{"data":[{"facilityId":"epoch-meta-prometheus","slug":"meta-prometheus-new-albany-oh","name":"Meta Prometheus","state":"OH","county":"Licking County","orgIds":["meta","vistra","terrapower","oklo","williams","aep","distribution-land-corp","sidecat-llc"],"iso":"PJM","utilities":["aep"],"id":"epoch-meta-prometheus:power.it_mw:epoch-ai-data-centers:2026-08-31","date":"2026-08-31","kind":"value","field":"power.it_mw","before":368,"after":496,"sourceId":"epoch-ai-data-centers","evidenceLevel":"estimated","text":"Current IT capacity: 368 MW → 496 MW","url":"https://datacenters.prithvidixit.com/facilities/meta-prometheus-new-albany-oh","source":{"id":"epoch-ai-data-centers","title":"AI data centers (Frontier Data Centers Hub)","publisher":"Epoch AI","url":"https://epoch.ai/data/ai-data-centers","license":"CC BY 4.0","retrievedAt":"2026-10-12"}},{"facilityId":"epoch-meta-prometheus","slug":"meta-prometheus-new-albany-oh","name":"Meta Prometheus","state":"OH","county":"Licking County","orgIds":["meta","vistra","terrapower","oklo","williams","aep","distribution-land-corp","sidecat-llc"],"iso":"PJM","utilities":["aep"],"id":"epoch-meta-prometheus:power.facility_mw:epoch-ai-data-centers:2026-08-31","date":"2026-08-31","kind":"value","field":"power.facility_mw","before":478,"after":645,"sourceId":"epoch-ai-data-centers","evidenceLevel":"estimated","text":"Current facility power: 478 MW → 645 MW","url":"https://datacenters.prithvidixit.com/facilities/meta-prometheus-new-albany-oh","source":{"id":"epoch-ai-data-centers","title":"AI data centers (Frontier Data Centers Hub)","publisher":"Epoch AI","url":"https://epoch.ai/data/ai-data-centers","license":"CC BY 4.0","retrievedAt":"2026-10-12"}},{"facilityId":"epoch-meta-prometheus","slug":"meta-prometheus-new-albany-oh","name":"Meta Prometheus","state":"OH","county":"Licking County","orgIds":["meta","vistra","terrapower","oklo","williams","aep","distribution-land-corp","sidecat-llc"],"iso":"PJM","utilities":["aep"],"id":"epoch-meta-prometheus:size.buildings_operational:epoch-ai-data-centers:2026-08-31","date":"2026-08-31","kind":"value","field":"size.buildings_operational","before":6,"after":11,"sourceId":"epoch-ai-data-centers","evidenceLevel":"estimated","text":"Buildings operational: 6 → 11","url":"https://datacenters.prithvidixit.com/facilities/meta-prometheus-new-albany-oh","source":{"id":"epoch-ai-data-centers","title":"AI data centers (Frontier Data Centers Hub)","publisher":"Epoch AI","url":"https://epoch.ai/data/ai-data-centers","license":"CC BY 4.0","retrievedAt":"2026-10-12"}},{"facilityId":"epoch-meta-prometheus","slug":"meta-prometheus-new-albany-oh","name":"Meta Prometheus","state":"OH","county":"Licking County","orgIds":["meta","vistra","terrapower","oklo","williams","aep","distribution-land-corp","sidecat-llc"],"iso":"PJM","utilities":["aep"],"id":"epoch-meta-prometheus:phase_operational:2026-08-31:epoch-ai-data-centers","date":"2026-08-31","kind":"milestone","milestone":"phase_operational","description":"Buildings 7-10 (tents) are operational, based on infrared drone video from RAAD (raad.com) captured on this date. The video suggests that 138.8 MW of nameplate turbine capacity is operating at the Socrates South power plant (about 69% of the 200 MW nameplate capacity), and Buildings 7-10 roof vents are bright on infrared while Buildings 11-12 vents are not. That's 4/6 buildings operating, implying about 67% of capacity, which is consistent with 69% of the power plant operating. In the north, Buildings 16-27 (tents) look to be in a completed state. Each northern set of 6 tents still awaits to be connected to one of the corresponding power plants to become operational. Drone video from August 19th shows no turbines operating at Socrates North, though there are 3 small diesel generators operating. Building 13 (Vantage) is