What changed — OpenAI

Follow

Get changes to OpenAI

How often

Double opt-in; one-click unsubscribe in every email. We store only your email and what you follow. More

Or subscribe in a feed reader: RSS / Atom

RSS / Atom feed for this view

Capacity, status, permit, grid-request and construction changes over the last three years, each with its source. A change means the same source reported a new value later; two sources disagreeing is not a change. Follow a facility, company, utility, state or ISO by email, or subscribe to the feed in any RSS reader.

Each change is tagged by evidence: ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. filing, deed, permit or grid recordAnnouncedStated by the company or reported in the press; not yet backed by a filing or grid record. company or press claimEst.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. satellite, model or map inferenceHow levels are assigned

Clear
Changes per month by evidence level. Click a month to filter (showing 2026-05; click it again to clear).
2023-112026-10
This view:Download CSVJSONAPI docs
  1. May 23, 2026
    OpenAI Stargate Abilene · TX
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Current IT capacity: 211 MW → 421 MW
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Current facility power: 295 MW → 590 MW
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Buildings operational: 2 → 4
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.New capacity online: Buildings 3 and 4 are estimated to be operational. On April 22nd, Oracle posted that "In Abilene, 200MW is already operational". This suggests that there was still only Building 1 and 2 operational. Since Buildings 3 …
    Source: Epoch AI
  2. May 20, 2026
    CoreWeave Chester VA · VA
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Current IT capacity: 27 MW → 82 MW
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Current facility power: 38 MW → 114 MW
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Buildings operational: 1 → 2
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.New capacity online: Based on satellite imagery, Building 3 has cleared its land and is beginning construction. Building 2 is operational judging from the colored motion artifacts on the cooling tower fans.
    Source: Epoch AI
  3. May 6, 2026
    CoreWeave Marble NC · NC
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Current IT capacity: 36 MW → 65 MW
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Current facility power: 50 MW → 91 MW
    • Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Status: Operating + expanding → Operating
    Source: Epoch AI