing, deed, permit or grid recordAnnouncedStated by the company or reported in the press; not yet backed by a filing or grid record. company or press claimEst.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. satellite, model or map inferenceHow levels are assigned
- May 23, 2026OpenAI Stargate Abilene · TX
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Current IT capacity: 211 MW → 421 MW
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Current facility power: 295 MW → 590 MW
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Buildings operational: 2 → 4
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.New capacity online: Buildings 3 and 4 are estimated to be operational. On April 22nd, Oracle posted that "In Abilene, 200MW is already operational". This suggests that there was still only Building 1 and 2 operational. Since Buildings 3 …
Source: Epoch AI - Jan 2, 2026OpenAI Stargate Wisconsin · WI
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Construction started: Ground broken for the facility, land clearing begins for all buildings
Source: Epoch AI - Dec 24, 2025OpenAI Stargate Abilene · TX
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Current IT capacity: 105 MW → 211 MW
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Current facility power: 147 MW → 295 MW
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Buildings operational: 1 → 2
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.New capacity online: Building 2 is fully operational. This exact date corresponds to the expected completion date of "Four (4) data hall spaces and an administrative office build-out" according to a TDLR filing, but this date is also cons…
Source: Epoch AI - Dec 4, 2025OpenAI Stargate Michigan · MI
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Construction started: Land clearing begins for the entire site
Source: Epoch AI - Oct 1, 2025OpenAI Stargate New Mexico · NM
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Construction started: Construction and land clearing begins
Source: Epoch AI - Sep 26, 2025OpenAI Stargate Abilene · TX
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Buildings operational: 0 → 1
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Status: Under construction → Operating + expanding
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.New capacity online: Building 1 is fully operational around this date. The first phase was "live" on September 30 according a Crusoe announcement. While the first phase consists of Building 1 and 2, the language doesn't outright confirm t…
Source: Epoch AI - Aug 1, 2025OpenAI Stargate Shackelford · TX
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Construction started: Land clearing begins.
Source: Epoch AI - May 31, 2024OpenAI Stargate Abilene · TX
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Construction started: Land clearing begins for northern two buildings (Building 1-2)
Source: Epoch AI