still under construction, we estimate another 3 months before operability.","sourceId":"epoch-ai-data-centers","evidenceLevel":"estimated","text":"New capacity online: Buildings 7-10 (tents) are operational, based on infrared drone video from RAAD (raad.com) captured on this date. The video suggests that 138.8 MW of nameplate turbine capacity is operating at the Socrates South power…","url":"https://datacenters.prithvidixit.com/facilities/meta-prometheus-new-albany-oh","source":{"id":"epoch-ai-data-centers","title":"AI data centers (Frontier Data Centers Hub)","publisher":"Epoch AI","url":"https://epoch.ai/data/ai-data-centers","license":"CC BY 4.0","retrievedAt":"2026-10-12"}},{"facilityId":"epoch-meta-gallatin","slug":"meta-gallatin-gallatin-tn","name":"Meta Gallatin","state":"TN","county":"Sumner County","orgIds":["meta","cumberland-elec-member-corp"],"iso":"None (non-RTO region)","utilities":["cumberland-elec-member-corp"],"id":"epoch-meta-gallatin:phase_operational:2026-08-24:epoch-ai-data-centers","date":"2026-08-24","kind":"milestone","milestone":"phase_operational","description":"Building 1 is operational, based on a lack of construction activity around the shell and cooling equipment, and about 6 months passing after structural completion.","sourceId":"epoch-ai-data-centers","evidenceLevel":"estimated","text":"New capacity online: Building 1 is operational, based on a lack of construction activity around the shell and cooling equipment, and about 6 months passing after structural completion.","url":"https://datacenters.prithvidixit.com/facilities/meta-gallatin-gallatin-tn","source":{"id":"epoch-ai-data-centers","title":"AI data centers (Frontier Data Centers Hub)","publisher":"Epoch AI","url":"https://epoch.ai/data/ai-data-centers","license":"CC BY 4.0","retrievedAt":"2026-10-12"}},{"facilityId":"epoch-meta-aiken","slug":"meta-aiken-trenton-sc","name":"Meta Aiken","state":"SC","county":"Aiken County","orgIds":["meta","dominion-energy-south-carolina-inc"],"iso":"None (non-RTO region)","utilities":["dominion-energy-south-carolina-inc"],"id":"epoch-meta-aiken:size.buildings_operational:epoch-ai-data-centers:2026-08-07","date":"2026-08-07","kind":"value","field":"size.buildings_operational","before":0,"after":1,"sourceId":"epoch-ai-data-centers","evidenceLevel":"estimated","text":"Buildings operational: 0 → 1","url":"https://datacenters.prithvidixit.com/facilities/meta-aiken-trenton-sc","source":{"id":"epoch-ai-data-centers","title":"AI data centers (Frontier Data Centers Hub)","publisher":"Epoch AI","url":"https://epoch.ai/data/ai-data-centers","license":"CC BY 4.0","retrievedAt":"2026-10-12"}},{"facilityId":"epoch-meta-aiken","slug":"meta-aiken-trenton-sc","name":"Meta Aiken","state":"SC","county":"Aiken County","orgIds":["meta","dominion-energy-south-carolina-inc"],"iso":"None (non-RTO region)","utilities":["dominion-energy-south-carolina-inc"],"id":"epoch-meta-aiken:status:epoch-ai-data-centers:2026-08-07","date":"2026-08-07","kind":"value","field":"status","before":"under_construction","after":"operating","sourceId":"epoch-ai-data-centers","evidenceLevel":"estimated","text":"Status: Under construction → Operating","url":"https://datacenters.prithvidixit.com/facilities/meta-aiken-trenton-sc","source":{"id":"epoch-ai-data-centers","title":"AI data centers (Frontier Data Centers Hub)","publisher":"Epoch AI","url":"https://epoch.ai/data/ai-data-centers","license":"CC BY 4.0","retrievedAt":"2026-10-12"}},{"facilityId":"epoch-meta-aiken","slug":"meta-aiken-trenton-sc","name":"Meta Aiken","state":"SC","county":"Aiken County","orgIds":["meta","dominion-energy-south-carolina-inc"],"iso":"None (non-RTO region)","utilities":["dominion-energy-south-carolina-inc"],"id":"epoch-meta-aiken:phase_operational:2026-08-07:epoch-ai-data-centers","date":"2026-08-07","kind":"milestone","milestone":"phase_operational","description":"Building 