What changed — Nova Mango Farms LLC C/O Corporation Service Company

Follow

Get changes to Nova Mango Farms LLC C/O Corporation Service Company

How often

Double opt-in; one-click unsubscribe in every email. We store only your email and what you follow. More

Or subscribe in a feed reader: RSS / Atom

RSS / Atom feed for this view

Capacity, status, permit, grid-request and construction changes over the last three years, each with its source. A change means the same source reported a new value later; two sources disagreeing is not a change. Follow a facility, company, utility, state or ISO by email, or subscribe to the feed in any RSS reader.

Each change is tagged by evidence: ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. filing, deed, permit or grid recordAnnouncedStated by the company or reported in the press; not yet backed by a filing or grid record. company or press claimEst.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. satellite, model or map inferenceHow levels are assigned

Clear
Changes per month by evidence level. Click a month to filter.
2023-112026-10
This view:Download CSVJSONAPI docs
  1. May 20, 2026
    Google Bristow · VA
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Current IT capacity: 174 MW → 238 MW
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Current facility power: 208 MW → 286 MW
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Buildings operational: 2 → 3
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Status: Operating + expanding → Operating
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.New capacity online: Building 3 is operational, based off of colored motion artifacts from cooling towers.
    Source: Epoch AI
  2. Apr 29, 2025
    Google Bristow · VA
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Current IT capacity: 87 MW → 174 MW
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Current facility power: 104 MW → 208 MW
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Buildings operational: 1 → 2
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.New capacity online: Building 2 is operational, based off it being at least 12 months since the roof was complete. Building 3 is finishing construction of cooling towers.
    Source: Epoch AI
  3. Apr 29, 2024
    Google Bristow · VA
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Buildings operational: 0 → 1
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Status: Under construction → Operating + expanding
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.New capacity online: Building 1 is operational, based off of colored motion artifacts from cooling towers. Building 2 is undergoing construction.
    Source: Epoch AI