What changed — Dominion Energy
Follow
Get changes to Dominion Energy
Or subscribe in a feed reader: RSS / Atom
Capacity, status, permit, grid-request and construction changes over the last three years, each with its source. A change means the same source reported a new value later; two sources disagreeing is not a change. Follow a facility, company, utility, state or ISO by email, or subscribe to the feed in any RSS reader.
Each change is tagged by evidence: ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record. filing, deed, permit or grid recordAnnouncedStated by the company or reported in the press; not yet backed by a filing or grid record. company or press claimEst.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure. satellite, model or map inferenceHow levels are assigned
- Jun 25, 2024Amazon IAD-1 · VA
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Land acquired: Deed/transfer recorded for parcel 0343 09 0004A (no sale price disclosed).
- Jun 25, 2024Amazon IAD-22 · VA
- ConfirmedBacked by a filing, deed, permit, interconnection-queue record, or a government or utility record.Land acquired: Deed/transfer recorded for parcel 0343 09 0004A (no sale price disclosed).
- Jun 23, 2024QTS Richmond 1 · VA
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Current IT capacity: 47 MW → 94 MW
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Current facility power: 66 MW → 132 MW
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.Buildings operational: 1 → 2
- Est.Modeled, measured from satellite imagery, inferred from community mapping, or computed by this site. Not a disclosed figure.New capacity online: Building 2 (retrofitted) is operational. This is based on Building 2 looking compelte, and construction around Building 1 and 2 being mostly cleared. A colored motion artifact on one of the Building 1 cooling tower fa…
Source: Epoch AI