1 is confirmed operational via drone imagery with 8/9 group of coolers with spinning fans. Imagery also confirms all cooling and power infrastructure in place for Building 2.","sourceId":"epoch-ai-data-centers","evidenceLevel":"estimated","text":"New capacity online: Building 1 is confirmed operational via drone imagery with 8/9 group of coolers with spinning fans. Imagery also confirms all cooling and power infrastructure in place for Building 2.","url":"https://datacenters.prithvidixit.com/facilities/meta-aiken-trenton-sc","source":{"id":"epoch-ai-data-centers","title":"AI data centers (Frontier Data Centers Hub)","publisher":"Epoch AI","url":"https://epoch.ai/data/ai-data-centers","license":"CC BY 4.0","retrievedAt":"2026-10-12"}},{"facilityId":"epoch-meta-sarpy","slug":"meta-sarpy-springfield-ne","name":"Meta Sarpy","state":"NE","county":"Sarpy County","orgIds":["meta","opdp"],"iso":"SPP","utilities":["opdp"],"id":"epoch-meta-sarpy:size.buildings_operational:epoch-ai-data-centers:2026-08-02","date":"2026-08-02","kind":"value","field":"size.buildings_operational","before":0,"after":1,"sourceId":"epoch-ai-data-centers","evidenceLevel":"estimated","text":"Buildings operational: 0 → 1","url":"https://datacenters.prithvidixit.com/facilities/meta-sarpy-springfield-ne","source":{"id":"epoch-ai-data-centers","title":"AI data centers (Frontier Data Centers Hub)","publisher":"Epoch AI","url":"https://epoch.ai/data/ai-data-centers","license":"CC BY 4.0","retrievedAt":"2026-10-12"}},{"facilityId":"epoch-meta-sarpy","slug":"meta-sarpy-springfield-ne","name":"Meta Sarpy","state":"NE","county":"Sarpy County","orgIds":["meta","opdp"],"iso":"SPP","utilities":["opdp"],"id":"epoch-meta-sarpy:status:epoch-ai-data-centers:2026-08-02","date":"2026-08-02","kind":"value","field":"status","before":"under_construction","after":"operating","sourceId":"epoch-ai-data-centers","evidenceLevel":"estimated","text":"Status: Under construction → Operating","url":"https://datacenters.prithvidixit.com/facilities/meta-sarpy-springfield-ne","source":{"id":"epoch-ai-data-centers","title":"AI data centers (Frontier Data Centers Hub)","publisher":"Epoch AI","url":"https://epoch.ai/data/ai-data-centers","license":"CC BY 4.0","retrievedAt":"2026-10-12"}},{"facilityId":"epoch-meta-sarpy","slug":"meta-sarpy-springfield-ne","name":"Meta Sarpy","state":"NE","county":"Sarpy County","orgIds":["meta","opdp"],"iso":"SPP","utilities":["opdp"],"id":"epoch-meta-sarpy:phase_operational:2026-08-02:epoch-ai-data-centers","date":"2026-08-02","kind":"milestone","milestone":"phase_operational","description":"Building 1 is operational (estimate).","sourceId":"epoch-ai-data-centers","evidenceLevel":"estimated","text":"New capacity online: Building 1 is operational (estimate).","url":"https://datacenters.prithvidixit.com/facilities/meta-sarpy-springfield-ne","source":{"id":"epoch-ai-data-centers","title":"AI data centers (Frontier Data Centers Hub)","publisher":"Epoch AI","url":"https://epoch.ai/data/ai-data-centers","license":"CC BY 4.0","retrievedAt":"2026-10-12"}}],"meta":{"total":11,"limit":100,"offset":0,"dataAsOf":"2026-10-12"},"attribution":{"license":"Open Database License (ODbL) 1.0 for the compiled database; individual sources keep their own terms (see sources[].license).","credit":["© OpenStreetMap contributors (ODbL 1.0) — https://www.openstreetmap.org/copyright","Epoch AI, 'AI data centers'. Published online at epoch.ai. Retrieved from 'https://epoch.ai/data/ai-data-centers' (CC BY 4.0)","Datacenter Source — https://datacenters.prithvidixit.com"],"terms":"/api#license","note":"Every figure links to its source. MW totals are floors (most facilities don't disclose power). Evidence levels: confirmed / announced / estimated — see /sources#evidence-levels."}}